               Demolition of Building
                      Codes of Development
               33.    Unless specifically conditioned otherwise, all works must comply with the relevant acceptable
                      solutions as contained in the Waste Management Code and Water Quality and Drainage
                      Code of the Noosa Plan 2020.
                      Works
               34.    Demolition must be undertaken in a manner that causes no detrimental effect upon the
                      amenity of the neighbourhood by reason of the creation of excessive noise, lighting, air-borne
                      hazards, atmospheric pollutants (including dust or odours) nuisance or any other emissions
                      in accordance with the nuisance provisions of the Environmental Protection Act 1994.
                      Waste Management
               35.    Adequate area must be provided on-site for the collection and separate storage of recyclable,
                      non-recyclable, vegetative and hazardous materials in their specific waste streams during
                      removal or demolition works.
               36.    All waste materials must be removed from the site to avoid causing unhealthy conditions,
                      with the site left clean, tidy and free from any debris.
               37.    Where a development permit has not been issued for the future use of the site, hard surfaced
                      areas including concrete slabs must be removed and disturbed areas must be revegetated
                      in accordance with PSP2 Landscaping of the Noosa Plan 2020. Alternatively, the site must
                      be turfed within 20 business days of completing the removal or demolition work.
                      Water Quality and Drainage
               38.    Erosion and sediment control is to be undertaken in accordance with the requirements of the
                      Water Quality and Drainage Code of the Noosa Plan. Measures are to be installed and/or
                      maintained until soils are stabilised by vegetation or sealed.
                      NOTE: It is an offence under the Environmental Protection Act 1994 to deposit or potentially
                      allow litter, waste, soil, or other contaminants to enter a waterway or storm water drainage
                      system (e.g. roadside gutter).
                      Health and Safety
               39.    All building materials containing asbestos, including asbestos cement sheeting or roofing and
                      lagging, are removed from the building prior to demolition or relocation.
               40.    Removal of building materials containing asbestos must be undertaken by a licensed
                      asbestos removalist.
               41.    Asbestos removal work (Section 466) of the Work Health and Safety Regulation 2011
                      requires a licensed asbestos removalist to give notice to Workplace Health and Safety
                      Queensland (WHSQ) of licensed asbestos removal work at least five days before the work
                      commences. Notification must be made using Form 65: Notification of licensed asbestos
                      removal work, demolition work or emergency demolition.
               42.    All building materials containing asbestos products are wrapped and disposed of in
                      accordance with the Public Health Regulation 2006 and the Environmental Protection
                      Regulation 2008.
                      Note: Asbestos is a Regulated Waste. The Department of Environment & Science licenses
                      businesses that transport asbestos waste, and landfills that accept this waste.
                      General
               43.    Infrastructure including reticulated water, sewerage, stormwater, and electricity must be
                      protected from damage and made safe to the standard required by the regulatory authority.
               44.    Any damage to footpaths, street plantings, natural vegetation/trees, kerb and channel,
                      bridges or roadways at the removal/demolition site must be repaired or reinstated to at least
                      pre-existing conditions.


                                                                                                      Page 6 of 10
Document Set ID: 23993720
Version: 6, Version Date: 06/08/2025

Log in to download the original (Decision Notice - Approved by Delegation of Authority MCU24 0155 (As Published).pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.