Council archive · source document
Delegated Report - Code - Planning OPW18 0240 · OPW18/0240
Author Monkeith Kadhum – Development Engineer Development Assessment APPLICATION DETAILS Application No. OPW18/0240 Applicant Westera Partners Pty Ltd Proposal Operational Works - Vehicle Crossover Properly Made Date 3 September 2018 Information Request Date N/A Information Response Date N/A Decision Due Date 07 November 2018 Report Completed Date 09 October 2018 Number of Submissions Not Applicable PROPERTY DETAILS Property Address 24 Arakoon Cres Sunshine Beach Qld 4567 RP Description Lot 794 RP 48111 Land Area 636 m² Existing Use of Land Vacant Land STATUTORY DETAILS SEQRP Designation Urban Footprint Locality Eastern Beaches Zone Detached Housing Overlays Biodiversity Overlay – Environmental Protection Area Natural Hazard Overlay – Slide Hazard & Acid Sulfate Soils Natural Resource Overlay – Coastal Protection Area Assessment Type Code PROPOSAL The application seeks approval for Operational Works - Vehicle Crossover. site details Background This application for non-standard driveway/crossover is related dwelling approval MCU18/0013 (.01). Site Description The site is vacant steep land in Detached Housing Zone assessment Instruments for Statutory Assessment Under the Planning Act 2016 the application must be assessed against each of the following statutory planning instruments to the extent they are relevant to the development: State Planning Policy; South East Queensland Regional Plan; Planning Regulation 2017 The Noosa Plan. The following codes from the Noosa Plan are applicable to this development: Detached House Driveways Code; Engineering Works Codes; cONSULTATION Referral Agencies Not Applicable: Comment & conclusion The proposed development generally complies with the requirements of the planning scheme and the applicable engineering standards, and does not raise any significant issues that cannot be addressed by reasonable and relevant conditions. The application is therefore recommended for approval. The report is provided in accordance with Section 63(5) of the Planning Act 2016. RECOMMENDATION With regard to Application No OPW18/0240 for Operational Works - Vehicle Crossover situated at 24 Arakoon Cres Sunshine Beach Qld 4567 and described as Lot 794 RP 48111, it is recommended the application be approved in accordance with the following details for the Decision Notice: application details Application No: OPW18/0240 Street address: 24 Arakoon Cres Sunshine Beach Qld 4567 Real property description: Lot 794 RP 48111 Planning Scheme: The Noosa Plan (8 June 2018) Decision details Council decided to issue the following type of approval: Development Permit for Operational Works - Vehicle Crossover CURRENCY PERIOD of approval The currency period for this development approval is 2 years starting the day that this development approval takes effect. assessment manager conditions APPROVED PLANS Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions. Plan No. Rev. Plan/Document Name Date Sheet 1 of 2 Project: S18/003 C - Notes & Legend, prepared by Westera Partners July 2018 Sheet 2 of 2 Project: S18/003 C - Civil Works Plan, prepared by Westera Partners July 2018 PRIOR TO CONSTRUCTION Engineering A condition report including photographs of the frontage of the site must be completed and submitted to Council at the prestart meeting. The principal contractor must have all the appropriate insurance and public liability documentation to carry out the works. The principal contractor is also responsible to ensure that any subcontractors also have the appropriate insurance and public liability documentation. Certificates demonstrating currency of public liability insurance and works insurance covering the works must be submitted to Council prior to the prestart meeting. Council must be contacted at least 5 working days prior to any works commencing to organise a prestart. The contact number to arrange a pre-start meeting is 5329 6245. The pre-start meeting must include the relevant parties for the following aspects of the works: Civil engineering works; Traffic control. A Construction Management Plan must be submitted to Council prior to the pre-start meeting and must specifically include: Traffic Management generally in accordance with the Traffic Guidance Schemes, prepared by Verifact (Ref BH18416 and dated 26/07/2018) and associated documents/amendments, to be implemented during all aspects of the construction phase and must address but not limited to the following: A Traffic Management Control Plan in accordance with Manual of Uniform Traffic Control Devices (MUTCD) detailing all temporary signage and traffic control measures prior to construction. Maintenance of safe pedestrian access across the frontage of the site both during daily construction and after daily construction has ceased. Measures to minimising impacts on traffic flows particularly during peak hours and on waste collection days. Should footpath or the service road closures be necessary to carry out construction works, the duration of closures must be minimised and Council’s Engineering Officer must be notified prior to the proposed closure and all requirements complied with. Proposed fencing to the site during the construction phase of the development Adequate parking arrangements for construction workers. No queuing of trucks is permitted on residential streets, especially prior to 7.00am. Further parked trucks must have engines turned off. Maintenance and protection of water quality and existing drainage lines through the construction site through the implementation of appropriate erosion and sediment control measures. Works programme identifying key components of the works and their respective durations. Establishment of a communication protocol with the general public, adjoining owners, emergency services and local businesses to advise of agreed construction times, impacts on traffic and services and other relevant issues. identification of complaint management procedures including: contact details for the on-site manager dispute resolution procedures Any changes to the details associated with the supervising RPEQ or Principal Contractor during construction, must be notified to council in writing within five business days of the change occurring. Any conflict between the development and an existing or proposed service must be referred to the relevant service authority for determination prior to commencement of works. DURING CONSTRUCTION Engineering The integrity and condition of any existing public or Council infrastructure and services (above ground and/or underground) must not be adversely affected by the proposed works. The developer must meet any costs to repair damage to any public and/or Council asset during construction, where damage is a result of the development works. Damage to assets must be repaired immediately where it creates a hazard to the community. In circumstances where the damage does not create a hazard to the community, it must be repaired immediately on completion of the works associated with the development. All works must be constructed and work procedure undertaken in accordance with: The approved plans/documents and conditions detailed in this Decision Notice. All relevant Noosa Council Planning Scheme Policies, standard drawings, standard specifications and guidelines. The latest version of the Healthy Waterways document “Water Sensitive Urban Design Technical Design Guidelines for South East Queensland” for all water quality devices to be constructed on site. Works within Road Reserves No removal of street trees is permitted without Council’s prior written approval. All works must match neatly with existing road and verge/footpath features. Additional works beyond the frontage may be required to provide an acceptable transition to existing road and verge profiles. In order to mitigate the potential of public liabilities due to trip and similar hazards, Council does not permit any unauthorized works within the road reserve such as steps, sleeper steppers, hazardous landscaping and the like unless specifically approved by Council. Driveways Driveway crossovers must be constructed generally in accordance with the approved plans and as directed by the supervising/certifying RPEQ and in compliance with the relevant requirements of AS 2890.1 and IPWEA Standard Drawings RS-049 and RS-050, and must : Have surface consists of either an approved hot mixed asphaltic concrete or plain/patterned concrete. Have a slip resistant surface. Be constructed so as not to concentrate stormwater runoff, increase flows or cause ponding onto neighbouring properties and road verge. Any proposed surface drainage pit or grated channel must be located wholly within the private property. Have a minimum clearance of 500mm from any Unitywater/Telstra asset, unless a written approval is obtained from Unitywater/ Telstra and submitted to Council. The property access must be located a minimum of 1m clear of any existing power poles, streetlights and/or street signage. Pavement design for privately owned works must be undertaken in accordance with the relevant standards. Structural integrity of the driveway and car park areas will remain the responsibility of the property owner/developer. Any existing unnecessary or redundant property accesses must be removed, and verge area reinstated to match the existing treatments. Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed or turf, and must be maintained by the developer until established. Environment (Erosion and Sediment Control) Prescribed Water Contaminants (as defined in the Environmental Protection Act 1994) must not be released from the site or to waters within the site, or be likely to be released should rainfall occur, unless all reasonable and practicable measures are taken to prevent or minimise the release and concentration of contamination. The contractor must ensure non-essential exposure of soil is prevented by restricting the extent of works and minimising the duration of soil exposure to adverse weather conditions. Exposed areas must be suitably covered/stabilised/reinstated as soon as practicable and prior to any predicted rainfall occurring. Erosion and sediment control measures must be installed and maintained to minimise erosion on the site and to minimise the export of sediment and associated pollutants from the site. The erosion and sediment control measures must be designed, installed and maintained in accordance with current best practice standards. FOLLOWING CONSTRUCTION Upon completion of all works (including crossover, driveway, stormwater drainage and stabilisation works) a certificate must be issued by an RPEQ certifying that the works have been constructed in accordance with the requirements of this Operational Works permit. A final inspection and approval of the new driveway and completed reinstatement works by Council’s Inspector is required. Please contact Council on 5329 6245 to arrange for the final inspection. referral agencies Not applicable. Advisory notes The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions: General Advisory Notes As this driveway is a private structure, the owner bears full responsibly for the standard of its construction, maintenance and any liabilities associated with its construction. It is recommended that professional advice be sought for the construction of the driveway to ensure that the driveway is constructed in accordance with the applicable standards. Council has undertaken an audit check of the Operational Works drawings in relations to the proposed works. A detailed check of the calculations and drawings has not been undertaken, as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of the engineering design. Council reserves the right to require further amendments and/or additions at a later date should design errors become apparent. Should any changes or modifications to the approved plans be required as a result of construction constraints, a “Request to change an existing approval” under the Planning Act 2016 must be made. Amended plans clearly indicating the changes must be lodged with this application along with the appropriate fees. Prestart Inspections Request Contact Council on 5329 6245 to arrange a prestart or an inspection giving a minimum of 5 business days notice of preferred inspection time. It should be noted prior to arranging a pre-start meeting the Appeal Period of 20 business days must have passed or the applicant must have provided Council with written confirmation that the applicant has accepted the conditions of Decision Notice and waived their appeal rights. If Council officers are required to undertake additional inspections of the same works, a reinspection fee will be applicable in accordance with Council’s Fees and Charges register applicable at the time. Environmental Advisory Notes The Environmental Protection Act 1994 states that a person must not carry out any activity that causes, or is likely to cause, environmental harm unless the person takes all reasonable and practicable measures to prevent or minimise the harm. Environmental harm includes environmental nuisance. In this regard persons and entities, involved in the civil, earthworks, construction and landscaping phases of this development are to adhere to their ‘general environmental duty’ to minimise the risk of causing environmental harm. Erosion and Sediment Control Accepted best practice standards include: the Sunshine Coast Regional Council Manual for Erosion and Sediment Control V1.2 or other superseding document subsequently adopted by Council; Best Practice Erosion and Sediment Control, International Erosion Control Association (2008). property notes Not applicable. VARIATION approval details Not applicable. further development permits required Not applicable. submissions Not applicable. RIGHTS OF APPEAL You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the Planning Act 2016 is attached. During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval. If Council agrees or agrees in part with the representations, a negotiated decision notice will be issued. Only one negotiated decision notice may be given. OTHER DETAILS If you wish to obtain more information about the decision, electronic copies are available on line at www.noosa.qld.gov.au or at Council Offices. [word/footer1.xml] Page 7 of 7 [word/header1.xml] 3 [word/header2.xml] DEVELOPMENT ASSESSMENT DELEGATED REPORT
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report - Code - Planning OPW18 0240Related documentApplication case desk ↗
About this file
- File size
- 138 KB (small file)
- File type
- DOCX
No other editions are linked here.