Appendix C - SDAP State Code 1

of 17

Page text shows just the words. Original shows the document exactly as it was published.

State code 1: Development in a state-controlled road
environment
Table 1.1 Development in general
 Performance outcomes                                Acceptable outcomes                            Response
 Buildings, structures, infrastructure, services and utilities
 PO1 The location of the development does not     AO1.1 Development is not located in a state-      Complies – The proposed development is well located
 create a safety hazard for users of the state-   controlled road.                                  for its intended use as a car wash being between two
 controlled road.                                                                                   (2) existing and adjoining service stations and fronting
                                                  AND                                               Elm Street. The development has been considered by
                                                                                                    Traffic Transport Plus who have prepared a Traffic
                                                     AO1.2 Development can be maintained without    Impact Assessment, which confirms the proposed
                                                     requiring access to a state-controlled road.   development will not create a safety hazard in this
                                                                                                    location (refer Attachment 3).
 PO2 The design and construction of the              No acceptable outcome is prescribed.           Complies – The design and construction of the car
 development does not adversely impact the                                                          wash and small food and drink outlet will not adversely
 structural integrity or physical condition of the                                                  impact the structural integrity or physical condition of
 state-controlled road or road transport                                                            the road given the traffic volumes are expected to be
 infrastructure.                                                                                    less than that generated by the approved shopping
                                                                                                    centre on the land (MCU18/0158). Further, will not
                                                                                                    adversely impact upon road transport infrastructure
                                                                                                    (refer Attachment 3).
 PO3 The location of the development does not        No acceptable outcome is prescribed.           Complies – The proposed development has been
 obstruct road transport infrastructure or                                                          designed for the site and will not adversely impact the
 adversely impact the operating performance of                                                      existing bus stop in Elm Street. Further, will not affect
 the state-controlled road.                                                                         the operating performance of the state-controlled road
                                                                                                    (refer Attachment 3).
 PO4 The location, placement, design and             No acceptable outcome is prescribed.           Complies – The proposed advertising signage for the
 operation of advertising devices, visible from                                                     car wash is to be integrated within the proposed built
 the state-controlled road, do not create a                                                         form and will not create a safety hazard for users of the
 safety hazard for users of the state-controlled                                                    state-controlled road (refer Elevation Drawings -
 road.                                                                                              Attachment 1)

State Development Assessment Provisions v3.0

State code 1: Development in a state-controlled road environment                                                                                   Page 1 of 17
Log in to download the original file

Appendix C - SDAP State Code 1.pdf · 236 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 16 pages

Page 2

 Performance outcomes                             Acceptable outcomes                                  Response
 PO5 The design and construction of buildings     AO5.1 Facades of buildings and structures            Complies – The design of the development including
 and structures does not create a safety hazard   fronting the state-controlled road are made of       the built form is compatible with and in keeping with the
 by distracting users of the state-controlled     non-reflective materials.                            character of the area. The building materials used will
 road.                                                                                                 not be reflective and the development will provide for
                                                  AND                                                  hooded security lighting only. The construction of the
                                                                                                       proposed buildings and other structures will be subject
                                                  AO5.2 Facades of buildings and structures do         to a construction management plan.
                                                  not direct or reflect point light sources into the
                                                  face of oncoming traffic on the state-controlled
                                                  road.

                                                  AND

                                                  AO5.3 External lighting of buildings and
                                                  structures is not directed into the face of
                                                  oncoming traffic on the state-controlled road.

                                                  AND

                                                  AO5.4 External lighting of buildings and
                                                  structures does not involve flashing or laser
                                                  lights.
 PO6 Road, pedestrian and bikeway bridges         AO6.1 Road, pedestrian and bikeway bridges           Not Applicable
 over a state-controlled road are designed and    over the state-controlled road include throw
 constructed to prevent projectiles from being    protection screens in accordance with section
 thrown onto the state-controlled road.           4.11 of the Design Criteria for Bridges and
                                                  Other Structures Manual, Department of
                                                  Transport and Main Roads, 2020.
 Landscaping
 PO7 The location of landscaping does not         AO7.1 Landscaping is not located in a state-         Complies – The landscaping for the proposed
 create a safety hazard for users of the state-   controlled road.                                     development is contained within the site and will not
 controlled road.                                                                                      affect sightlines. The development proposes
                                                  AND                                                  replacement street trees in Diamond Lane following
                                                                                                       road widening works. The development will not affect
                                                  AO7.2 Landscaping can be maintained without          the safety of users of the state-controlled road (refer
                                                  requiring access to a state-controlled road.         Attachment 6).

State Development Assessment Provisions v3.0

State code 1: Development in a state-controlled road environment                                                                                     Page 2 of 17

Page 3

 Performance outcomes                                Acceptable outcomes                                Response

                                                     AND

                                                     AO7.3 Landscaping does not block or obscure
                                                     the sight lines for vehicular access to a state-
                                                     controlled road.
 Stormwater and overland flow
 PO8 Stormwater run-off or overland flow from        No acceptable outcome is prescribed.               Complies – The proposed stormwater from the
 the development site does not create or                                                                development is to be managed on site in accordance
 exacerbate a safety hazard for users of the                                                            with the Stormwater Management Plan and will not
 state-controlled road.                                                                                 cause a safety hazard (refer Attachment 4).
 PO9 Stormwater run-off or overland flow from        No acceptable outcome is prescribed.               Complies – There is no additional stormwater runoff
 the development site does not result in a                                                              as a result of the development given the nature of the
 material worsening of the operating                                                                    use and intended water harvesting and reuse onsite
 performance of the state-controlled road or                                                            (refer Attachment 4).
 road transport infrastructure.
 PO10 Stormwater run-off or overland flow from       No acceptable outcome is prescribed.               Complies – The post-developed site will have a greatly
 the development site does not adversely impact                                                         reduced overall site stormwater volume and peak flow
 the structural integrity or physical condition of                                                      discharge than the pre-developed site (refer
 the state-controlled road or road transport                                                            Attachment 4).
 infrastructure.
 PO11 Development ensures that stormwater is         AO11.1 Development does not create any new Complies – The stormwater will discharge to the
 lawfully discharged.                                points of discharge to a state-controlled road. existing underground system in Opal Street (refer
                                                                                                     Preliminary Stormwater Layout Plan - Attachment 4).
                                                     AND

                                                     AO11.2 Development does not concentrate
                                                     flows to a state-controlled road.

                                                     AND

                                                     AO11.3 Stormwater run-off is discharged to a
                                                     lawful point of discharge.

                                                     AND

State Development Assessment Provisions v3.0

State code 1: Development in a state-controlled road environment                                                                                     Page 3 of 17

Page 4

 Performance outcomes                              Acceptable outcomes                               Response

                                                   AO11.4 Development does not worsen the
                                                   condition of an existing lawful point of
                                                   discharge to the state-controlled road.
 Flooding
 PO12 Development does not result in a             AO12.1 For all flood events up to 1% annual       Complies – The proposed development requires
 material worsening of flooding impacts within a   exceedance probability, development results       minimal earthworks and will not result in the material
 state-controlled road.                            in negligible impacts (within +/- 10mm) to        worsening of flooding impacts (refer Earthworks Plan –
                                                   existing flood levels within a state-controlled   Attachment 1).
                                                   road.

                                                   AND

                                                   AO12.2 For all flood events up to 1% annual
                                                   exceedance probability, development results
                                                   in negligible impacts (up to a 10% increase) to
                                                   existing peak velocities within a state-
                                                   controlled road.

                                                   AND

                                                   AO12.3 For all flood events up to 1% annual
                                                   exceedance probability, development results
                                                   in negligible impacts (up to a 10% increase) to
                                                   existing time of submergence of a state-
                                                   controlled road.
 Drainage Infrastructure
 PO13 Drainage infrastructure does not create a    AO13.1 Drainage infrastructure is wholly          Complies – The proposed development does not
 safety hazard for users in the state-controlled   contained within the development site, except     require additional stormwater drainage infrastructure to
 road.                                             at the lawful point of discharge.                 be provided off the site and will not create a hazard for
                                                                                                     users of the state-controlled road.
                                                   AND




State Development Assessment Provisions v3.0

State code 1: Development in a state-controlled road environment                                                                                   Page 4 of 17

Page 5

 Performance outcomes                               Acceptable outcomes                               Response
                                                    AO13.2 Drainage infrastructure can be
                                                    maintained without requiring access to a state-
                                                    controlled road.
 PO14 Drainage infrastructure associated with,      No acceptable outcome is prescribed.              Not Applicable
 or within, a state-controlled road is
 constructed, and designed to ensure the
 structural integrity and physical condition of
 existing drainage infrastructure and the
 surrounding drainage network.

Table 1.2 Vehicular access, road layout and local roads
 Performance outcomes                                 Acceptable outcomes                                 Response
 Vehicular access to a state-controlled road or within 100 metres of a state-controlled road intersection
 PO15 The location, design and operation of a      No acceptable outcome is prescribed.              Complies – The ingress to the car wash will be
 new or changed access to a state-controlled                                                         from Opal Street and egress from Diamond Lane,
 road does not compromise the safety of users of                                                     which is to be widened and will not compromise
 the state-controlled road.                                                                          the safety of users of the state-controlled road
                                                                                                     (refer Site Layout Plan - Attachment 1).


 PO16 The location, design and operation of a         No acceptable outcome is prescribed.                Complies – The existing access in Elm Street is
 new or changed access does not adversely                                                                 to be removed and reinstated removing the direct
 impact the functional requirements of the state-                                                         access to a state-controlled road, which is
 controlled road.                                                                                         beneficial for the function of the state-controlled
                                                                                                          road.
 PO17 The location, design and operation of a         No acceptable outcome is prescribed.                Complies – The location, design and operation of
 new or changed access is consistent with the                                                             the proposed development new access and
 future intent of the state-controlled road.                                                              egress points is consistent with the future intent of
                                                                                                          the state-controlled road.
 PO18 New or changed access is consistent with        No acceptable outcome is prescribed.                Complies
 the access for the relevant limited access road
 policy:
 1. LAR 1 where direct access is prohibited; or
 2. LAR 2 where access may be permitted,
     subject to assessment.
State Development Assessment Provisions v3.0

State code 1: Development in a state-controlled road environment                                                                                   Page 5 of 17

Page 6

 Performance outcomes                                 Acceptable outcomes                    Response
 PO19 New or changed access to a local road           No acceptable outcome is prescribed.   Complies – The Traffic Impact Assessment has
 within 100 metres of an intersection with a state-                                          considered the location of the access points
 controlled road does not compromise the safety                                              relevant to the intersection with the state-
 of users of the state-controlled road.                                                      controlled road and the development will not
                                                                                             compromise the safety of users (refer
                                                                                             Attachment 3).
 PO20 New or changed access to a local road         No acceptable outcome is prescribed.     Complies – The Traffic Impact Assessment has
 within 100 metres of an intersection with a state-                                          considered the impact of the development on the
 controlled road does not adversely impact on the                                            operation of state-controlled road at the
 operating performance of the intersection.                                                  intersections (refer Attachment 3).
 Public passenger transport and active transport
 PO21 Development does not compromise the           No acceptable outcome is prescribed.     Complies – The proposed development will have
 safety of users of public passenger transport                                               no impact on the operation of the existing bus
 infrastructure, public passenger services and                                               stop fronting the development in Elm Street.
 active transport infrastructure.
 PO22 Development maintains the ability for         No acceptable outcome is prescribed.     Complies
 people to access public passenger transport
 infrastructure, public passenger services and
 active transport infrastructure.
 PO23 Development does not adversely impact the No acceptable outcome is prescribed.         Complies
 operating performance of public passenger
 transport infrastructure, public passenger
 services and active transport infrastructure.
 PO24 Development does not adversely impact         No acceptable outcome is prescribed.     Complies
 the structural integrity or physical condition of
 public passenger transport infrastructure and
 active transport infrastructure.


Table 1.3 Network impacts
 Performance outcomes                                 Acceptable outcomes                    Response
 PO25 Development does not compromise the             No acceptable outcome is prescribed.   Complies – The proposed development will not
 safety of users of the state-controlled road                                                compromise the safety of the state-controlled road
 network.                                                                                    network.



State Development Assessment Provisions v3.0

State code 1: Development in a state-controlled road environment                                                                    Page 6 of 17

Page 7

 Performance outcomes                                 Acceptable outcomes                    Response
 PO26 Development ensures no net worsening of         No acceptable outcome is prescribed.   Complies – Having regard to the advice of Traffic
 the operating performance of the state-controlled                                           Transport Plus the development will have less
 road network.                                                                               impact on the surrounding road network when
                                                                                             compared to the current approval for a small
                                                                                             shopping centre (MCU18/0158) (refer
                                                                                             Attachment 3).
 PO27 Traffic movements are not directed onto a       No acceptable outcome is prescribed.   Complies – Access and egress is directed on to
 state-controlled road where they can be                                                     local roads being Opal Street and Diamond Lane,
 accommodated on the local road network.                                                     which is to be widened (refer Attachment 1).
 PO28 Development involving haulage exceeding         No acceptable outcome is prescribed.   Not Applicable
 10,000 tonnes per year does not adversely impact
 the pavement of a state-controlled road.
 PO29 Development does not impede delivery of         No acceptable outcome is prescribed.   Complies
 planned upgrades of state-controlled roads.
 PO30 Development does not impede delivery of         No acceptable outcome is prescribed.   Complies
 corridor improvements located entirely within
 the state-controlled road corridor.

Table 1.4 Filling, excavation, building foundations and retaining structures
 Performance outcomes                                 Acceptable outcomes                    Response
 PO31 Development does not create a safety            No acceptable outcome is prescribed.   Complies – The development will not create a
 hazard for users of the state-controlled road or                                            safety hazard for users of the state-controlled
 road transport infrastructure.                                                              road.
 PO32 Development does not adversely impact the       No acceptable outcome is prescribed.   Complies – The extent of earthworks on the site
 operating performance of the state-controlled                                               for the development is minimal (refer Proposed
 road.                                                                                       Cut & Fill Plan – Attachment 1).
 PO33 Development does not undermine, damage          No acceptable outcome is prescribed.   Complies
 or cause subsidence of a state-controlled road.
 PO34 Development does not cause ground water         No acceptable outcome is prescribed.   Complies
 disturbance in a state-controlled road.
 PO35 Excavation, boring, piling, blasting and fill   No acceptable outcome is prescribed.   Complies – The proposed earthworks will have
 compaction do not adversely impact the physical                                             no impact on the state-controlled road.
 condition or structural integrity of a state-
 controlled road or road transport
 infrastructure.
State Development Assessment Provisions v3.0

State code 1: Development in a state-controlled road environment                                                                   Page 7 of 17

Page 8

 Performance outcomes                                             Acceptable outcomes                                              Response
 PO36 Filling and excavation associated with the                  No acceptable outcome is prescribed.                             Complies
 construction of new or changed access do not
 compromise the operation or capacity of existing
 drainage infrastructure for a state-controlled
 road.



Table 1.5 Environmental emissions
Statutory note: Where a state-controlled road is co-located in the same transport corridor as a railway, the development should instead comply with Environmental emissions in State code 2:
Development in a railway environment.
  Performance outcomes                                            Acceptable outcomes                                             Response
  Reconfiguring a lot
  Involving the creation of 5 or fewer new residential lots adjacent to a state-controlled road or type 1 multi-modal corridor
  PO37 Development minimises free field noise       AO37.1 Development provides a noise barrier or      Not applicable
  intrusion from a state-controlled road.           earth mound which is designed, sited and
                                                    constructed:
                                                    1. to achieve the maximum free field acoustic
                                                         levels in reference table 2 (item 2.1);
                                                    2. in accordance with:
                                                          a. Chapter 7 integrated noise barrier design
                                                               of the Transport Noise Management
                                                               Code of Practice: Volume 1 (Road Traffic
                                                               Noise), Department of Transport and
                                                               Main Roads, 2013;
                                                          b. Technical Specification-MRTS15 Noise
                                                               Fences, Transport and Main Roads,
                                                               2019;
                                                          c. Technical Specification-MRTS04 General
                                                               Earthworks, Transport and Main Roads,
                                                               2020.

                                                                   OR

                                                                   AO37.2 Development achieves the maximum free
                                                                   field acoustic levels in reference table 2 (item
                                                                   2.1) by alternative noise attenuation measures
State Development Assessment Provisions v3.0

State code 1: Development in a state-controlled road environment                                                                                                                    Page 8 of 17

Page 9

 Performance outcomes                               Acceptable outcomes                                     Response
                                                     where it is not practical to provide a noise barrier
                                                     or earth mound.

                                                     OR

                                                   AO37.3 Development provides a solid gap-free
                                                   fence or other solid gap-free structure along the
                                                   full extent of the boundary closest to the state-
                                                   controlled road.
 Involving the creation of 6 or more new residential lots adjacent to a state-controlled road or type 1 multi-modal corridor
 PO38 Reconfiguring a lot minimises free field     AO38.1 Development provides noise barrier or        Not applicable
 noise intrusion from a state-controlled road.     earth mound which is designed, sited and
                                                   constructed:
                                                   1. to achieve the maximum free field acoustic
                                                        levels in reference table 2 (item 2.1);
                                                   2. in accordance with:
                                                         a. Chapter 7 integrated noise barrier design
                                                              of the Transport Noise Management
                                                              Code of Practice: Volume 1 (Road Traffic
                                                              Noise), Department of Transport and
                                                              Main Roads, 2013;
                                                         b. Technical Specification-MRTS15 Noise
                                                              Fences, Transport and Main Roads,
                                                              2019;
                                                         c. Technical Specification-MRTS04 General
                                                              Earthworks, Transport and Main Roads,
                                                              2020.

                                                     OR

                                                     AO38.2 Development achieves the maximum free
                                                     field acoustic levels in reference table 2 (item
                                                     2.1) by alternative noise attenuation measures
                                                     where it is not practical to provide a noise barrier
                                                     or earth mound.
 Material change of use (accommodation activity)

State Development Assessment Provisions v3.0

State code 1: Development in a state-controlled road environment                                                               Page 9 of 17

Page 10

 Performance outcomes                                Acceptable outcomes                                    Response
 Ground floor level requirements adjacent to a state-controlled road or type 1 multi-modal corridor
 PO39 Development minimises noise intrusion from AO39.1 Development provides a noise barrier or       Not applicable
 a state-controlled road in private open space.   earth mound which is designed, sited and
                                                  constructed:
                                                  1. to achieve the maximum free field acoustic
                                                      levels in reference table 2 (item
                                                      2.2) for private open space at the ground
                                                      floor level;
                                                  2. in accordance with:
                                                       a. Chapter 7 integrated noise barrier design
                                                             of the Transport Noise Management
                                                             Code of Practice: Volume 1 (Road Traffic
                                                             Noise), Department of Transport and
                                                             Main Roads, 2013;
                                                       b. Technical Specification-MRTS15 Noise
                                                             Fences, Transport and Main Roads,
                                                             2019;
                                                       c. Technical Specification-MRTS04 General
                                                             Earthworks, Transport and Main Roads,
                                                             2020.

                                                     OR

                                                     AO39.2 Development achieves the maximum free
                                                     field acoustic level in reference table 2 (item
                                                     2.2) for private open space by alternative noise
                                                     attenuation measures where it is not practical to
                                                     provide a noise barrier or earth mound.
 PO40 Development (excluding a relevant              AO40.1 Development (excluding a relevant                Not applicable
 residential building or relocated                   residential building or relocated building)
 building) minimises noise intrusion from a state-   provides a noise barrier or earth mound which is
 controlled road in habitable rooms at the           designed, sited and constructed:
 facade.                                             1. to achieve the maximum building façade
                                                           acoustic level in reference table 1 (item 1.1)
                                                           for habitable rooms;
                                                     2. in accordance with:

State Development Assessment Provisions v3.0

State code 1: Development in a state-controlled road environment                                                              Page 10 of 17

Page 11

 Performance outcomes                               Acceptable outcomes                                    Response
                                                          a.   Chapter 7 integrated noise barrier design
                                                               of the Transport Noise Management
                                                               Code of Practice: Volume 1 (Road Traffic
                                                               Noise), Department of Transport and
                                                               Main Roads, 2013;
                                                          b.   Technical Specification-MRTS15 Noise
                                                               Fences, Transport and Main Roads,
                                                               2019;
                                                          c.   Technical Specification-MRTS04 General
                                                               Earthworks, Transport and Main Roads,
                                                               2020.

                                                     OR

                                                     AO40.2 Development (excluding a relevant
                                                     residential building or relocated building)
                                                     achieves the maximum building façade acoustic
                                                     level in reference table 1 (item 1.1) for habitable
                                                     rooms by alternative noise attenuation
                                                     measures where it is not practical to provide a
                                                     noise barrier or earth mound.
 PO41 Habitable rooms (excluding a relevant          No acceptable outcome is provided.           Not applicable
 residential building or relocated building) are
 designed and constructed using materials to
 achieve the maximum internal acoustic level in
 reference table 3 (item 3.1).
 Above ground floor level requirements (accommodation activity) adjacent to a state-controlled road or type 1 multi-modal corridor
 PO42 Balconies, podiums, and roof decks include: No acceptable outcome is provided.              Not applicable
 1. a continuous solid gap-free structure or
     balustrade (excluding gaps required for
     drainage purposes to comply with the Building
     Code of Australia);
 2. highly acoustically absorbent material
     treatment for the total area of the soffit above
     balconies, podiums, and roof decks.


State Development Assessment Provisions v3.0

State code 1: Development in a state-controlled road environment                                                                     Page 11 of 17

Page 12

 Performance outcomes                               Acceptable outcomes                           Response
 PO43 Habitable rooms (excluding a relevant         No acceptable outcome is provided.              Not applicable
 residential building or relocated building) are
 designed and constructed using materials
 to achieve the maximum internal acoustic level in
 reference table 3 (item 3.1).
 Material change of use (other uses)
 Ground floor level requirements (childcare centre, educational establishment, hospital) adjacent to a state-controlled road or type 1 multi-modal
 corridor
 PO44 Development:                                  No acceptable outcome is provided.              Not applicable
 1. provides a noise barrier or earth mound that
      is designed, sited and constructed:
      a. to achieve the maximum free field
          acoustic level in reference table 2 (item
          2.3) for all outdoor education areas and
          outdoor play areas;
      b. in accordance with:
             i. Chapter 7 integrated noise barrier
                 design of the Transport Noise
                 Management Code of Practice:
                 Volume 1 (Road Traffic Noise),
                 Department of Transport and Main
                 Roads, 2013;
            ii. Technical Specification-MRTS15
                 Noise Fences, Transport and Main
                 Roads, 2019;
           iii. Technical Specification-MRTS04
                 General Earthworks, Transport
                 and Main Roads, 2020; or
 2. achieves the maximum free field acoustic
      level in reference table 2 (item 2.3) for all
      outdoor education areas and outdoor
      play areas by alternative noise
      attenuation measures where it is not
      practical to provide a noise barrier or earth
      mound.


State Development Assessment Provisions v3.0

State code 1: Development in a state-controlled road environment                                                                        Page 12 of 17

Page 13

 Performance outcomes                               Acceptable outcomes                           Response
 PO45 Development involving a childcare centre      No acceptable outcome is provided.
 or educational establishment:
 1. provides a noise barrier or earth mound that
      is designed, sited and constructed:
 2. to achieve the maximum building facade
      acoustic level in reference table 1 (item
      1.2);
 3. in accordance with:
      a. Chapter 7 integrated noise barrier design
          of the Transport Noise Management
          Code of Practice: Volume 1 (Road Traffic
          Noise), Department of Transport and
          Main Roads, 2013;
      b. Technical Specification-MRTS15 Noise
          Fences, Transport and Main Roads,
          2019;
      c. Technical Specification-MRTS04 General
          Earthworks, Transport and Main Roads,
          2020; or
 4. achieves the maximum building facade
      acoustic level in reference table 1 (item
      1.2) by alternative noise attenuation
      measures where it is not practical to provide
      a noise barrier or earth mound.
 PO46 Development involving:                        No acceptable outcome is provided.             Not applicable
 1. indoor education areas and indoor play
      areas; or
 2. sleeping rooms in a childcare centre; or
 3. patient care areas in a hospital achieves the
      maximum internal acoustic level in reference
      table 3 (items 3.2-3.4).
 Above ground floor level requirements (childcare centre, educational establishment, hospital) adjacent to a state-controlled road or type 1 multi-
 modal corridor
 PO47 Development involving a childcare centre      No acceptable outcome is provided.             Not applicable
 or educational establishment which have
 balconies, podiums or elevated outdoor play

State Development Assessment Provisions v3.0

State code 1: Development in a state-controlled road environment                                                                         Page 13 of 17

Page 14

 Performance outcomes                                    Acceptable outcomes                               Response
 areas predicted to exceed the maximum free
 field acoustic level in reference table 2 (item 2.3)
 due to noise from a state-controlled road are
 provided with:
 1. a continuous solid gap-free structure or
      balustrade (excluding gaps required for
      drainage purposes to comply with the Building
      Code of Australia);
 2. highly acoustically absorbent material
      treatment for the total area of the soffit above
      balconies or elevated outdoor play areas.
 PO48 Development including:                             No acceptable outcome is provided.                 Not applicable
 1. indoor education areas and indoor play
      areas in a childcare centre or educational
      establishment; or
 2. sleeping rooms in a childcare centre; or
 3. patient care areas in a hospital located
      above ground level, is designed and
      constructed to achieve the maximum internal
      acoustic level in reference table 3 (items 3.2-
      3.4).
 Air, light and vibration
 PO49 Private open space, outdoor education              AO49.1 Each dwelling or unit has access to a       Not applicable
 areas and outdoor play areas are protected              private open space which is shielded from a
 from air quality impacts from a state-controlled        state-controlled road by a building, solid gap-
 road.                                                   free fence, or other solid gap-free structure.

                                                         OR

                                                         AO49.2 Each outdoor education area and
                                                         outdoor play area is shielded from a state-
                                                         controlled road by a building, solid gap-free
                                                         fence, or other solid gap-free structure.



State Development Assessment Provisions v3.0

State code 1: Development in a state-controlled road environment                                                             Page 14 of 17

Page 15

 Performance outcomes                                 Acceptable outcomes                                 Response
 PO50 Patient care areas within hospitals are         AO50.1 Hospitals are designed and constructed
 protected from vibration impacts from a state-       to ensure vibration in the patient treatment area
 controlled road or type 1 multi-modal corridor.      does not exceed a vibration dose value of
                                                      0.1m/s1.75.

                                                      AND

                                                      AO50.2 Hospitals are designed and constructed
                                                      to ensure vibration in the ward of a patient care
                                                      area does not exceed a vibration dose value of
                                                      0.4m/s1.75.
 PO51 Development is designed and sited to            No acceptable outcomes are prescribed.               Not applicable
 ensure light from infrastructure within, and from
 users of, a state-controlled road or type 1 multi-
 modal corridor, does not:
 1. intrude into buildings during night hours (10pm
     to 6am);
 2. create unreasonable disturbance during
     evening hours (6pm to 10pm).

Table 1.6: Development in a future state-controlled road environment
 Performance outcomes                                 Acceptable outcomes                                 Response
 PO52 Development does not impede delivery of a       AO52.1 Development is not located in a future       Not applicable
 future state-controlled road.                        state-controlled road.

                                                      OR ALL OF THE FOLLOWING APPLY:

                                                      AO52.2 Development does not involve filling and
                                                      excavation of, or material changes to, a future
                                                      state-controlled road.

                                                      AND


State Development Assessment Provisions v3.0

State code 1: Development in a state-controlled road environment                                                            Page 15 of 17

Page 16

 Performance outcomes                                 Acceptable outcomes                                 Response
                                                      AO52.3 The intensification of lots does not occur
                                                      within a future state-controlled road.

                                                      AND

                                                      AO52.4 Development does not result in the
                                                      landlocking of parcels once a future state-
                                                      controlled road is delivered.
 PO53 The location and design of new or               AO53.1 Development does not include new or          Not applicable
 changed access does not create a safety hazard       changed access to a future state-controlled
 for users of a future state-controlled road.         road.
 PO54 Filling, excavation, building foundations and   No acceptable outcome is prescribed.                Not applicable
 retaining structures do not undermine, damage
 or cause subsidence of a future state-controlled
 road.
 PO55 Development does not result in a material       No acceptable outcome is prescribed.                Not applicable
 worsening of stormwater, flooding, overland flow
 or drainage impacts in a future state-controlled
 road or road transport infrastructure.
 PO56 Development ensures that stormwater is          AO56.1 Development does not create any new          Not applicable
 lawfully discharged.                                 points of discharge to a future state-controlled
                                                      road.

                                                      AND

                                                      AO56.2 Development does not concentrate flows
                                                      to a future state-controlled road.

                                                      AND

                                                      AO56.3 Stormwater run-off is discharged to a
                                                      lawful point of discharge.

                                                      AND

State Development Assessment Provisions v3.0

State code 1: Development in a state-controlled road environment                                                           Page 16 of 17

Page 17

 Performance outcomes                               Acceptable outcomes                                  Response

                                                    AO56.4 Development does not worsen the
                                                    condition of an existing lawful point of discharge
                                                    to the future state-controlled road.




State Development Assessment Provisions v3.0

State code 1: Development in a state-controlled road environment                                                    Page 17 of 17

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.