Council archive · source document
Delegated Report - Code - Planning OPW26 0085 (As Published) · OPW26/0085
c. the latest version of the Healthy Waterways document “Water Sensitive Urban Design
Technical Design Guidelines for South East Queensland” for all water quality devices
to be constructed on site.
Works within Road Reserves
12. No removal of street trees is permitted without Council’s prior written approval.
13. Safe pedestrian access on all streets in the vicinity of the development must be maintained
at all times. Should footpath/road closures be necessary to carry out construction works,
Council’s Engineering Officer must be notified prior to the proposed closure and all
requirements complied with.
14. All works must match neatly with existing road and verge/footpath features. Additional works
beyond the frontage may be required to provide an acceptable transition to existing road and
verge/footpath profiles.
Driveways
15. Driveway crossovers must be constructed generally in accordance Council’s Standard
Drawings RS-056, RS-056.1 and any associated addendum.
16. Any existing unnecessary or redundant property accesses must be removed, and the kerb,
footpath and verge area reinstated to match the existing footpath and/or verge treatments.
Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed
or turf, and must be maintained by the developer until established.
17. The following must be complied with during the construction of the required
crossover/driveway:
a. the driveway surfacing must consist of either an approved hot mixed asphaltic concrete
or patterned/plain concrete.
b. the driveway must be in accordance with the requirements of AS2890.1 Off-Street Car
Parking for longitudinal and crossfall gradients.
c. the driveway must be constructed so as to not concentrate or direct stormwater runoff
onto neighbouring properties
d. underground service conduits for water supply, electricity and any other services must
be provided as part of the access driveway
e. where there is an existing pedestrian path, a matching crossfall must be provided for
the driveway on the alignment of the path, for the full width of the path
f. have a minimum clearance of 500mm from any Unitywater/Energex/Telstra asset,
unless a written approval is obtained from Unitywater/Energex/Telstra and submitted
to Council.
g. any stormwater kerb outlet in close proximity to the edge of the new driveway must be
provided with an approved kerb adaptor
h. any existing kerb sections requiring removal due to the works must be saw-cut and
removed to allow for a smooth and neat finish with the new driveway
18. Pavement design for privately owned works must be undertaken in accordance with the
relevant standards. Structural integrity of the driveway and car park areas will remain the
responsibility of the property owner/developer.
Stormwater Drainage
19. The constructed driveway must not cause additional ponding on the road formation or the
road reserve.
Page 6 of 9
Document Set ID: 25065708
Version: 6, Version Date: 03/09/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report - Code - Planning OPW26 0085 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 4.0 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.