5.6.5 Erosion and Sediment Control Implementation Program
Licenses, permits or approvals for each environmentally relevant activity must be obtained
prior to the commencement of the particular activity.
Appropriate control measures such as sediment fences, temporary construction entry/ exit
sediment traps, pollution containment devices (e.g. sandbags), stormwater diversion and
administrative controls must be installed and established prior to commencement of the
earthworks and construction activities.
Pollution control devices such as spill control equipment must be inspected on a regular
basis (at least weekly).
Other sediment and pollution control equipment such as containment bunds, hay bales and
sediment fences must be inspected on a regular basis (at least daily).
Inspection for any leaks, spills or potential contaminating activity must be performed on a
regular basis (at least daily).
Remove accumulated sediment or other contaminants from sediment/ pollution control
devices on a regular basis.
All erosion and sediment control measures must be inspected within 24 hours of expected
rain and within 18 hours of a rainfall event.
5.6.6 Responsible Person Or Organisation
The contractor shall be responsible for the implementation and maintenance of the Erosion and
Sediment Control Measures.
5.6.7 Reporting / Review
Records such as licences, approvals, permits and inspection reports must be reviewed on a regular
basis (e.g. at least monthly) to ensure that legal compliance is met, complaints are reviewed and
systems are working to prevent contamination.
5.6.8 Corrective Actions
Perform clean-up of any spills immediately.
Any mud or sediment which is tracked onto public roads is to be immediately removed
using dry clean-up methods i.e. shovel and broom.
Remove or relocate any stockpiles of waste where there is a reasonable risk of erosion and
sedimentation.
Replace or repair sediment or pollution control devices if they are not maintained in good
working condition.
Excellence with Economy in Engineering 16
https://mpncnetau.sharepoint.com/sites/administration/shared documents/8000-8999/8200-
8299/8293/reports/06-09-22 stormwater management plan_issue e.docx
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
06-09-22 Stormwater Management Plan_Issue F.pdfRelated documentApplication case desk ↗
About this file
- File size
- 14.6 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.