STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads · OPW24/0125
Very large file (58.9 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.
Original PDF page 395, section 1. The text section number identifies this passage in the reader.
Residual
Proposed Controls Responsible
Rating
Initial
Risk
Risk
HC
Activity Hazard Person
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)
specific hazard, procedures and
prevent spread processes
of contaminants
where possible Workers EXTREME 5 All inducted personnel on the project shall be introduced to the project specific Emergency Preparedness and Response Plan. Site
unaware of Workers shall be informed of the Emergency Control Organisation team members and the location of displayed emergency contact Management
hazard details. Contract
Partners
Site
Workers not EXTREME 5 All inducted personnel shall be informed of the emergency evacuation procedure and processes including location of emergency Management
familiar with assembly point and pedestrian routes.
location of Contract Partner
assembly
point/s or
pedestrian
traffic routes
19.22 Structural Damage
Planning Activity HIGH 5 Woollam Emergency Control Organisation established. Each member shall complete the applicable training modules in ELMO. Site
planning, Management
hazard
identification, HIGH 5 Project specific Emergency Preparedness and Response Plan completed prior to work commencing on the project. Site
resourcing, and Management
implementation
of controls
Use of specific mobile crane, HIGH 5 Crane maintenance and servicing to be maintained.
equipment propping, Ensure all propping is stored appropriately, is greased and ready for use
barricading
Site
List activities in Workers EXTREME 5 All inducted personnel on the project shall be introduced to the project specific Emergency Preparedness and Response Plan. Management
procedure e.g. unfamiliar with Workers shall be informed of the Emergency Control Organisation team members and the location of displayed emergency contact
Evacuation to emergency details. Contract
route, isolate procedures and Partners
specific hazard, processes
Project Hazard/Risk Assessment / Page 153 of 160
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads.pdfRelated documentApplication case desk ↗
About this file
- File size
- 58.9 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.