                              i.       a video inspection of the defined route; and
                              ii.      an itemised list of each existing defect.
                      d.      Construction/Traffic Management during all aspects of the construct phase including:
                              i.       A Parking Management Plan for construction workers
                              ii.      A waste collection/haulage conflict management plan prepared in collaboration
                                       with Noosa Council’s Waste Team identifying waste collection times and haulage
                                       schedules designed to avoid traffic conflicts.
                              iii.     A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
                                       Control Devices (MUTCD) detailing all temporary signage and traffic control
                                       measures prior to construction.
                              iv.      Restricting on-street car parking to facilitate safe turning widths for HV’s.
                              v.       Maintenance of safe vehicle and pedestrian access across the frontage of the
                                       site both during daily construction and after daily construction has ceased.
                              vi.      Proposed fencing to the site during the construction phase of the development.
                      e.      Maintenance and protection of water quality and existing drainage lines through the
                              construction site through the implementation of appropriate erosion and sediment
                              control measures.
                      f.      Works programme identifying key components of the works and their respective
                              durations.
                      g.      Establishment of a communication protocol in the form of an information and response
                              website, and correspondence to adjoining owners, emergency services and local
                              businesses to advise of agreed construction times, impacts on traffic and services and
                              other relevant issues.
                      h.      Include a post out to the local residents and businesses along the haulage route from
                              the Serenity Close cul-de-sac to the Leslie/Noosa Drive bridge advising of the
                              proposed development including the expected time frames and the site contact details.
                      i.      Include signage in prominent locations on the boundaries of the site advising of the
                              proposed development, the expected time frames and the site contact details.
                      j.      identification of complaint management procedures including:
                              i.       contact details for the on-site manager.
                              ii.      dispute resolution procedures.
                      k.      details on the location of external fill/dump sites/sources, the haulage route, type of
                              vehicle to be utilised during filling operations and frequency of usage. Note any
                              damage to the existing road system as a result of haulage operations shall be fully
                              repaired at the applicant’s expense.
               12.    All works must be carried out in accordance with a site specific Geotechnical Report prepared
                      by a qualified person* and endorsed prior to a prestart meeting.
                      *(Refer to Advisory Note)
               13.    Prior to the commencement of municipal works associated with this development, Council
                      requires the provision of a bank guarantee, or a cash bond, of not less than 10% (minimum
                      of $5000) of the value of the municipal works.
               14.    Any changes to the details associated with the supervising RPEQ or Principal Contractor
                      during construction, must be notified to council in writing within five business days of the
                      change occurring.
               15.    Any conflict between the development and an existing or proposed service must be referred
                      to the relevant service authority for determination prior to commencement of works.



                                                                                                             Page 5 of 15
Document Set ID: 24555245
Version: 3, Version Date: 23/02/2026

Used in these records

About this file

File size
198 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Minor Change Existing Approval OPW25 0042 02 (As Published).pdf · 198 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.