STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads · OPW24/0125
Very large file (58.9 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.
Original PDF page 148, section 1. The text section number identifies this passage in the reader.
Expected Completion Date Approx. 07/2027
Hours of Operation The construction works would generally be undertaken during standard
construction hours, being:
7:00 am to 6:30 pm Monday to Friday
7:00 am to 2:00 pm Saturdays
Non works on Sunday or Public Holidays
After hours contact details will be displayed on the Woollam site entry
banner located adjacent to the vehicle and/or pedestrian site access point.
Revision History
Revision Date Amendments Reviewed By
001 22/04/24 Initial Draft CStewart
Plan Approval
This plan will be reviewed and approved by the Project Manager, Site Manager, Site HSE Adviser / Regional
HSE Coordinator and HSEQT Manager before it can be implemented.
Role Name Signature Date
HSEQT Manager: Cameron Stewart
Project Manager: Bryan Ward
Site Manager: TBA
Site HSE Adviser TBA
Regional HSE TBA
Coordinator:
Document ID: WC ENV 002 Revision: 011 Date: 20/02/2024 Owner: HSEQT Manager
Document uncontrolled if printed – Refer to Woollam Quality Management System to ensure current revision.
Environmental Management Plan / Page 4 of 18
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads.pdfRelated documentApplication case desk ↗
About this file
- File size
- 58.9 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.