               4.     ASSESSMENT MANAGER CONDITIONS

               APPROVED PLANS
               1.     Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development. The approved plans are listed in the following table unless
                      otherwise amended by these conditions.

                         Plan No.           Rev.    Plan/Document Name                            Date

                         OW3.1              .       Operational Works: Earthworks & Piling        April 2022
                                                    Prepared by SCG

                         SW1.1              .       Operational       Works:        Stormwater April 2022
                                                    Management
                                                    Prepared by SCG

                         SW1.2              .       Operational Works: Stormwater Details         April 2022
                                                    Prepared by SCG

                         LC01               01      Landscape Concept – DA                        January 2024
                                                    Prepared by JRLD Design and Landscape
                                                    As Amended by Council

               CURRENCY PERIOD
               2.     The Currency Period for this development approval lapses if the development has not
                      substantially started by 21 February 2026, unless an application to extend the currency
                      period is approved by Council.
               PRIOR TO COMMENCEMENT OF WORKS
                      Engineering
               3.     All necessary approvals from external service providers (e.g., Unitywater) and external
                      parties on which the development works are proposed have been obtained and a copy
                      supplied to Council.
               4.     Any changes to the details associated with the supervising RPEQ or Principal Contractor
                      during construction, must be notified to council in writing within five business days of the
                      change occurring.
               5.     Any conflict between the development and an existing or proposed service must be referred
                      to the relevant service authority for determination prior to commencement of works.
               DURING CONSTRUCTION
                      Engineering
               6.     The developer must meet any costs to repair damage to any Council asset during
                      construction, where damage is a result of the development works. Damage to assets must
                      be repaired immediately where it creates a hazard to the community. In circumstances where
                      the damage does not create a hazard to the community, it must be repaired immediately on
                      completion of the works associated with the development.
               7.     All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
                      who is independent of the Developer and Principal Contractor, and they must certify that all
                      works conform to the Operational Works permit. Where municipal works are involved, such
                      confirmation must be submitted for the respective hold points prior to any site inspection by
                      Council Officers.



                                                                                                      Page 2 of 7
Document Set ID: 22822937
Version: 3, Version Date: 21/02/2024

Used in these records

About this file

File size
158 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - OPW23 0181 [As Published].pdf · 158 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.