Information Request OPW26 0033 [As Published]
However, given the extent of vegetation clearing proposed and the importance of ensuring
that appropriate site preparation and soil conditions are established to support successful
street-tree planting, conditions 29 and 32 must be addressed as part of the current Operational
Works approval. Integrating the landscaping and covenant-area requirements at this stage will
ensure coordinated design, avoid conflicts between civil and environmental works, and
support compliance with the approved development conditions.
Information Required
13. Provide information to satisfy conditions 29 and 32, including, but not limited to:
13.1. Provide a detailed site rehabilitation management plan for the covenant area,
prepared by a suitably qualified person. The plan must outline rehabilitation
methodologies, areas of targeted regeneration planting (where required), weed
management, vegetation protection measures, and monitoring and maintenance
requirements to ensure long-term protection and ecological function of the
covenant area, giving due consideration to the ecological assessment referenced
in condition 29 of the higher order approval (RAL 19/0014).
13.2. A detailed Landscape Plan prepared by a suitably qualified person demonstrating
proposed street-tree planting and landscaping of the bioretention basin in
accordance with the Noosa Plan PSP2 Landscaping. In addition to the
requirements of higher order condition 32 (RAL19/0014) the plan must address:
• proposed species and locations
• appropriate spatial setbacks from sewer and water infrastructure,
• avoidance of conflicts with future driveway locations,
• adequate soil volumes and soil depths to support long-term tree health, and
measures to ensure the sustainable establishment and viability of all
vegetation.
Issue – vegetation retention within the road reserve
The submitted plans indicate that clearing of existing vegetation within the road verge will be
limited to the minimum necessary to undertake the proposed works. However, insufficient
information has been provided to demonstrate that a thorough assessment has been carried
out to identify vegetation that may be suitable for retention, nor have appropriate measures
been proposed to ensure the protection of such vegetation during construction.
Information Required
14. Provide an Arboricultural Impact Assessment (AIA) prepared by an AQF Level 5
qualified arborist in accordance with AS4970 Protection of trees on development sites,
including:
14.1. A site survey identifying all trees within the road reserve, including the calculation
and mapping of Tree Protection Zones (TPZ) and Structural Root Zones (SRZ) for
each tree, spatially referenced to the proposed engineering works.
14.2. Identification of trees with potential for retention, based on tree health, structure,
species, location, and anticipated construction impacts.
14.3. A detailed Tree Protection Plan, outlining all required protection measures for trees
identified for retention during all stages of the development. The plan must include
specifications for protective fencing, signage, soil-protection measures, monitoring
protocols, and any special construction techniques or root-zone management
required to minimise impacts.
Page 7 of 8
Document Set ID: 24593729
Version: 2, Version Date: 12/03/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Information Request OPW26 0033 [As Published].pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.