Next steps
The steps planned for the next six months of the project include:
• Finalise construction contract to build reefs at 4 sites
• Finalise contract for engineering oversight of reef builds
• Construct reefs, map reefs and provide construction report to government
• Finalise contract for independent monitoring of the sites
• Undertake baseline monitoring
• Support Oyster Gardening Project activities
• Support Senior Schools Project activities with EEHub
• Support Junior Schools Project activities with NCBA
• Finalise grant to Noosa Parks Association (NPA) to undertake baseline sediment study
• Establish Tewantin demonstration project site
• Produce Summer/Autumn/Winter editions of the Noosa Oyster Chronicle
• Produce construction information package and distribute to community, respond to community queries
• Distribute seagrass report
• Review partnership arrangement
• Prepare final Annual Report – due September 2022.
38
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.