OPERATIONAL PLAN 2019-20 PROGRESS REPORT
THE NOOSA COMMUNITY
No. Project Responsibility Uy ele FC SELES)
1. Continue implementation of Council’s Social Strategy Director Community Services Update on Social Strategy implementation plan presented to Council in On track @
including the Cultural Plan, Sport and Active Recreation September 2019.
Plan and Health and Wellbeing Plan
2 Undertake pre-feasibility study for a Regional Art Gallery Director Community Services Analysis of current Regional Gallery complete. Brief for consultant drafted. On track @
3 Complete a major refurbishment of the Noosa Aquatic Community Facilities Manager Refurbishment of Noosa Aquatic Centre complete and centre re-opened to Completed @
Centre public
4 Commence construction of the new Peregian Beach Director Community Services Tender process for construction of new Community House, carparking and On track @
Community House landscaping complete - report to award contract to be considered in October
Council meetings
5 Complete Stage 1 of the Noosa North Shore Director Corporate Services Redevelopment works underway with completion expected by December On track @
Campground redevelopment 2019.
6 — Review options for mobile/ outreach library services Libraries & Galleries Manager Options for replacement scoped and assessed. Report to be considered by On track @
Council in November/December 2019.
7 Adoption of Master Plans for the Noosa District Sports Community Development Manager Consultation with each sport complex user group undertaken. Draft to be On track @
Complex and the Cooroy Sports Complex finalised and presented to Council by end of 2019.
8 Complete replacement of the Noosa Botanic Gardens Director Infrastructure Services Construction of the structure is complete. Landscaping and irrigation to On track g
Shade House commence.
Page 120 of 129See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.