2010/574 SPA Decision Notice [As Published] · 132010.574
2010/574
(a) any part of the approval relating to the 467 Appeals about changing or cancelling
assessment manager’s decision about conditions imposed by assessment
any part of the application requiring manager or concurrence agency
impact assessment under section 314; or (1) A person to whom a notice under section
(b) any part of the approval relating to the 378(9)(b) giving a decision to change or
assessment manager’s decision under cancel a condition of a development approval
section 327 has been given may appeal to the court
(3) The appeal must be started within 20 against the decision in the notice.
business days after the day the decision (2) The appeal must be started within 20
notice or negotiated decision notice is given business days after the day the notice of the
to the advice agency as a submitter. decision is given to the person.
(4) However, if the advice agency has given the For Building Works Only
assessment manager a notice under section 532 Appeals by applicants
339(1)(b)(ii), the advice agency may not
appeal the decision. (1) If—
465 Appeals about decisions relating to (a) a person has been given, or is entitled to
extensions for approvals be given—
(1) For a development approval given for a (i) an information notice under the
development application, a person to whom a Building Act about a decision
notice is given under section 389, other than other than a decision under
a notice for a decision under section 386(2), that Act made by the
may appeal to the court against the decision Queensland Building Services
in the notice. Authority; or
(2) The appeal must be started within 20 (ii) an information notice under the
business days after the day the notice of the Plumbing and Drainage Act
decision is given to the person. 2002 about a decision under
part 4 or 5 of that Act; or
(3) Also, a person who has made a request
under section 383 may appeal to the court (b) a person—
against a deemed refusal of the request (i) was an applicant for a building
(4) An appeal under subsection (3) may be development approval; and r
started at any time after the last day the (ii) is dissatisfied with a decision
decision on the matter should have been under the Building Act by a
made. building certifier or referral
agency about inspection of
466 Appeals about decisions relating to
building work the subject of the
permissible changes)
approval; the person may
(1) For a development approval given for a appeal against the decision to
development application, the following a building and development
persons may appeal to the court against a committee.
decision on a request to make a permissible
(2) An appeal under subsection (1) must be
change to the approval—
started within 20 business days after the day
(a) if the responsible entity for making the the person is given notice of the decision.
change is the assessment manager for (3) If—
the application—
(a) under the Building Act, a person makes
(i) the person who made the request; an application other than a building
or development application to a local
(ii) an entity that gave a notice under government; and
section 373 or a pre-request (b) the period required under that Act for the
response notice about the request
local government to decide the
(b) if the responsible entity for making the application (the decision period) has
change is a concurrence agency for the passed; and
application—the person who made the (c) the local government has not decided
request.. the application; the person may appeal
(2) The appeal must be started within 20 to a building and development
business days after the day the person is committee against the lack of the
given notice of the decision on the request decision and for the committee to decide
under section 376. the application as if it were the local
(3) Also, a person who has made a request government.
under section 369 may appeal to the court (4) An appeal under subsection (3) must be
against a deemed refusal of the request. started within 20 business days after the end
(4) An appeal under subsection (3) may be of the decision period..
started at any time after the last day the
decision on the matter should have been
made.
Page 8 of 8
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
2010/574 SPA Decision Notice [As Published]Related documentApplication case desk ↗
About this file
- File size
- 61 KB (small file)
- File type
No other editions are linked here.