SWMS:34 – Refuelling (Plant & Equipment)
Safe Work Methods
H Controls / Work Methods Responsible Residual Risk
Job Steps Potential Hazards L C R O 1. Eliminate 2. Substitute 3. Isolate 4. Engineer Person/s for
Monitor & Review L C R
C 5. Admin 6. PPE
C 5 E 5 All persons using any hazardous good / Hutchinson Builders D 3 M
Prior to using a hazardous Failing to identify the risks
22 dangerous substance must be signed into Foreman 9
substance / dangerous good on associated with a particular
associated SWMS: 14 Hazardous goods prior to
site hazardous substance /
handling any refuelling substance.
dangerous good
C 4 E 3 Plant/ equipment are to be refuelled in a Hutchinson Builders D 4 H
Using / handling refuelling Struck by other plant
18 designated area away from other operating plant Foreman 14
substances
and equipment.
C 5 E 3 Plant to be shut down prior to refuelling. Hutchinson Builders D 4 H
Fire
22 Foreman 14
All ignition sources are to be removed from
designated refuelling area.
Ensure there are not any hot work activities
occurring in the vicinity of the refuelling area.
Fire extinguisher to be at hand (foam/dry
chemical).
C 3 H 6 Ensure all appropriate PPE equipment is in use Hutchinson Builders D 2 L5
Personal injury
13 when refuelling plant / equipment, refer to SDS Foreman
and associated SWMS.
Thoroughly wash hands, any contaminated skin or
5
clothing following refuelling.
Ensure refuel area is well ventilated, to disperse
5 any chemical fumes.
6 Ensure the onsite first aid kit has portable eye
wash canister in case of an emergency
Spills C 3 H 4 Refuel using mechanical pump or decanting drum, Hutchinson Builders D 2 L5
13 or an appropriate pour spout to refuel. Foreman
584 Milton Road TOOWONG QLD 4066 SWMS Developed by: Jamie Gilbert VERSION 7 – September 2015
P: (07) 3335 5000 F: (07) 3335 5005 Position: National Health & Safety Co-ordinator Page 152
ABN: 52 009 778 330
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.