Decision Notice - OPW24 0083 (As Published)
Prepared by Robin Russell
F314-02 A Electricity Reticulation – Residential 27 May 2024
Prepared by Robin Russell
CURRENCY PERIOD
2. The Currency Period for this development approval lapses if the development has not
substantially started by 10 September 2026, unless an application to extend the currency
period is approved by Council.
PRIOR TO COMMENCEMENT OF WORKS
Engineering
3. All necessary approvals from external service providers (e.g., Energex) and external parties
on which the development works are proposed have been obtained and a copy supplied to
Council.
4. A condition report including photographs of the frontage of the site and shared access
driveway must be completed and submitted to council at the prestart meeting / prior to any
works commencing.
5. Certificates demonstrating currency of public liability insurance and works insurance covering
the works must be submitted to Council prior to the prestart meeting.
6. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. Electrical reticulation works.
7. A preliminary Construction Management Plan must be submitted with the Operational Works
application and must address the following:
a. Traffic management during all phases of construction;
b. Adequate parking arrangements for works and deliveries;
c. appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
Devices (MUTCD); and
d. provision for safe vehicle and pedestrian access across the frontage of the site both
during daily construction and after daily construction has ceased.
8. Any changes to the details associated with the supervising RPEQ or Principal Contractor
during construction, must be notified to council in writing within five business days of the
change occurring.
9. Any conflict between the development and an existing or proposed service must be referred
to the relevant service authority for determination prior to commencement of works.
DURING CONSTRUCTION
Engineering
10. The developer must meet any costs to repair damage to any Council asset during
construction, where damage is a result of the development works. Damage to assets must
be repaired immediately where it creates a hazard to the community. In circumstances where
the damage does not create a hazard to the community, it must be repaired immediately on
completion of the works associated with the development.
11. All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
who is independent of the Developer and Principal Contractor, and they must certify that all
works conform to the Operational Works permit. Where municipal works are involved, such
confirmation must be submitted for the respective hold points prior to any site inspection by
Council Officers.
Page 2 of 9