SWMS:22 – Kwik Stage Scaffolds
Safe Work Methods
H Controls / Work Methods Responsible Residual
Job Steps Potential Hazards L C R O 1. Eliminate 2. Substitute 3. Isolate 4. Engineer Person/s for Risk
C 5. Admin 6. PPE Monitor & Review L C R
C 5 E 1 Do not remove any external linings that have been Person(s) using E 5 H
Accessing and working from Kwik Contact with overhead
22 installed in the vicinity of overhead power lines Scaffold 1
stage scaffold (cont.) powerlines
where there is a risk of any part of the materials, 5
person or object entering a power line’s exclusion
zone.
Note: This is 3m minimum for low voltage, if unsure check
with site manager.
B 5 E 4 Tools are to be secured by lanyards to the person to E 4 H
Special note: Falling objects
24 minimise the risk of falling objects - if other workers 1
Installing and dismantling in high risk are at risk of injury or property damage outside the 0
areas exclusion area.
Scaffold components are to be secured by lanyards to
4 the scaffold to minimise the risk of falling objects - if
other workers are at risk of injury or property damage
outside the exclusion area.
The scaffold plan will reflect the additional tie or
5 bracing requirements for the component lanyard
connection points.
Methods for monitoring and reviewing effectiveness of chosen control measures
Hutchinson Builders & Subcontracted Personnel: Follow procedure and report Kwik stage scaffold hazards
Workers: Follow procedure and report Kwik stage scaffold hazards
Hutchinson Builders Foreman: Ensure licenced / competent persons erect Kwik stage scaffolds and regularly inspect Kwik stage scaffolds erected on
site
Monitor SWMS controls on site using the Task Observation form
584 Milton Road TOOWONG QLD 4066 SWMS Developed by: Jamie Gilbert VERSION 8 – September 2015
P: (07) 3335 5000 F: (07) 3335 5005 Position: National Health & Safety Co-ordinator Page 67
ABN: 52 009 778 330
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.