Internal Catchment Areas for DRAINS Modelling
Project number: 21020 Calculations: B. Parry
Street Address: 55 Carpenters Road
Locality: Cooroy, Noosa Council Date: 27/07/2022
Existing Site
Existing Site Directly connected (m²) Indirectly connected (m²)
Lot 2 RP 200519 Roof 474.1 - 678.6
Impervious Ground 359.7 - 1,181.5
Road - - 750.3
Total Imp 833.8
Total Per 23,476.6
Site Area 24,310.4 - 2,610.4
% impervious Effective DCIA = 75% DCIA ICIA +25% ineffective DCIA
0 2610.4
Impervious 3.4% 0.0% 10.7%
Pervious 96.6%
Time of Concentration
Roof Drainage
Older dwelling 2.0 mins (per DRAINS recommendations)
Sheet flow (Friends Eqn.)
Length 188 m
Horton's n 0.045 Average grassed
Fall over distance 9.5 m
Slope 5.1 %
Time 20.0 mins
Total Time 22.0 mins
Proposed Site
Proposed Directly connected (m²) Indirectly connected (m²)
Lot 2 RP 200519 Roof 3,135.4 3,135.4 -
Impervious Ground 2,029.5 - 2,029.5
8878 Road 4,831.0 4,831.0 -
Total Imp 9,995.9
Total Per 14,314.5
Site Area 24,310.4 7,966.4 2,029.5
% impervious Effective DCIA = 75% DCIA ICIA +25% ineffective DCIA
5,974.8 4,021.1
41.1% 24.6% 16.5%
58.9%
Standard Inlet Time (QUDM Table 4.6.2)
Time 13.0 mins
Pipe Flow (Mannings Eqn)
Length 335 m
R (375 dia pipe) 0.1875 m
Slope 0.031 m/m
n (Manning's)
Table 9.3.4 0.013
Time 1.3 mins
Total Time 15.0 mins
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (RFI - Attachment 3 - Stormwater Management Plan.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.