Delegated Report - Code - Planning OPW26 0033 (As Published)

of 27
               DEVELOPMENT ASSESSMENT DELEGATED REPORT

               Author                  Senior Development Engineer, Daniel Epps
                                       Development Assessment



                    APPLICATION DETAILS

                    Application No.                OPW26/0033

                    Applicant                      Surveyor Pty Ltd

                    Proposal                       Operational Works - Drainage Works, Earthworks, Roadworks,
                                                   Stormwater, Clearing Vegetation under planning scheme

                    Properly Made Date             13 February 2026

                    Information Request Date       12 March 2026

                    Information Response Date      16 June 2026

                    Decision Due Date              10 August 2026

                    Report Reviewed &              Will Lowe – 7 August 2026
                    Finalised By


                    PROPERTY DETAILS

                    Property Address               30 Pottery St Pomona Qld 4568

                    RP Description                 Lot 496 MCH 591

                    Land Area                      20230.000 m²

                    Existing Use of Land           Residential (Dwelling House)


                    STATUTORY DETAILS

                    SEQRP Designation              Urban Footprint

                    Zone                           Rural Resident

                    Precinct                       Not applicable

                    Local Plan Area                Hinterland Villages

                    Overlays                       Biodiversity, Waterways and Wetlands Overlay, Bushfire
                                                   Hazard, Koala Habitat Area

                    Assessment Type                Code

               1.      PROPOSAL
               The application seeks approval for Operational Works - Drainage Works, Earthworks, Roadworks,
               Stormwater, Clearing Vegetation under planning scheme.



Document Set ID: 25027781
Version: 3, Version Date: 13/08/2026

Log in to download the original (Delegated Report - Code - Planning OPW26 0033 (As Published).pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 26 pages

Page 2

               The locality and proposal plan are included below.




                                                      Figure 1 – Locality




                                                      Figure 2 – Site Plan




                                                                             Page 2 of 27

Document Set ID: 25027781
Version: 3, Version Date: 13/08/2026

Page 3

               2.     SITE DETAILS
               2.1. Site History
               This application relates to higher-order approval for reconfiguration of a lot (application ref:
               RAL19/0014), lodged with Council 20 May 2019 and deemed properly made under the Noosa Plan
               2006.
               The proposal sought to subdivide the existing 2ha site into nine (9) residential lots, including the
               construction of a new local access road (cul-de-sac) and the establishment of a vegetation
               covenant over the rear portion of proposed Lot 8 (Figure 3).




                                       Figure 3 – Approved subdivision plan (RAL19/0014)
               At the time the application was made the site was located within the Mary River Catchment locality
               and zoned Detached Housing, the application was subject to code assessment. The zoning of the
               site and surrounding area is shown in Figure 4.




                                             Figure 4 – Noosa Plan 2006 zoning map


                                                                                                     Page 3 of 27

Document Set ID: 25027781
Version: 3, Version Date: 13/08/2026

Page 4

               The application assessed in accordance with the applicable statutory instruments of the time and
               approval granted on 27 October 2021.
               2.2. Site Description
               The site is densely vegetated and generally grades towards the south.
               2.3. Surrounding Land Uses
               The adjoining land is zoned low density and rural residential.
               3.     ASSESSMENT
               3.1. Instruments for Statutory Assessment
               Under the Planning Act 2016 the application must be assessed against each of the following
               statutory planning instruments to the extent they are relevant to the development:
               •      State Planning Policy;
               •      South East Queensland Regional Plan;
               •      Planning Regulation 2017; and
               •      Noosa Plan 2020 (26 September 2025).
               3.2. Noosa Plan 2020
               The following codes from the Noosa Plan 2020 are applicable to this development:
               •      Works Codes
               The application has been found to generally comply with all applicable statutory instruments. The
               pertinent issues arising out of the assessment are discussed below:
               External Works
               The external works to Pottery Street and the Pottery / Red Street intersection is consistent with the
               higher order approval. The design was referred to Infrastructure Services for discussion where
               some minor alterations to the location of a pram ramp and asphalt alignment were requested.
               As part of the proposal, the existing, unformed secondary driveway servicing Lot 1 of RP71117 is
               to be impacted due to the reshaping of the road shoulder. The applicant has indicated that this
               driveway crossover will be reconstructed. Council records suggest this driveway hasn’t been
               approved by Council. Council does not oppose these works but recognise that this application is
               the wrong application type to have that secondary driveway approved.
               New Road
               The proposed new road remains consistent with the higher order approval and complies with the
               requirements of Planning Scheme Policy 6.
               Access to Proposed Lots
               Access is provided to Lots 6 – 9 in accordance with the higher order approval.
               The higher order approval did not specify that proposed Lots 1 – 5 were to be provided with a
               driveway crossover prior to Council signing the Plan of Survey.
               Earthworks
               The proposed earthworks incudes a cut-to-fill strategy that sees 2,373m3 of earth cut and filled
               across 2,397m3 of the site. The balance indicates that ~25m3 of material will need to be imported
               into the site.
               The works are generally consistent with the higher order approval and have been designed by a
               RPEQ.
               Stormwater



                                                                                                      Page 4 of 27

Document Set ID: 25027781
Version: 3, Version Date: 13/08/2026

Page 5

               The proposed stormwater works are consistent with the higher order approval and includes inter-
               allotment drainage, road drainage infrastructure, a bioretention basin and the improvement of the
               roadside drainage south down Pottery Street.
               The bioretention basin satisfies the requirements of Water by Design and other relevant industry
               standards and includes a lockable maintenance access.
               It is recommended that the bioretention basin is constructed with a sacrificial turf layer while
               construction of the future dwellings occur and is planted after 24 months or when dwellings have
               been constructed on 80% of the lots.
               Summary
               Engineering and Environment is satisfied that the proposed application satisfies the higher order
               approval, relevant provisions of The Noosa Plan 2020 and recommend the following conditions.
               4.      CONSULTATION
               4.1. Referral Agencies
               Not Applicable
               4.2. Internal Council Referrals
               The application was forwarded to the following internal Council officers for review and/or comment:
               •       Senior Environment Officer, Development Assessment:
                       Biodiversity / Vegetation Overlays
                       The higher order was assessed and approved under superseded Planning Scheme (Noosa
                       Plan 2006). At that time, the property was mapped as ‘Environmental Enhancement Area’
                       (see Figure 5). The site is largely vegetated, with the exception of the existing house site.
                       The site identified under the current Biodiversity Waterways and Wetlands Overlay (Noosa
                       Plan 2026) (see Figure 6).




                    Figure 5 – Biodiversity Overlay – Noosa Plan       Figure 6 – Biodiversity, Waterways and
                                        2006                          Wetlands Overlay Code – Noosa Plan 2020

                       Koala Habitat Area in SEQ
                       Changes to Queensland's planning and koala regulations, introduced in February 2020
                       alongside the South East Queensland Koala Conservation Strategy 2020–2025, established


                                                                                                      Page 5 of 27

Document Set ID: 25027781
Version: 3, Version Date: 13/08/2026

Page 6

                      new protections across the region. These reforms restricted land clearing and mandated
                      state-level assessment for development in designated koala habitats.
                      Under the current koala regulation and associated mapping, the site is identified as a Koala
                      Priority Area and Core Koala Habitat (Figure 7). Any vegetation clearing would be considered
                      Prohibited Development unless exempt.




                                                    Figure 7 – SEQ KHA mapping

                      The South East Queensland (SEQ) koala habitat framework includes transitional
                      arrangements that protect existing development rights. Relevant provisions include:
                           •    Development applications that were properly made before 7 February 2020 are
                                generally assessed against the planning provisions that applied at the time the
                                application was lodged.
                           •    Clearing within koala habitat is generally exempt where it is authorised under a
                                development approval (including a preliminary approval) granted for an application
                                that was properly made before 7 February 2020.
                      The proposed works affecting koala habitat are considered exempt under these transitional
                      arrangements, as the original development application was properly made prior to the
                      commencement of the current koala habitat regulations.
                      A Koala Survey Report prepared by OWAD Environment (dated 6 October 2019), was
                      submitted as part of the reconfiguration application (RAL19/0014). The survey utilised two
                      professionally trained koala detection dogs and found no evidence of koalas residing on, or
                      visiting, the site within at least the previous six months. The report also concluded that the
                      proposed vegetation protection covenant would ensure the ongoing protection of any koala
                      food trees within the covenant area in perpetuity.
                      Assessment
                      The application was lodged in 2019 under the now superseded Noosa Plan 2006 and is
                      therefore assessed under that Planning Scheme.
                      The proposed vegetation clearing is consistent with that assessed in the higher order
                      approval (RAL19/0014). Pertinent matters of the higher order approval conditions considered
                      in the assessment of this application are outlined in Table 1.




                                                                                                      Page 6 of 27

Document Set ID: 25027781
Version: 3, Version Date: 13/08/2026

Page 7

                                       Table 1 – Compliance with higher order conditions of approval

                Condition       Description                               Information submitted with OPW           Satisfactorily
                                                                          application                              addressed

                1               Approved plans                            Vegetation clearing plan consistent           Yes
                                                                          with the higher order approved
                                                                          plans

                25              The development must be carried out       The application material included:            Yes
                                generally in accordance with Bushfire
                                                                          The fire trail and easement is
                                Hazard         Assessment       and
                                                                          identified on a scaled ‘Tree
                                Management Plan v2 prepared by
                                                                          Location Survey’ (Plan No. 3365
                                North Coast Environmental Services
                                                                          APZ, Cadastral & Engineering
                                dated June 2021, and items a-f
                                                                          Surveying Consultant) as required
                                outlined.
                                                                          by condition 25(fiii).
                                                                          A Vegetation Management Plan
                                                                          (North    Coast      Environmental
                                                                          Services,     27/05/2026)        was
                                                                          submitted identifying all trees within
                                                                          the APZ which are required to be
                                                                          removed and those to be retained,
                                                                          to comply with 25(fvi).

                28              “No-clearing   zones”    must       be    “No-clearing zones” are nominated             Yes
                                established and maintained                on the Landscape Design &
                                                                          Rehabilitation Management Plan,
                                                                          prepared        by       Florafied
                                                                          Environmental Design (3 July
                                                                          2026)

                29              The vegetation protection covenant        A     Landscape     Design      &             Yes
                                land area identified for rehabilitation   Rehabilitation Management Plan,
                                within a Covenant Area Management         prepared        by      Florafied
                                Plan (or similar) and associated          Environmental Design (3 July
                                Bushland Rehabilitation Program           2026) was submitted with the
                                prepared by a qualified person* as        application.
                                per the referenced Ecological
                                Assessment Report (February 2017
                                v2 North Coast Environmental
                                Services) must be provided and
                                endorsed through an Operational
                                Works approval and must include
                                areas for rehabilitation and the
                                removal of all weed species

                31              Fencing to protected land                 The requirement for fencing in                Yes
                                                                          accordance with the higher order is
                                                                          specified   in   the   Vegetation
                                                                          Covenant Area – Rehabilitation
                                                                          Management Plan (Florafied, 3
                                                                          July 2026).

                32              The development site must be              A Landscape Plan was submitted                Yes
                                landscaped. The works must be             to address the requirements of
                                undertaken in accordance with an          condition 32 of the higher order.
                                Operational Works approval and The        See     Landscape    Design    &
                                Noosa Plan and Planning Scheme            Rehabilitation Management Plan
                                Policy 3 Landscaping Plants and           (Sheet LD-02).



                                                                                                                   Page 7 of 27

Document Set ID: 25027781
Version: 3, Version Date: 13/08/2026

Page 8

                                Guidelines for that specific area and
                                must include in particular:
                                       a. provision of 1 x 45 litre pot size
                                            street tree within the road
                                            reserve for every 5 metres of
                                            road frontage suitably located
                                            for sight lines; and
                                       b. control of all weeds species
                                            listed    in    the    following
                                            standards and legislation:
                                       i. declared plants under the Land
                                                 Protection (Biodiversity
                                                 Act 2014 and sub-
                                                 ordinate        Regulation
                                                 2016).
                                       ii. Noosa Local Government Area
                                                 Pest Management Plan
                                                 2015-2019.
                                       iii.Undesirable Species as listed
                                                 in Planning Scheme
                                                 Policy 3 Landscaping
                                                 Plants and Guidelines.



                35              Fauna Management – vegetation                  A Fauna Management Plan,            Yes. Several
                                must only be removed in accordance             prepared by Equilibrium Ecology     additional
                                with a Fauna Management Plan                   (dated 16 Jan 2025) was submitted   conditions are
                                prepared by a qualified person                 with the application.               proposed to
                                                                                                                   ensure
                                                                                                                   adequate
                                                                                                                   measures to
                                                                                                                   mitigate any
                                                                                                                   impacts     to
                                                                                                                   fauna.

                      Vegetation clearing
                      The proposed vegetation clearing footprint is consistent with the higher order approval
                      development layout, to accommodate building envelopes and asset protection areas. Lots 1-
                      6 involves complete clearance. Lots 7-9 identify trees for retention within the asset protection
                      zones.
                      Vegetation protection and retention
                      The application material includes a Tree Protection Plan (sheets 1-2 of 2), prepared by TOD
                      Consulting Engineers. This plan identifies ‘no clearing zones,’ to be excluded from access.
                      As part of this application process, 5 trees (tree no. 1, 2, 22, 23 and 24) are identified for
                      retention within lots 7 and 9.
                      Covenant Area Management Plan
                      The application includes a Landscape Design & Rehabilitation Management Plan, prepared
                      by outlines measures to for the establishment and maintenance of the covenant area,
                      including weed treatment, planting and maintenance works.
                      Fauna management
                      A Fauna Management Plan, prepared by Equilibrium Ecology, dated 16 Jan 2025 was
                      submitted as part of the application material to address the requirement of condition 35 of
                      the higher order. The Fauna Management Plan prescribes measures to manage fauna prior
                      to and during vegetation clearing.


                                                                                                                   Page 8 of 27

Document Set ID: 25027781
Version: 3, Version Date: 13/08/2026

Page 9

                       Several additional measures have been identified to ensure best practice. A condition is
                       included to incorporate these measures into the Fauna Management Plan, to be submitted
                       to Council for endorsement prior to clearing.
               5.      CONCLUSION & REASONS FOR DECISION
               The proposed development generally complies with the requirements of the planning scheme and
               does not raise any significant issues that cannot be addressed by reasonable and relevant
               conditions. The application is therefore recommended for approval.
               The report is provided in accordance with Section 63(5) of the Planning Act 2016.
               RECOMMENDATION
               With regard to Application No OPW26/0033 for Operational Works - Drainage Works, Earthworks,
               Roadworks, Stormwater, Clearing Vegetation under planning scheme situated at 30 Pottery St
               Pomona Qld 4568 and described as Lot 496 MCH 591, it is recommended the application be
               approved in accordance with the following details for the Decision Notice:
               1.      APPLICATION DETAILS

                   Application No:                  OPW26/0033

                   Street address:                  30 Pottery St Pomona Qld 4568

                   Real property description:       Lot 496 MCH 591

                   Planning Scheme:                 Noosa Plan 2020 (26 September 2025)

               2.      DECISION DETAILS

               Council decided to issue the following type of approval:
               •       Development Permit for Operational Works - Drainage Works, Earthworks, Roadworks,
                       Stormwater, Clearing Vegetation under planning scheme
               3.      CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.
               4.      ASSESSMENT MANAGER CONDITIONS

               APPROVED PLANS
               1.      Development undertaken in accordance with this approval must generally comply with the
                       approved plans of development. Where there are inconsistencies between the approved plan
                       and the conditions of the approval, the conditions of the approval override the approved
                       plans.
                       The approved plans are listed in the following table unless otherwise amended by these
                       conditions.

                          Plan No.              Rev.     Plan/Document Name                       Date

                          -                     1        Fauna Management Plan, prepared by 16   January
                                                         Equilibrium Ecology                2025

                          J000864               -        Vegetation Management Plan for APZ / Fire 27 May 2026
                                                         Break Trail Tree Retention
                                                         Prepared by North Coast Environmental
                                                         Services


                                                                                                      Page 9 of 27

Document Set ID: 25027781
Version: 3, Version Date: 13/08/2026

Page 10

                         19660-C100    B   Earthworks, Clearing and Preliminary ESC 16 June 2026
                                           Control Plan – Sheet 1 of 2
                                           Prepared by TOD Consulting Engineers
                                           As Annotated by Council

                         19660-C101    B   Earthworks, Clearing and Preliminary ESC 16 June 2026
                                           Control Plan – Sheet 2 of 2
                                           Prepared by TOD Consulting Engineers
                                           As Annotated by Council

                         19660-C110    A   Tree Protection Plan – Sheet 1 of 2           16 June 2026
                                           Prepared by TOD Consulting Engineers

                         19660-C111    A   Tree Protection Plan – Sheet 2 of 2           16 June 2026
                                           Prepared by TOD Consulting Engineers

                         19660-C200    B   Roadworks and Drainage Plan – Sheet 1 of 16 June 2026
                                           2
                                           Prepared by TOD Consulting Engineers
                                           As Annotated by Council

                         19660-C201    C   Roadworks and Drainage Plan – Sheet 2 of 16 June 2026
                                           2
                                           Prepared by TOD Consulting Engineers

                         19660-C202    B   Road Longitudinal      Sections,      Typical 16 June 2026
                                           Sections & Details
                                           Prepared by TOD Consulting Engineers

                         19660-C203    B   Typical Sections & Details                    16 June 2026
                                           Prepared by TOD Consulting Engineers

                         19660-C204    B   Road Cross Sections Road 1                    16 June 2026
                                           Prepared by TOD Consulting Engineers

                         19660-C205    B   Road Cross Sections Pottery Street            16 June 2026
                                           Prepared by TOD Consulting Engineers

                         19660-C300    B   Stormwater Drainage Longitudinal Sections     16 June 2026
                                           Prepared by TOD Consulting Engineers

                         19660-C301    B   Stormwater Bioretention Basin Details         16 June 2026
                                           Prepared by TOD Consulting Engineers

                         19660-CLC     B   Stormwater Drainage Catchment Plan & 16 June 2026
                                           Calculations
                                           Prepared by TOD Consulting Engineers



                                                                                          Page 10 of 27

Document Set ID: 25027781
Version: 3, Version Date: 13/08/2026

Page 11

                           LD-01              A      Landscape  Design    &    Rehabilitation 3 July 2026
                                                     Management Plan – Cover Sheet
                                                     Prepared    by    Florafield       Environmental
                                                     Design

                           LD-02              A      Landscape  Design    &   Rehabilitation 3 July 2026
                                                     Management Plan – Landscape Design
                                                     Prepared    by    Florafield       Environmental
                                                     Design

                           LD-03              A      Landscape  Design    &     Rehabilitation 3 July 2026
                                                     Management Plan – Specification Notes
                                                     Prepared    by    Florafield       Environmental
                                                     Design

                           LD-04              A      Landscape     Design      &        Rehabilitation 3 July 2026
                                                     Management       Plan          –     Landscape
                                                     Construction Details
                                                     Prepared    by    Florafield       Environmental
                                                     Design

                           LD-05              A      Landscape     Design     & Rehabilitation 3 July 2026
                                                     Management Plan – Vegetation Covenant
                                                     Area - Rehabilitation Plan
                                                     Prepared    by    Florafield       Environmental
                                                     Design

                           LD-06              A      Landscape  Design         &        Rehabilitation 3 July 2026
                                                     Management Plan
                                                     Prepared    by    Florafield       Environmental
                                                     Design

                           LD-07              A      Landscape  Design         &        Rehabilitation 3 July 2026
                                                     Management Plan
                                                     Prepared    by    Florafield       Environmental
                                                     Design

               CURRENCY PERIOD
               2.     The Currency Period for this development approval lapses if the development has not
                      substantially started by 13 August 2028, unless an application to extend the currency period
                      is approved by Council.
               SITE SPECIFIC CONDITIONS
                      Erosion and Sediment Control Plans
               3.     Submit a site-specific Erosion and Sediment Control Plan in accordance with the
                      International Erosion Control Association’s (IECA) Best Practice Erosion and Sediment
                      Control and prepared by a suitably qualified person (RPEQ and/or CPESC). The Plan must
                      be submitted prior to the commencement of works.
               4.     Prior to the commencement of bulk earthworks:
                      a.      a hold-point inspection is required with a Council delegate to review that the erosion
                              and sediment controls on-site generally reflect the Erosion and Sediment Control Plan.

                                                                                                        Page 11 of 27

Document Set ID: 25027781
Version: 3, Version Date: 13/08/2026

Page 12

                      b.      certification from a suitably qualified person (RPEQ and/or CPESC) must be submitted
                              to Council certifying that the erosion and sediment controls on site have been installed
                              in accordance with the Plan and IECA’s Best Practice Erosion and Sediment Control.
               PRIOR TO COMMENCEMENT OF WORKS
                      Engineering
               5.     Council must be contacted at least 5 working days prior to any works commencing to
                      organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
                      pre-start meeting must include the relevant parties for the following aspects of the works:
                      a.      civil engineering works;
                      b.      arboreal (tree) works;
                      c.      fauna management works;
                      d.      landscape works;
                      e.      rehabilitation works;
                      f.      erosion and sediment control works; and
                      g.      other relevant parties.
               6.     Prior to requesting a prestart meeting:
                      a.      Tree protection fencing must be installed under the supervision of the qualified person*.
                              (Refer to Retention of Existing Trees conditions).
                      b.      Pre-clearance surveys and habitat assessment required by the approved Fauna
                              Management Plan and conditions of this Decision Notice, must be undertaken (Refer
                              to Fauna Management conditions).
               7.     Submit a copy of the approved plans that are issued “For Construction” and duly signed by
                      the consultant Registered Professional Engineer of Queensland (RPEQ). Plans must be
                      submitted and approved by Council prior to the pre-start meeting.
               8.     Submit certificates demonstrating currency of public liability insurance and works insurance
                      covering the works. Certificates must be submitted to Council prior to the pre-start meeting.
               9.     Submit a condition report documenting any existing defects in the road reserve or
                      infrastructure, including photographs of the site frontage. The report must be submitted to
                      Council prior to the pre-start meeting.
               10.    Submit a Construction Management Plan to Council prior to the pre-start meeting. The
                      Construction Management Plan must specifically address the following:
                      a.      traffic management during all aspects of the construct phase including:
                              i.       a Traffic Management Plan in accordance with Manual of Uniform Traffic Control
                                       Devices (MUTCD) detailing all temporary signage and traffic control measures
                                       prior to construction;
                              ii.      maintenance of safe vehicle and pedestrian access across the frontage of the
                                       site both during daily construction and after daily construction has ceased;
                              iii.     proposed fencing to the site during the construction phase of the development;
                              iv.      adequate parking arrangements for construction workers and deliveries; and
                              v.       no queuing of trucks is permitted on residential streets;
                      b.      maintenance and protection of water quality and existing drainage lines through the
                              construction site through the implementation of appropriate erosion and sediment
                              control measures;
                      c.      works programme identifying key components of the works and their respective
                              durations;

                                                                                                        Page 12 of 27

Document Set ID: 25027781
Version: 3, Version Date: 13/08/2026

Page 13

                      d.      establishment of a communication protocol with the general public, adjoining owners,
                              emergency services and local businesses to advise of agreed construction times,
                              impacts on traffic and services and other relevant issues;
                      e.      include a post out to the local residents and businesses advising of the proposed
                              development, the expected time frames and the site contact details;
                      f.      include signage in prominent locations on the boundaries of the site advising of the
                              proposed development, the expected time frames and the site contact details;
                      g.      identification of complaint management procedures including:
                              i.       contact details for the on-site manager; and
                              ii.      dispute resolution procedures.
                      h.      details on the location of external fill/dump sites/sources, the haulage route, type of
                              vehicle to be utilised during filling operations and frequency of usage.
                              Any damage to the existing road system as a result of haulage operations shall be fully
                              repaired at the applicant’s expense.
               11.    All necessary approvals from external service providers (e.g., Unitywater) and external
                      parties on which the development works are proposed have been obtained and a copy
                      supplied to Council.
               12.    Any changes to the details associated with the supervising RPEQ or Principal Contractor
                      during construction, must be notified to council in writing within five business days of the
                      change occurring.
               13.    Any conflict between the development and an existing or proposed service must be referred
                      to the relevant service authority for determination prior to commencement of works.
               VEGETATION PROTECTION
                      Retention of Existing Trees and Vegetation
               14.    All trees and vegetation identified for retention must be protected in accordance with
                      AS 4970, Protection of trees on development sites.
               15.    A qualified person (*) must be engaged for the duration of the works to:
                      a.      Oversee installation of all tree protection fencing prior to commencement of any works
                              onsite (including any clearing).
                      b.      Supervise tree protection within the development site and frontages, prior to, during
                              and following construction in accordance with AS4970, Protection of trees on
                              development sites.
                      c.      Oversee approved tree removal in proximity to retained trees.
                      d.      Undertake a risk assessment of all trees within striking distance of the development
                              works and site and carry out hazard removal and amenity pruning in accordance with
                              AS 4373, Pruning of amenity trees.
                              (*) Refer to Advisory Note
               16.    Vegetation areas for protection must:
                      a.      Be protected in accordance with the approved Tree Protection Plan(s) listed in this
                              Decision Notice.
                      b.      Be protected with a minimum 1.2m high temporary safety fence (or temporary barrier
                              mesh / three-strand wire with pickets at 3m centres or flagging / bunting).
                      c.      Have the fence installed prior to the prestart meeting and maintained for the entire
                              period of construction.



                                                                                                      Page 13 of 27

Document Set ID: 25027781
Version: 3, Version Date: 13/08/2026

Page 14

                      d.      Have ‘Exclusion Zone’ (‘No Go,’ ‘No clearing zone’) signage fixed to the fence at
                              10m centres.
                      e.      Have no construction material, equipment or personnel entering the Exclusion Zone’
                              (‘No Go,’ ‘No clearing zone’) except to undertake approved rehabilitation activities.
                              (*) Refer to Advisory Note
               Removal of existing trees and vegetation
               17.    Approved vegetation removal, felling and lopping must:
                      a.      Be undertaken in a manner that avoids damaging surrounding vegetation and habitat
                              to be retained.
                      b.      Retain old growth tree hollows and suitably relocate and distribute for nesting fauna.
                      c.      Mulch all other wood and leaf material (without root balls, soil or debris and minimising
                              weed seeds) for re-usable mulch.
                      d.      Have mulch for re-use in landscape or rehabilitation stockpiled and aged for a minimum
                              of three months.
                      e.      Have mulch stockpiles no larger than 1000m3, 2.5m in height and with 10m separation
                              between piles.
                              (*) Refer to Advisory Note
               FAUNA MANAGEMENT
               18.    Fauna management works must be managed, supervised, undertaken and certified by
                      qualified persons (*) to:
                      a.      ensure all works, prior to and during clearing, are carried out in accordance with the
                              approved Fauna Management Plan and fauna management conditions listed in this
                              Decision Notice; and the Nature Conservation Act 1992.
                      b.      Undertake pre-clearing inspections including fauna relocation and removal or blocking
                              of all vacant hollows.
                      c.      Ensure clearing works avoids nesting times of animals and birds.
                      d.      Co-ordinate staging and sequence of clearing with fauna protection.
                      e.      Protect and recover fauna during clearing operations (not previously removed).
                      f.      Manage the translocation of animals and recovery procedures in accordance with
                              relevant legislation.
                      A qualified person for the purpose of managing and supervising fauna protection, preparing
                      Fauna reporting and certification and calculating compensatory habitat, is considered to be
                      an Ecologist and Environmental Scientist with a minimum of three years current experience
                      in the field of fauna assessment and management and current certification under the
                      Queensland Parks and Wildlife Service.
                      (*) Refer to Advisory Note
                      Pre-clearance site inspection and surveys
               19.    Prior to any vegetation clearing, a site inspection will be completed by a suitably qualified
                      person (*) to identify any hollow-bearing trees and/or other significant habitat features (i.e.
                      den sites, nests, hollowed termitarium etc.) These will be clearly marked in the field with high
                      visibility paint as well as shown on appropriately scaled plans.
                      (*) Refer to Advisory Note
               20.    A thermal drone survey must be undertaken each morning prior to the commencement of
                      tree removal works to identify the presence of Koalas, where environmental conditions are
                      suitable for the effective use of thermal imaging technology.

                                                                                                       Page 14 of 27

Document Set ID: 25027781
Version: 3, Version Date: 13/08/2026

Page 15

                      Where environmental conditions are unsuitable for thermal surveying, a daily Koala risk
                      assessment must be undertaken by a suitably qualified fauna spotter-catcher (*). The
                      assessment must include:
                      a.      a search for evidence of Koala activity, including scats, within and adjacent to the day's
                              proposed tree removal area; and
                      b.      a visual inspection of all trees proposed for removal, and adjoining habitat trees that
                              may be affected by the works.
                      Tree removal must not commence until the assessment confirms that no Koalas are present
                      within the work area
                      (*) Refer to Advisory Note
                      Pre-clearing fauna trapping
               21.    Subsequent to the site inspection, and prior to commencement of site clearing works, a pre-
                      clearing trapping program will be completed, by a qualified person (*), targeting native
                      ground-dwelling and arboreal mammals. The trapping program will be designed to
                      progressively move through the site, from the east towards to the west of the site, ahead of
                      the subsequent under scrubbing operations.
                      Each area will be trapped for a minimum of four (4) nights, and any animals captured will be
                      relocated to suitable habitat area/s in consultation with Noosa Council and the Department
                      of Environment and Heritage Protection (DEHP). Arboreal mammals captured will be re-
                      located within suitably designed nest-boxes to be installed at the agreed release site.
               22.    Under scrubbing will not occur until the qualified person (*) has confirmed the location and
                      the extent of the trapped area and clearly identified the limits of the trapped area on site using
                      high visibility flagging tape.
               23.    The program will utilise the following trapping methodologies:
                      •       Pitfall traps/funnel traps
                      •       Small (Type A) Elliott traps – installed both on the ground and on platforms on the
                              trunks of trees;
                      •       Medium (Type B) Elliott traps – installed both on the ground and on platforms on the
                              trunks of trees; and
                      •       Cage traps
                      •       All traps will be baited with the universal mixture of peanut butter, honey and rolled
                              oats, or as otherwise directed by the suitably qualified person (*).
                              (*) Refer to Advisory Note
                      Under scrubbing
               24.    Once each area has been trapped, and the extent of the trapped area clearly identified the
                      groundcover and midstorey will be cleared utilising a slasher with a mulching head
                      attachment or similar. Any hollow-bearing trees and/or other significant habitat features
                      identified during the initial site inspection will be retained. All under scrubbing works will be
                      completed with a suitably qualified fauna spotter/catcher (*) in attendance.
                      (*) Refer to Advisory Note
                      Clearing non-habitat trees
               25.    After under scrubbing of each area is complete, non-habitat trees (i.e. trees other than those
                      identified as habitat trees) will be cleared and stockpiled for mulching. Clearing of non-habitat
                      trees will only occur where their removal will not impact on identified habitat trees (e.g.
                      canopies do not interconnect with habitat trees).
                      Hollow inspection and removal


                                                                                                        Page 15 of 27

Document Set ID: 25027781
Version: 3, Version Date: 13/08/2026

Page 16

               26.    After under scrubbing and clearing on non-habitat trees, an elevated work platform or cherry-
                      picker will be used in conjunction with a chainsaw operator and suitably qualified fauna
                      spotter/catcher to inspect and remove hollows a necessary prior to habitat tree felling. This
                      method involves the fauna spotter/catcher (*) inspecting each of the potential habitat features
                      (usually hollows, dreys and arboreal termite nests) to determine the presence of arboreal
                      fauna. This process is detailed following the step by step basis below:
                      a.      The fauna spotter/catcher (qualified person*), with the Arborist will inspect each visible
                              hollow or potential habitat resource identified in each tree using the cherry-picker. This
                              is usually carried out by simply looking into hollows with the assistance of a small torch,
                              however, burrow and bore-scopes can also be useful for deep hollows.
                      b.      If fauna is located within a hollow, a piece of towel or rag will be firmly placed in the
                              entrance to prevent the wildlife form escaping as in most cases arboreal fauna become
                              aware of the presence of the fauna spotter/catcher and may attempt to flee the
                              nesting/denning hollow due to a perceived threat. If an occupied hollow is
                              encountered, the fauna spotter/catcher should quietly approach (i.e. avoid contacting
                              other branches) in the cherry-picker bucket and physically capture the fauna by placing
                              the entire hollow in a catch bag or only the fauna if it emerges.
                      c.      Once the hollow entrance has been secured the arborist or fauna spotter/catcher will
                              cut the entire hollow limb off below the cavity where the branch remains solid. In
                              circumstances where a hollow continues into the main stem of the tree, a small window
                              will be carefully cut into the hollow, allowing the fauna spotter/catcher to plug the hollow
                              above and below the window, then the hollow limb removed and lowered to the ground
                              in sections.
                      d.      When the fauna has been safely secured within its hollow, the entire limb can then be
                              placed in the cherry-picker bucket or lowered to the ground using ropes depending on
                              the size of the limb.
                      e.      This limb will then be placed in a cool, quiet location until translocation to the recipient
                              habitat site, when at dusk the follow entrance is re-opened to allow the fauna to emerge
                              of its own accord.
                              (*) Refer to Advisory Note
                      Landscape Works
               27.    Landscape works must be supervised, undertaken and certified by qualified persons*. All
                      works must be completed in accordance with this Decision Notice.
                      (*) Refer to Advisory Note
               28.    Public amenity street trees (*) must:
                      a.      Be certified to meet AS2303:2018 Tree stock for landscape use.
                      b.      Be located in accordance with engineering requirements for safe vehicle and
                              pedestrian sight lines.
                      c.      Be located in accordance with the approved Landscape Design & Rehabilitation Plan
                              listed in this Decision Notice or otherwise approved by Council.
                      (*) Refer to Advisory Note
               29.    Turfed areas must be free of pest, diseases and weeds and level with adjoining surfaces.
                      Rehabilitation Works
               30.    Rehabilitation works must be supervised, undertaken and certified by qualified persons (*).
                      All works must be completed in accordance with this Decision Notice.
                      (*) Refer to Advisory Note
               31.    The Rehabilitation supervisor must annually, for a minimum period 12 months:


                                                                                                          Page 16 of 27

Document Set ID: 25027781
Version: 3, Version Date: 13/08/2026

Page 17

                      a.      Organise formal inspection with Council’s delegate.
                      b.      Submit to Council (with each inspection request) a Rehabilitation Status Report (written
                              and photographic), mapping:
                              i.       The condition of the regeneration area.
                              ii.      Detailing works undertaken in the previous year.
                              iii.     The percentage cover of indigenous recruitment.
                              iv.      Measuring the works against the approved Vegetation Covenant Area –
                                       Rehabilitation Management Plan.
               DURING CONSTRUCTION
                      Engineering
               32.    The developer must meet any costs to repair damage to any Council asset during
                      construction, where damage is a result of the development works. Damage to assets must
                      be repaired immediately where it creates a hazard to the community. In circumstances where
                      the damage does not create a hazard to the community, it must be repaired immediately on
                      completion of the works associated with the development.
               33.    All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
                      who is independent of the Developer and Principal Contractor, and they must certify that all
                      works conform to the Operational Works permit. Where municipal works are involved, such
                      confirmation must be submitted for the respective hold points prior to any site inspection by
                      Council Officers.
               34.    All works must be constructed and work procedure undertaken in accordance with:
                      a.      the approved plans/documents and conditions detailed in this Decision Notice;
                      b.      the relevant conditions of the higher order Reconfiguration of Lot approval viz.
                              RAL19/0014 to which this approval relates;
                      c.      all relevant Noosa Council Planning Scheme Policies, standard drawings, standard
                              specifications and guidelines; and
                      d.      the latest version of the Healthy Waterways document “Water Sensitive Urban Design
                              Technical Design Guidelines for South East Queensland” for all water quality devices
                              to be constructed on site.
                      Roadworks (External Roadworks & Road Widening Works)
               35.    All pavement widening or construction of new pavement must join neatly to the existing
                      pavement so that there are no irregularities in line or level resulting at or adjacent to the join
                      for the length of the construction. Where necessary the existing pavement must be brought
                      to a satisfactory standard to allow for the above.
               36.    All street surfacing must consist of a minimum depth of 30mm of an approved hot mixed
                      asphaltic concrete, unless other pavement types are approved as feature areas in
                      intersection thresholds, speed control devices, turning areas, indented parking etc.
               37.    The installation and/or modification of any traffic signs, street signs, line marking and Raised
                      Reflective Pavement Markings (RRPMs) must be in accordance with the Manual of Uniform
                      Traffic Control Devices (MUTCD). New or relocated signage must be installed using the VLok
                      installation system. All new signage must be Class 1 retroreflective material in accordance
                      with AS 1906.1, Retroreflective materials and devices for road traffic control purposes – Part
                      1: Retroreflective sheeting.
                      Pavement Design and Construction
               38.    The pavement designs shown on the engineering drawings are not approved. To attain
                      approval for the pavement design, the following details must be submitted and certified by
                      an RPEQ with the proposed pavement design.

                                                                                                        Page 17 of 27

Document Set ID: 25027781
Version: 3, Version Date: 13/08/2026

Page 18

                      a.      the design CBR must be based on the four-day soaked CBR value for the subgrade
                              material;
                      b.      the design subgrade CBR must be representative of each homogenous insitu section
                              of finished subgrade. With respect to each section:
                              i.       for four or less test results, the design CBR must be taken as the least estimated
                                       insitu CBR result; and
                              ii.      for five or more test results, the design CBR must be taken as the 10th percentile
                                       of all estimated insitu CBR results.
                      c.      the samples must be taken generally in the position of the outer wheel path on both
                              sides of the proposed road. A sketch plan showing the location of all tests must be
                              submitted with the test results for pavement design approval.; and
                      d.      where imported material has been (or is proposed to be) used for subgrade
                              replacement, and the depth of the imported material is less than 300mm, the pavement
                              design CBR must be based on the testing results of the insitu material and not the
                              imported material.
               39.    A hold point inspection is required with a Council delegate upon completion of the following
                      stages of road construction:
                      a.      subgrade; and
                      b.      base course (pre-seal).
                      At the time of the inspection(s), the pavement layer must exhibit no visible signs of
                      deformation under proof rolling by a fully loaded water truck to the reasonable satisfaction of
                      Council. The pavement layer will not pass the inspection until this requirement has been
                      achieved.
                      (*) Refer to Advisory Note
               40.    Pavement design for privately owned works must be undertaken in accordance with the
                      relevant standards. Structural integrity of the driveway and car park areas will remain the
                      responsibility of the property owner/developer and must be certified by an RPEQ.
                      Works within Road Reserve/Reinstatement
               41.    Safe pedestrian and vehicle access on all streets in the vicinity of the development must be
                      maintained at all times. Should footpath/road closures be necessary to carry out construction
                      works, Council’s Engineering Officer must be notified prior to the proposed closure and all
                      requirements complied with.
               42.    All frontage works must match neatly with existing road and verge/footpath features.
                      Additional works beyond the frontage may be required to provide an acceptable transition to
                      existing road and verge/footpath profiles.
               43.    Electrical conduits or other services proposed to be installed within existing and proposed
                      road reserves under existing sealed carriageways, concrete pathways, concrete/sealed
                      driveways or significant vegetation must be installed by boring. Trenching is not permitted,
                      unless specifically approved by Council.
                      Pathways
               44.    All pathways must be constructed in accordance with the following requirements:
                      a.      all footpath/cycleway must comply with Council’s Standard Drawing SEQ R-065;
                      b.      provision must be made for disabled access at all kerb crossings associated with
                              pathways, in accordance with Council's current standards;
                      c.      all paths must have a slip resistant surface;
                      d.      expansion and contraction joints must provide a flush finish. Installation of joints by saw
                              cutting is preferred to ensure a smooth ride for cyclists; and

                                                                                                          Page 18 of 27

Document Set ID: 25027781
Version: 3, Version Date: 13/08/2026

Page 19

                      e.      the required work includes any modifications to ensure the footpath finishes flush with
                              all existing service covers and the like, or alternatively these services are raised or
                              altered, so as not to create a pedestrian safety hazard.
               45.    Pathways must:
                      a.      terminate in a manner that ensures smooth transition to existing surfaces for public
                              safety; and
                      b.      be designed and constructed to comply with the Disability Discrimination Act (DDA),
                              Access to Premises Standard, Austroads and relevant sections of AS1428 Design for
                              access and mobility.
                      Site Access and Driveways
               46.    Driveway crossovers must be constructed in accordance with council’s Standard Drawings:
                      a.      RS-049, RS-050 and any associated addendum.
               47.    Any existing unnecessary or redundant property accesses must be removed, and the kerb,
                      footpath and verge area reinstated to match the existing footpath and/or verge treatments.
                      Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed
                      or turf and must be maintained by the developer until established.
               48.    The following must be complied with during the construction of the required
                      crossover/driveway:
                      a.      the driveway surfacing must consist of an approved hot mixed asphaltic concrete or
                              patterned/plain concrete;
                      b.      decorative surfaces must be approved by Council, have a maximum 5mm depth
                              variation in the finished surface profile, and comply with AS4586, AS3661.1 and any
                              associated addendum;
                      c.      the driveway must be constructed so as not to concentrate stormwater runoff onto
                              neighbouring properties;
                      d.      underground service conduits for water supply, electricity and any other services must
                              be provided as part of the access driveway;
                      e.      where there is an existing pedestrian path, a matching crossfall must be provided for
                              the driveway on the alignment of the path, for the full width of the path;
                      f.      have a minimum clearance of 500mm from any Unitywater/Energex/Telstra asset,
                              unless a written approval is obtained from Unitywater/Energex/Telstra and submitted
                              to Council; and
                      g.      the property access must be located a minimum of 1m clear of existing power poles,
                              streetlights or other signage.
                              The developer is responsible for any necessary relocation of existing services to
                              provide this clearance and must contact the relevant service authorities and comply
                              with their requirements in relation to these works.
                      Earthworks and Retaining Walls
               49.    All earthworks shall be undertaken in accordance with the provisions of AS 3798 Guidelines
                      on Earthworks for Commercial and Residential Development, with geotechnical testing
                      undertaken in accordance with Section 8 of the Standard, and to a minimum of ‘Level 1’ as
                      defined in Appendix B. Test results as required by AS 3798, and a certificate of quality and
                      uniformity of fill shall be provided by a RPEQ and submitted to Council prior to Council signing
                      the Plan of Survey.
               50.    All earthworks and associated batters/retaining structures, both above and below ground
                      level, both temporary and permanent, must be contained entirely within the subject site
                      unless written permission from the respective landowner(s) is provided to Council.


                                                                                                      Page 19 of 27

Document Set ID: 25027781
Version: 3, Version Date: 13/08/2026

Page 20

               51.    Fall protection must be provided to retaining walls that are over 1m high.
               52.    Slope and batters are a maximum grade of:
                      a.      1 in 6 where in proximity to waterbodies;
                      b.      1 in 4 for grassed areas;
                      c.      1 in 3 for planted areas; and
                      d.      1 in 2 for combined structural engineering and planting solutions.
                      Stormwater Drainage
               53.    Appropriate scour protection must be provided at the outlet of all stormwater pipes including
                      temporary outlets.
               54.    Works associated with this permit must not adversely impact on the existing drainage
                      conditions on other properties (e.g., by blocking or interfering with natural overland flows).
               55.    Construction of all internal stormwater drainage works must comply with the relevant
                      section/s of Australian Standard AS/NZS 3500.3.
                      Bioretention Basins – Construction
               56.    The bioretention devices must be constructed in accordance with the document Construction
                      and Establishment Guidelines: Swales, Bioretention Systems and Wetlands (Water by
                      Design, 2009). Option 1 of the staged construction and establishment methods is to be
                      followed as documented in the guidelines.
               57.    During construction and establishment of the bioretention devices, the supervising RPEQ
                      must ensure that the device is constructed in accordance with the document Construction
                      and Establishment Guidelines: Swales, Bioretention Systems and Wetlands (Water by
                      Design, 2009) and that the forms contained in section 3.15 including the associated
                      supporting information and data are completed.
                      These forms and certification from the RPEQ that the device has been constructed in
                      accordance with the Construction and Establishment Guidelines: Swales, Bioretention
                      Systems and Wetlands (Water by Design, 2009), all conditions of approval, and the approved
                      engineering drawings must be submitted to Council prior to plan sealing.
               58.    A construction hold point with a Council delegate must be established once the bioretention
                      device underdrainage pipe work is installed.
                      At the time of inspection, a sample of the drainage layer, transition layer, and filtration media
                      materials must be stockpiled on-site. Laboratory results must be provided for the filter media
                      which demonstrate that the media complies with the specifications contained in the latest
                      version of the “Guidelines for Soil Filter Media in Bioretention Systems” (produced by the
                      Facility for Advancing Water Biofiltration) and that the minimum hydraulic conductivity
                      specified on the approved engineering plans will be achieved. In addition, laboratory results
                      must be provided demonstrating that the transition layer and drainage layer meet the
                      following bridging criteria:
                      a.      D15 (drainage layer) ≤ 5 × D85 (transition layer)
                      b.      D15 (transition layer) ≤ 5 × D85 (filter media)
                      Bioretention Basins – Maintenance & handover
               59.    Following installation of the filter media for the bioretention devices, a temporary cover
                      consisting of a suitable geotextile covered with soil and turfed is to be immediately installed.
                      This temporary cover is to be maintained in place for a minimum period of 24 months
                      following acceptance of the bioretention devices On Maintenance or until 80% of building
                      works has been completed (whichever occurs first).



                                                                                                       Page 20 of 27

Document Set ID: 25027781
Version: 3, Version Date: 13/08/2026

Page 21

                      Following this period the temporary cover is to be removed, and the approved plantings
                      installed. The bioretention devices are then to be appropriately maintained for a minimum
                      period of 12 months prior to being accepted as Off Maintenance by Council’s delegate.
               60.    Prior to acceptance of the basin either On or Off Maintenance, Council must receive evidence
                      that the results for the in-situ hydraulic conductivity testing conducted in accordance with
                      FAWB PRACTICE NOTE 1: In Situ Measurement of Hydraulic Conductivity Belinda Hatt,
                      Sebastien Le Coustumer April 2008 for the bioretention filter media achieve the design
                      criteria.
               61.    Subsoil drains are to be cleaned out and accumulated sediment manually removed from the
                      surface of basin and coarse sediment forebays at Off Maintenance and as required during
                      the maintenance period.
               62.    All stormwater quality treatment devices must be maintained by the development in
                      accordance with Water by Design (2009) Maintaining Vegetated Stormwater Assets (Version
                      1) until they are accepted as Off Maintenance by Council.
               63.    Any defects in WSUD devices identified during the maintenance period must be reviewed
                      and a report recommending required rectification works submitted to Council and endorsed
                      by Council’s delegate. Works to repair the device and prevent the problem occurring in the
                      future must be completed and the device maintained for a minimum period of 12 months prior
                      to the WSUD device being accepted as Off Maintenance.
               64.    Prior to Council accepting the bioretention devices Off Maintenance, maintenance checklists
                      including the full cost of maintaining the devices in accordance with Water by Design (2009)
                      Maintaining Vegetated Stormwater Assets (Version 1) must be submitted to Council.
                      Erosion and Sediment Control
               65.    Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection
                      Regulation 2019) must not be released from the site or to waters within the site, or be likely
                      to be released should rainfall occur, unless all reasonable and practicable measures are
                      taken to prevent or minimise the release and concentration of contamination.
               66.    Sediment and erosion control measures must be in place prior to works commencing. If such
                      measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such
                      fines can be issued if sediments from the site are found to enter or have the potential to enter
                      Council’s stormwater system, natural waterways, any downstream stormwater filtration
                      system or adversely impacting on other properties.
                      The sediment and erosion control design and measures have NOT been approved, it is the
                      site's Supervising Engineer who is responsible for ensuring that the sediment and erosion
                      control measures have:
                      a.      Been duly designed by an RPEQ or CPESC and constructed in accordance with "best
                              practise" methods;
                      b.      Been revised by an RPEQ or CPESC to address the issues raised by changes in the
                              projected construction schedule and/or methods;
                      c.      Been revised to address predicted rainfall events; and
                      d.      Achieve the desired environmental outcomes.
                      Council may request further controls to be installed should the implemented measures be
                      found inefficient.
               67.    The erosion and sediment control measures must be designed, installed and maintained in
                      accordance with the supervising engineer’s instructions and the current best practice
                      standards. A copy of the latest erosion and sediment control plan, prepared and endorsed
                      by a suitably qualified person (RPEQ/CPESC), must be made available to Council within 5
                      business of request.
                      (*) Refer to Advisory Note

                                                                                                      Page 21 of 27

Document Set ID: 25027781
Version: 3, Version Date: 13/08/2026

Page 22

               68.    All erosion and sediment controls must be inspected to ensure the controls are not being
                      bypassed. Inspections must occur and be electronically recorded:
                      a.      at least daily (when work is occurring on site) or weekly (when work is not occurring on
                              site); or
                      b.      within 24 hours of expected rain; or
                      c.      within 18 hours of a rainfall event (i.e. an event of sufficient intensity and duration to
                              mobilise sediment on site).
               69.    Earthworks and the implementation of erosion and sediment controls are undertaken in ways
                      which ensure flooding characteristics (including stormwater quantity characteristics) external
                      to the development site are not worsened during construction for all events up to and
                      including the 1% AEP (1 in 100 year ARI) event.
               70.    The developer must ensure non-essential exposure of soil is prevented by restricting the
                      extent of disturbance and minimising the duration of soil exposure to adverse weather
                      conditions and effectively turf, cover or stabilise any disturbed area without delay and prior
                      to rainfall occurring.
               71.    The developer must ensure sediment does not leave the site or enter onto adjoining
                      properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or
                      machinery. It is essential to implement appropriate approved erosion and sediment control
                      measures throughout the site during all phases of construction including vehicle shakedown
                      pad/grid (or similar) at the access to the construction site. Where sediments or other
                      contaminants are deposited on a road, they must be removed so as not to enter Council’s
                      drainage system or waterways.
                      Damage to Services and Assets
               72.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      where otherwise, upon completion of the works associated with the development.
                      Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval.
               PRIOR TO COUNCIL SIGNING THE PLAN OF SURVEY
                      Certification
               73.    Upon completion of the work:
                      a.      a certificate must be issued to Council by an RPEQ certifying that the works have been
                              constructed in accordance with the Operational Works permit; and
                      b.      a condition report of the drainage system must be issued to Council. The report must
                              include a CCTV inspection of the new stormwater network commencing from “1/A” and
                              concluding at “8/A” and include all new branches.
                      As Constructed Plans and ADAC XML Files (Council)
               74.    Prior to acceptance of civil works to become Council assets “On Maintenance”, satisfactory
                      “As-Constructed” records must be submitted to Council. The bundle of “As Constructed”
                      information shall include:
                      a.      As-Constructed Engineering Drawings. Data is to be submitted in an electronic drawing
                              file format (.dwg), with all plans clearly endorsed “As-Constructed”, along with the
                              accompanying hardcopies (PDFs of the As-Constructed .dwg drawing files), and;




                                                                                                        Page 22 of 27

Document Set ID: 25027781
Version: 3, Version Date: 13/08/2026

Page 23

                      b.      ADAC XML Digital File. ADAC File format (ADAC - Asset Design As Constructed)
                              prepared in accordance with industry standards and recorded in “MGA - UTM56 /
                              GDA94” projection.
                              Please Note: Further information and advice relating to the as-constructed drawing
                              presentation, as-constructed survey capture and associated guidelines for preparation
                              of a compliant ADAC XML digital file are available on the webpage titled “As-
                              Constructed Guidelines” and accessible at the Noosa Council Website: Planning &
                              Development / Development Tools & Guidelines / As-Constructed Guidelines.
                      c.      The “As-Constructed” drawings will require certification by a:
                              i.       Qualified experienced Civil Engineer (RPEQ) confirming design intent and
                                       conformance with applicable standards and specifications, along with the
                                       relevant descriptions of assets, services and structures and;
                              ii.      Registered Cadastral Surveyor (Qld) in regard to the cadastral and locational
                                       information, levels and applicable survey datum.
                      d.      The data must be in accordance with Council’s “Planning Scheme Policy 6 –
                              Engineering Design Standards” and fully detail the levels for all engineering works
                              including but not limited to the drainage network and structures, finished ground and
                              pavement surface levels.
                      e.      Landscaping, including all assets and improvements within parks, open space and road
                              reserves areas are to be shown on an accompanying separate landscape plan
                              (prepared in .dwg file format with accompanying hardcopy PDFs) and include a
                              complaint ADAC XML file. Details of the landscaping and all associated assets and
                              improvements may be included in the ADAC XML digital file prepared for associated
                              civil infrastructure, or alternatively, be provided as a separate ADAC XML digital file
                              containing landscape and asset information only.
                      On Maintenance
               75.    All municipal works must be accepted as ‘On Maintenance’ by Council in accordance with
                      Council’s Planning Scheme Policy 6 prior to plan sealing.
                      To achieve ‘On Maintenance’ status:
                      a.      the supervising RPEQ must submit to Council for review and acceptance:
                               i.      certification that all works have been undertaken and completed in accordance
                                       with the requirements of this approval;
                              ii.      as Constructed details in accordance with Council’s Planning Scheme Policy;
                                       and
                             iii.      maintenance and operational manuals for all proprietary or site-specific devices.
                      b.      Council must inspect and agree to accept the municipal works as ‘On Maintenance’.
                              Any defect or substandard work observed by Council during the inspection must be
                              rectified to the satisfaction of Council prior to Council’s acceptance of the ‘On
                              Maintenance’ status.
                              (*) Refer to Advisory Note
                      c.      A maintenance bond must be submitted to Council in accordance with Council’s
                              Planning Scheme Policy 6. The maintenance bond shall be 5% of the agreed value of
                              the municipal works to become ‘On Maintenance’ or $2,000 (whichever is greater).
               76.    Maintenance periods (*) must be:
                      a.      12 months for Streetscape Landscaping works.
                      b.      12 months for Rehabilitation or subject to meeting criteria outlined in the Vegetation
                              Covenant Area – Rehabilitation Management Plan.


                                                                                                         Page 23 of 27

Document Set ID: 25027781
Version: 3, Version Date: 13/08/2026

Page 24

                      (*) Refer to Advisory Note
               77.    Prior to requesting an On Maintenance inspection, the following information (prepared by
                      respective qualified persons* and certifying compliance with approvals) must be submitted
                      to Council:
                      a.      All required bonds.
                      b.      Landscaping certification.
                      c.      AS2303:2018 Tree stock for landscape use certification.
                      d.      Fauna Report documenting the findings and outcome of the fauna protection works
                              undertaken.
                      e.      Bushfire management certification.
                      Off Maintenance
               78.    Prior to requesting an Off Maintenance inspection, the developer must provide a written
                      request for the Off Maintenance inspection and include certifications from the Project Arborist
                      that all trees in public land have been inspected and rectification works for public safety and
                      longevity of the tree/s has been completed.
               79.    Off Maintenance will only be accepted after all works are confirmed in good order including,
                      but not limited to:
                      a.      Rectifying any damaged grassed areas.
                      b.      Topdressing to grassed areas.
                      c.      Remulching, fertilising and aeration of garden areas.
                      d.      Replacement of plant material.
               80.    A re-inspection fee in accordance with Council’s Fees and Charge Register will be charged
                      where:
                      a.      a Council inspection reveals works do not comply with approval requirements
                      b.      submitted certification falsely states works comply with approval requirements.
                      Final Inspection
               81.    A final inspection and approval of the new driveway and completed reinstatement works by
                      Council’s Inspector is required. Please contact Council on 5329 6500 to arrange for the
                      inspection.
               5.     REFERENCE DOCUMENTS

               Not applicable.
               6.     REFERRAL AGENCIES

               Not applicable.
               7.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
                      General Advisory Notes
               1.     As this driveway is a private structure, the owner bears full responsibly for the standard of its
                      construction, maintenance and any liabilities associated with its construction. It is
                      recommended that professional advice be sought for the construction of the driveway to
                      ensure that the driveway is constructed in accordance with standard drawings RS-049 and
                      RS-050.



                                                                                                       Page 24 of 27

Document Set ID: 25027781
Version: 3, Version Date: 13/08/2026

Page 25

               2.     Council has undertaken an audit check of the Operational Works drawings in relations to the
                      proposed works. A detailed check of the calculations and drawings has not been undertaken,
                      as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of
                      the engineering design. Council reserves the right to require further amendments and/or
                      additions at a later date should design errors become apparent.
               3.     Council reserves the right to call up any performance bond held or levy charges against the
                      property, should emergency works be required to be undertaken by Council to make the site
                      safe due to inactivity on the development site for extended periods of time.
               4.     Should any changes or modifications to the approved plans be required as a result of
                      construction constraints, a “Request to change an existing approval” under the Planning Act
                      2016 must be made. Amended plans clearly indicating the changes must be lodged with this
                      application along with the appropriate fees.
                      Prestart, Hold-Point, On and Off Maintenance and Rehabilitation Inspections Request
               5.     Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5
                      business days’ notice of preferred inspection time.
               6.     If Council officers are required to undertake additional inspections of the same works, a
                      reinspection fee will be applicable in accordance with Council’s Fees and Charges register
                      applicable at the time.
               7.     A minimum maintenance period of 12 months will apply to all municipal works and thereafter
                      until such time as the works are performing in accordance with the approved design unless
                      noted otherwise.
                      Environmental Advisory Notes
               8.     The Environmental Protection Act 1994 states that a person must not carry out any activity
                      that causes, or is likely to cause, environmental harm unless the person takes all reasonable
                      and practicable measures to prevent or minimise the harm. Environmental harm includes
                      environmental nuisance. In this regard persons and entities, involved in the civil, earthworks,
                      construction and landscaping phases of this development are to adhere to their ‘general
                      environmental duty’ to minimise the risk of causing environmental harm.
                      Retention of Existing Trees
               9.     The existing trees on adjoining properties must be retained and protected during construction
                      wherever achievable. To avoid doubt, this advisory note is not intended to exclude the
                      operation of Chapter 3 of the Neighbourhood Dispute Resolution Act 2011 following
                      construction of the development which is the subject of this development approval.
                      Landscape Works
               10.    The applicant must pay the re-inspection fee in accordance with Council's Fees and Charges
                      Register where:
                      a.      An inspection revealed that any constructed rehabilitation/landscape works do not
                              comply with the conditions of the Decision Notice, Approved Plans and or Approved
                              Documents
                      b.      Certification is submitted to Council falsely stating that works comply with the approved
                              plans, documents and or conditions of the Decision Notice.
               11.    Public amenity trees are defined as any tree located within public streets, parks or areas that
                      will become publicly owned as a result of this development.
                      Qualified Person
               12.    Qualified Person, for the purpose of:
                      a.      Supervising landscape works and preparing a landscape certification, is considered to
                              be a landscape architect, landscape designer or horticulturist with a minimum of three
                              years current experience in the field of landscape design.

                                                                                                       Page 25 of 27

Document Set ID: 25027781
Version: 3, Version Date: 13/08/2026

Page 26

                      b.      Undertaking landscape construction and establishment works is considered to be a
                              person with five years current experience in commercial landscape construction
                              projects.
                      c.      Undertaking rehabilitation construction and establishment works is considered to be a
                              person with five years current experience in revegetation and regeneration.
                      d.      Undertaking, supervising tree works and preparing arboriculture certification, is
                              considered to be a person with a minimum three years current experience in tree
                              protection, hazard identification/mitigation and certifying AS2303:2018 Tree stock for
                              landscape use and either:
                              i.       International Society of Arboriculture (ISA) certification; or
                              ii.      A Diploma of Arboriculture (min AQF level 5).
                      e.      Managing Fauna protection, preparing Fauna reporting and certification and
                              calculating compensatory habitat, is considered to be an Ecologist and Environmental
                              Scientist with a minimum of three years current experience in the field of fauna
                              assessment and management and current certification under the Queensland Parks
                              and Wildlife Service.
                      f.      Supervising and certifying Bushfire Management is considered to be an Ecologist with
                              suitable experience or a person with Fire Protection Association Australia – Bushfire
                              Planning and Design certification.
                      Erosion and Sediment Control
               13.    Accepted best practice standards include International Erosion Control Association
                      Australasia Best Practice Erosion and Sediment Control.
               14.    Qualified Person, for the purpose of erosion and sediment control is a Certified Professional
                      in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional
                      Engineer of Queensland (RPEQ).
               15.    As a general rule, a site is determined to have achieved effective short-term stabilisation if
                      at the time of the plan sealing inspection:
                      a.      Methods of stabilisation are:
                              •     appropriate for slopes and slope lengths; and
                              •     are consistent with best practice environmental management practices such as in
                                    the Manual for Erosion and Sediment Control or the IECA Manual; and
                      b.      Stormwater runoff from the site is not currently and is not likely to result in visible
                              evidence of sedimentation or erosion, or lead to water contamination.
                      Road Reserve Permit
               16.    This development permit provides the applicant with written authority to undertake the
                      prescribed works. Any additional activities that are undertaken inside Council’s road reserve
                      for the purpose of acting on this development permit may require a Road Reserve Permit.
                      These additional activities may include, but are not limited to, hoarding, pedestrian
                      diversions, laneway closures, etc. To apply for a Road Reserve Permit, or for more
                      information, Contact Council’s Road Reserve Officer at [email protected] Sealing
               17.    All works required by this permit must be completed and accepted by Council prior to
                      submitting an application for plan sealing.
                      Biosecurity Act 2014 – Fire Ant Control




                                                                                                        Page 26 of 27

Document Set ID: 25027781
Version: 3, Version Date: 13/08/2026

Page 27

               18.    Developers must remain vigilant for the presence of fire ants. Under the Biosecurity Act 2014,
                      individuals and businesses are responsible for ensuring that they follow the movement
                      controls for specific organic materials to help prevent the spread of fire ants within South
                      East Queensland’s fire ant biosecurity zones. Movement of a fire ant carrier from within a fire
                      ant biosecurity zone may need a biosecurity instrument permit. More information is available
                      on https://www.fireants.org.au/treat/business-andindustry/movement-controls.
               8.     PROPERTY NOTES

               Not applicable.
               9.     VARIATION APPROVAL DETAILS

               Not applicable.
               10.    FURTHER DEVELOPMENT PERMITS REQUIRED

                Type of Development                                    Subject of the required Development

                Operational Works                                      Electrical Reticulation

               11.    SUBMISSIONS

               Not applicable.
               12.    RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.
               During the appeal period, you as the applicant may suspend your appeal period and make written
               representations to Council about the conditions contained within the development approval. If
               Council agrees or agrees in part with the representations, a negotiated decision notice will be
               issued. Only one negotiated decision notice may be given.
               13.    OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available online at
               www.noosa.qld.gov.au or at Council Offices.




                                                                                                     Page 27 of 27

Document Set ID: 25027781
Version: 3, Version Date: 13/08/2026

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.