5.5.4 Maintenance
For the initial maintenance of the bioretention basin it is important to remove weeds and debris,
with regular watering until plants are established and actively growing.
Watering is to be undertaken following the construction of the basin at the following frequency:
Week 1 – 6, 5 times/week
Week 6 – 10, 3 times/week
Week 11 – 15, 2 times/week
If there is no rain, each plant should receive 2.5 – 5.0 litres of water per week during establishment
in the first 6 weeks (40mm/week).
Watering requirements to sustain healthy vegetation should be determined during ongoing
maintenance visits.
Detailed establishment techniques can be found in the Water By Design Construction and
Establishment Guidelines.
Inspections are also recommended following large storm events to check for scour and other
damage.
Maintenance of the bioretention basin will include:
Routine inspections of surface profile to identify areas of sediment buildup, scour and
erosion or clogging of the filter media;
Routine inspection of the overflow pits and under drains for blockages and litter buildup;
Removal of sediment where it is smothering the basin vegetation; and
Repair all basin damage due to scour or erosion by replacement of filter media and
vegetation.
A Bioretention Basin Maintenance Checklist is attached in Appendix 4.
Detailed maintenance techniques can be found in the Water By Design Maintaining Vegetated
Assets Guideline.
5.6 Construction Phase (Sediment and Erosion Control)
5.6.1 Intent of Erosion and Sediment Control Management Plan
To prevent stormwater contamination (of watercourses) and the release of contaminated
stormwater and wastewater by ensuring compliance with the Environmental Protection Act 1994
and Environmental Protection (Water) Policy 2009.
5.6.2 Implementation Strategy
Establish control measures and best practice approaches to prevent stormwater contamination
and minimise the risk and adverse effects of erosion and sedimentation. All Erosion and Sediment
Control measures must be designed, constructed and maintained in a manner that is
commensurate with the site’s erosion risk.
Excellence with Economy in Engineering 14
https://mpncnetau.sharepoint.com/sites/administration/shared documents/8000-8999/8200-
8299/8293/reports/06-09-22 stormwater management plan_issue e.docx
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
06-09-22 Stormwater Management Plan_Issue F.pdfRelated documentApplication case desk ↗
About this file
- File size
- 14.6 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.