Decision Notice - OPW24 0083 (As Published)

of 9

Page text shows just the words. Original shows the document exactly as it was published.

                                                       Prepared by Robin Russell

                           F314-02             A       Electricity Reticulation – Residential      27 May 2024
                                                       Prepared by Robin Russell

               CURRENCY PERIOD
               2.     The Currency Period for this development approval lapses if the development has not
                      substantially started by 10 September 2026, unless an application to extend the currency
                      period is approved by Council.
               PRIOR TO COMMENCEMENT OF WORKS
                      Engineering
               3.     All necessary approvals from external service providers (e.g., Energex) and external parties
                      on which the development works are proposed have been obtained and a copy supplied to
                      Council.
               4.     A condition report including photographs of the frontage of the site and shared access
                      driveway must be completed and submitted to council at the prestart meeting / prior to any
                      works commencing.
               5.     Certificates demonstrating currency of public liability insurance and works insurance covering
                      the works must be submitted to Council prior to the prestart meeting.
               6.     Council must be contacted at least 5 working days prior to any works commencing to
                      organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
                      pre-start meeting must include the relevant parties for the following aspects of the works:
                      a.      Electrical reticulation works.
               7.     A preliminary Construction Management Plan must be submitted with the Operational Works
                      application and must address the following:
                      a.      Traffic management during all phases of construction;
                      b.      Adequate parking arrangements for works and deliveries;
                      c.      appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
                              Devices (MUTCD); and
                      d.      provision for safe vehicle and pedestrian access across the frontage of the site both
                              during daily construction and after daily construction has ceased.
               8.     Any changes to the details associated with the supervising RPEQ or Principal Contractor
                      during construction, must be notified to council in writing within five business days of the
                      change occurring.
               9.     Any conflict between the development and an existing or proposed service must be referred
                      to the relevant service authority for determination prior to commencement of works.
               DURING CONSTRUCTION
                      Engineering
               10.    The developer must meet any costs to repair damage to any Council asset during
                      construction, where damage is a result of the development works. Damage to assets must
                      be repaired immediately where it creates a hazard to the community. In circumstances where
                      the damage does not create a hazard to the community, it must be repaired immediately on
                      completion of the works associated with the development.
               11.    All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
                      who is independent of the Developer and Principal Contractor, and they must certify that all
                      works conform to the Operational Works permit. Where municipal works are involved, such
                      confirmation must be submitted for the respective hold points prior to any site inspection by
                      Council Officers.


                                                                                                       Page 2 of 9
Document Set ID: 23234547
Version: 2, Version Date: 11/09/2024
Log in to download the original file

Decision Notice - OPW24 0083 (As Published).pdf · 163 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.