RFI - Attachment 3 - Stormwater Management Plan
Original PDF page 16, section 1. The text section number identifies this passage in the reader.
A summary of the results is included in Table 3.4 and showing the pre and post conditions at the nominated
locations through the drainage feature. Refer to Appendix C TUFLOW Modelling Flood for the flood maps
resulting from the modelling.
Table 3.4 – Pre and Post-Development Flood Depths and Depth Velocity
Point Existing Existing Developed Developed Existing Existing Developed Developed
ID 1% 1% 1% Critical 1% Critical 10% 10% 10% 10%
Critical Critical Depth dxV Critical Critical Critical Critical
Depth dxV Depth dxV Depth dxV
1 0.393 0.431 0.1 0.201 0.229 0.405 0 0
2 0.372 0.645 0.172 0.205 0.323 0.254 0 0
3 0.311 0.453 0.111 0.194 0.194 0.388 0 0
4 0.026 0.014 0.029 0.02 0.02 0.01 0 0
5 0.025 0.006 0 0 0 0 0 0
6 1.545 1.195 1.555 1.072 1.357 0.626 1.249 0.669
7 2.09 1.006 2.155 0.87 2.016 0.519 1.853 0.6
8 1.657 0.911 2.012 0.95 1.629 0.417 1.723 0.65
9 1.455 1.502 1.788 1.849 1.043 1.25 1.537 1.4
10 1.463 2.216 1.42 2.057 1.099 1.321 1.137 1.156
11 1.638 2.122 1.609 1.957 1.337 1.157 1.314 1.132
12 1.313 1.891 1.29 1.749 1.029 1.107 1.007 1.082
13 1.514 1.833 1.511 1.748 1.328 1.15 1.312 1.103
At the location of the culvert (POI 1 to 3), the road is now trafficable during the 1% AEP storms (depth < 0.2m and
dxV <0.3m/s² as per QUDM Table 7.4.5) and unaffected under the 10% AEP storms.
Although the culvert upgrade results in increased depth of flow upstream of the crossing, the impacts are
contained within the heavily vegetated riparian buffer zone and areas of biodiversity significance overlays where
impacts are expected to be minimal. At a location 100m upstream of the culvert, the difference from the existing
flows are negligible, and downstream of the crossing there is no worsening to existing conditions. Furthermore,
the upgraded culvert also results in an improvement to flood conditions under the 10% AEP storm event with
reduced flood depths upstream and downstream of the culvert. The proposed upgrade of the culvert is therefore
unlikely to result in changes to the upstream or downstream property owners causing additional risk of significant
nuisance or hazard beyond existing conditions.
Project number 21020 Page 16 of 36
File RECOR Concept Stormwater Management Report - 21020.docx, 2022-09-05
Revision 0
P +61 7 5211 1003 A 75 Noosa Drive, Noosa Heads Qld 4567 E [email protected] recorconsulting.com
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (RFI - Attachment 3 - Stormwater Management Plan.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.