Negotiated Decision Notice MCU24 0153 & OPW24 0202 (As Published) · MCU24/0153
Officer: Andrew Gaffney
Direct Telephone: 07 53296284
Our Reference: MCU24/0153 &
OPW24/0202
Your Reference: 20240911
16 December 2025
Archend
C/- Adapt Development Management P/L
Level 1/103 Sippy Downs Dr
SIPPY DOWNS QLD 4556
[email protected]
Dear Sir/Madam,
Negotiated Decision Notice
Planning Act 2016
I refer to your application and the representations you made in respect to the decision notice. On
15 December 2025, Council decided your representations. This negotiated decision notice
replaces the decision notice of 11 August 2025.
Details of the negotiated decision are as follows:
1. APPLICATION DETAILS
Application No: MCU24/0153 & OPW24/0202
Street address: 51 Elanda St Sunshine Beach Qld 4567
Real property description: Lot 403 RP 48112
Planning Scheme: Noosa Plan 2020 (25 September 2020)
2. DECISION DETAILS
Council on 15 December 2025, decided to issue the following type of approval:
• Development Permit Material Change of Use - Multiple dwelling (6 small dwellings).
• Development Permit for Operational Works - Roadworks, Stormwater, Landscaping and
Earthworks.
In relation to representations, Council on 15 December 2025 decided to:
A. Agree to the representations.
B. Agree to amend the ‘Decision Details’
C. Agree to amend condition 3 of the Material Change of Use.
D. Agree to amend condition 1 of the Preliminary Approval for Operational Works.
E. Agree to include additional conditions 3 -56 for Operational Works Approval.
ABN 97.969.214.121 PO Box 141
noosa.qld.gov.au Tewantin QLD 4565
[email protected] 07 5329 6500
Page 1 of 22
Document Set ID: 24037249
Version: 8, Version Date: 18/12/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 21 pages
Page 2
3. CURRENCY PERIOD OF APPROVAL
The currency period for this development approval is stated in the conditions below.
4. ASSESSMENT MANAGER CONDITIONS
DEVELOPMENT PERMIT FOR MATERIAL CHANGE OF USE (MCU24/0153)
PLANNING
When Conditions must be Complied With
1. Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to
the use commencing, and then compliance maintained at all times while the use continues.
Currency Period
2. This development approval lapses if the use has not happened by 11 August 2031, unless
an application to extend the currency period is approved by Council.
Approved Plans
3. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions*.
Plan No. Rev. Plan/Document Name Date
08 E Site Plan, prepared by Archend 28/11/2025
11 E Site Plan - Landscaping Areas, prepared by 28/11/2025
Archend
15 E Floor Plan - Basement, prepared by 28/11/2025
Archend
16 E General Arrangement - Ground Floor, 28/11/2025
prepared by Archend
17 E Floor Plan - Level 1, prepared by Archend 28/11/2025
18 E Floor Plan - Level 2, prepared by Archend 28/11/2025
19 E Floor Plan - Roof, prepared by Archend 28/11/2025
20 E Floor Plan - Ground GFA, prepared by 28/11/2025
Archend
21 E Floor Plan - Level 1 GFA, prepared by 28/11/2025
Archend
Page 2 of 22
Document Set ID: 24037249
Version: 8, Version Date: 18/12/2025
Page 3
22 E Floor Plan - Level 2 GFA, prepared by 28/11/2025
Archend
23 E North Elevation, prepared by Archend 28/11/2025
24 E South Elevation, prepared by Archend 28/11/2025
25 E West and East - Elevation, prepared by 28/11/2025
Archend
26 E Section A, prepared by Archend 28/11/2025
27 E Section A2, prepared by Archend 28/11/2025
28 E Section B and B2, prepared by Archend 28/11/2025
Nature and Extent of Approved Use
4. The approved development consists of Multiple dwelling (6 x small dwellings).
Building Height
5. The maximum height of the development must not exceed 12.0 metres above ground level,
except where shown on the Approved Plans.
6. Certification must be submitted to Council from a Registered Cadastral Surveyor (Qld) which
certifies that the building does not exceed the maximum height requirement of this Decision
Notice.
Performance Bond
7. Security in the form of a cash bond or trading bank guarantee to the sum of $20,000 must
be submitted to Council, to secure performance of all conditions of this approval, prior to the
issue of a Development Permit for Operational Works. The cash bond or trading bank
guarantee will be returned on performance of the conditions of approval less any costs
incurred by Council in respect of enforcing performance of this permit. Council reserves the
right to call upon the bond or guaranteed sum to effect compliance with conditions.
Street Identification
8. The street address of the development must be clearly visible and discernible from the
primary frontage of the site by the provision of a street number and, where appropriate, the
building name.
9. The entrance to the building and lift must be clearly visible and discernible from the visitor
car parks by the provision of a directional sign where appropriate.
Building Appearance
10. External design features, materials and finishes must be as shown on the Approved Plans,
with no inclusions or alterations made without approval in writing by Council.
11. The ‘open balcony’ areas shown for Units 3,4 5 and fronting Elanda Street are not to be fully
screened and are to remain open above balustrade height or 1.2 metres above slab level.
12. External finishes of the building must be a mix of lightweight and textured external finishes,
with masonry areas incorporating a variety of textured finishes to break up the surface.
Page 3 of 22
Document Set ID: 24037249
Version: 8, Version Date: 18/12/2025
Page 4
13. All deck and balcony areas must not be enclosed with shutters, louvres, glass panelling or
the like thus remaining as open structures, except where required to satisfy any privacy
condition of this Decision Notice.
14. External colours and finishes must be of an understated colour scheme and low-reflective
roofing and cladding materials.
15. All air conditioning units or other mechanical equipment must be fully enclosed or screened
such that they are not visible from the street frontages nor adjoining properties.
16. Waste storage areas, clothes drying areas and external storage areas must be screened
from view of the street.
Protection of Privacy
17. The upper level balconies located on the eastern elevation of Units 3-6 must include either
balcony planter boxes, balustrading or fixed external screens, positioned in such a way to
obscure direct views into the habitable room windows or private open space areas of the
adjoining property. Any fixed external screen(s) must not extend more than 50% of the length
of the balcony.
Water & Sewer Connections
18. An underground connection to reticulated water and sewerage must be provided to the
premises in accordance with the standards and requirements of Northern SEQ Distributor–
Retailer Authority (Unitywater).
19. A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater)
must be submitted to Council that certifies an underground connection to reticulated water
and sewerage has been provided to the premises.
Noise – Services and Pool Equipment
20. Written certification is required from a suitably qualified person confirming that sound
pressure levels from all mechanical plant and equipment comply with the following:
a. Air-conditioning and Refrigeration
i. 7am to 10pm: Maximum level allowable = background + 5dB(A)
ii. 10pm to 7am: Maximum level allowable = background + 3dB(A)
b. Pumps, Service Room
i. 7am to 7pm: Maximum level allowable = background + 5dB(A)
ii. 7pm to 10pm: Maximum level allowable = background + 3dB(A)
iii. 10pm to 7am: No audible noise.
21. The certification must be submitted to Council, which certifies that operational noise from any
fixed plant and equipment complies and with the requirements of this Decision Notice.
External Works
22. Elanda Street must be upgraded for the length of its frontage to the subject site. The works
must be undertaken in accordance with an Operational Works approval and must include in
particular:
a. construction of kerb and channelling to the development side only
b. widening and sealing of the existing road pavement to the centreline of Elanda Street.
c. construction of a pedestrian footpath in accordance with the conditions of this Decision
Notice
d. relocation of the existing overhead electricity pole
e. removal of the existing property access and reinstatement of the kerb, footpath and
verge area to match the balance of the site frontage, including the provision of topsoil
and turf where the existing verge is grassed
Page 4 of 22
Document Set ID: 24037249
Version: 8, Version Date: 18/12/2025
Page 5
Condition 22 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Site Access and Driveways
23. A sealed access driveway must be provided from Elanda Street to all parking and
manoeuvring areas of the development. The works must be undertaken in accordance with
an Operational Works approval and must include in particular:
a. Dimensions and grades generally in accordance with Council standard drawings RS-
049 and RS-050.
b. safety measures, including warning signage, to improve driver awareness of
pedestrians and enhance pedestrian safety. Warning signage must be provided near
the exit ramp from the underground parking area to warn motorists of pedestrian
movement along the frontage street
Car Parking
24. A minimum of 12 car parking spaces must be provided and marked on the site. The works
must be undertaken in accordance with an Operational Works approval and must include in
particular:
a. 2 visitor parking spaces within the total, which are clearly marked for that purpose and
accessible at all times for visitor use;
b. dimensions, crossfalls and gradients in accordance with Australian Standard AS2890:
Parking Facilities;
25. Directional signage must be provided to direct visitors to the car parking spaces provided on
site.
Paving Treatment of Vehicle Movement Areas
26. Alternative materials, patterns, or threshold treatments must be used to articulate the
pavement treatment of vehicle movement areas.
Pedestrian and Bicycle Facilities
27. Pedestrian and bicycle facilities must be provided for the development. The works must be
undertaken in accordance with an Operational Works approval and must include in particular:
a. A 1.5 metre wide footpath within the road verge for the entire length of the site’s
frontage to Elanda Street
Condition 27 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Stormwater Drainage
28. The site must be provided with a stormwater drainage system connecting to a lawful point of
discharge. The works must be undertaken in accordance with an Operational Works
approval and must include in particular:
a. Post-development peak flow rates must not exceed pre-development peak flow rates
up to a 1% AEP event, accounting for climate change and incorporating appropriate
detention measures
Condition 28 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Services
29. Unless otherwise stipulated by telecommunications legislation at the time of construction, the
development must be provided with all necessary conduits, pits and pipes to accommodate
the future connection of optic fibre technology telecommunications.
Page 5 of 22
Document Set ID: 24037249
Version: 8, Version Date: 18/12/2025
Page 6
30. Certification must be submitted to Council from all relevant service providers (Energex, NBN
and Unitywater) which certifies that the development has met the requirements of this
Decision Notice and all applicable legislation at the time of construction.
Geotechnical Stability
31. All works must be carried out in accordance with the recommendations contained in the
Proposed Unit Development report prepared by Tectonic listed within this Decision Notice.
Earthworks and Retaining Walls
32. All earthworks and associated batters/retaining structures, both above and below ground
level, both temporary and permanent, must be contained entirely within the subject site
unless written permission from the respective landowner(s) is provided to Council. All
earthworks must be undertaken in accordance with the provisions of Australian Standard
AS3798: Guidelines on Earthworks for Commercial and Residential Developments.
33. Where the development involves excavation or filling over, or adjacent to, drainage, water
supply or sewerage infrastructure, all access chamber surface levels must be adjusted to
provide a freeboard of 100mm above the finished ground surface level.
34. All retaining walls must be designed and constructed in accordance with the planning scheme
and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that
are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade
safety fence.
Landscaping Works
35. The development site must be landscaped. The works must be undertaken in accordance
with an Operational Works approval and the Noosa Plan for that specific area and must
include in particular:
a. the works shown on the reference plans.
b. The area between the southern boundary and the proposed footpath, landings, and
stairs must be landscaped. The works must include the provision of tall tree species
capable of growing to a minimum of 5 metres tall, to assist in softening the built form
of the development when viewed from neighbouring properties and Councils footpath.
c. Landscaping plans that substitute Nandina domestica for a variety of shrubs from the
Noosa Plan 2020 PSP 2 – Landscape.
d. The area between the swimming pool and rear fence is to be screened by a 3.5 metre
wide buffer densely planted with trees and shrubs.
e. Landscape plans that incorporate additional trailing vines that can achieve the
architectural intent of the submitted renders.
f. Vegetated screening of any electrical transformers, bin storage areas and the like from
the road frontage
g. Provision of 1 street tree within the road reserve for every 8 metres of road frontage
36. All landscape works must be established and maintained in accordance with the approved
design for the life of the development, and in a manner that ensures healthy, sustained and
vigorous plant growth. All plant material must be allowed to grow to full form and be
refurbished when its life expectancy is reached.
37. The existing trees located within neighbouring properties must be assessed by a qualified
person* and retained and protected in accordance with an Arborist Report (or part thereof)
prepared by a qualified person* and endorsed through an Operational Works approval.
38. All planting areas on the eaves must be planted and maintained at all times, with replacement
planting undertaken promptly where plants fail or do not have a healthy and vigorous growth.
Page 6 of 22
Document Set ID: 24037249
Version: 8, Version Date: 18/12/2025
Page 7
39. All planting areas on the northern side of the Unit 5 - Roof terrace is to contain suitable dense
screening and landscaping to ensure a minimum height of 2.0 metres. The landscaping is
to ensure overlooking is minimised and visual privacy is maintained to adjacent roof terraces
and private open spaces.
Waste Management
40. A waste storage area must be designed and maintained in accordance with Planning
Scheme Policy PSP9 Waste Management and the Noosa Plan’s Waste Management Code.
The waste storage area must be:
a. imperviously paved and correctly sized for all refuse and recycling containers;
b. bunded and graded so that wastewater and bin leakage drain to the sewer;
c. provided with a conveniently located hosecock and backflow prevention device,
connected to a water supply to service the area; and
d. roofed or otherwise covered.
Community Management Statement
41. Any proposed Community Management Statement required for the development pursuant to
the Body Corporate and Community Management Act 1997 must be submitted to Council for
endorsement at the same time as submission of the Building Format Plan (or similar) to
Council for compliance assessment.
42. All clauses and by-laws of the proposed Community Management Statement must accord
with the requirements of this Decision Notice and must include the following additional
clauses:
a. The dwelling units are not permitted to be used for short term accommodation, unless
where identified as accepted development by the Noosa Plan or where there is a
Development Permit for Material Change of Use for Short Term Accommodation in
effect. Short term accommodation means the use of the premises for providing
accommodation of less than 3 consecutive months to tourists or travellers.
Page 7 of 22
Document Set ID: 24037249
Version: 8, Version Date: 18/12/2025
Page 8
DEVELOPMENT PERMIT FOR OPERATIONAL WORKS (OPW24/0202)
ROAD WORK, DRAINAGE WORK, STORMWATER, EARTHWORKS, CAR PARKING &
LANDSCAPING
Approved Plans
1. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
010 B Siteworks Overall Layout Ground 26 August
2025
Prepared by RECOR
As Annotated by Council
011 B Siteworks Overall Layout Basement 26 August
2025
Prepared by RECOR
012 B Detailed Ground Level Layout 26 August
2025
Prepared by RECOR
014 B Vehicle Crossover Longitudinal Section 26 August
2025
Prepared by RECOR
015 B Footpath Longitudinal Section 26 August
2025
Prepared by RECOR
As Annotated by Council
016 B Roadworks Details 26 August
2025
Prepared by RECOR
017 B Driveway Vertical Vehicle Tracking 26 August
2025
Prepared by RECOR
020 B Bulk Earthworks Layout Plan 26 August
2025
Prepared by RECOR
021 B Bulk Earthworks Sections Sheet 1 26 August
2025
Prepared by RECOR
022 B Bulk Earthworks Sections Sheet 2 26 August
2025
Prepared by RECOR
042 B Stormwater Longitudinal Sections Sheet 1 26 August
2025
Prepared by RECOR
043 B Stormwater Longitudinal Sections Sheet 2 26 August
2025
Prepared by RECOR
Page 8 of 22
Document Set ID: 24037249
Version: 8, Version Date: 18/12/2025
Page 9
041 B Stormwater Catchment Layout 26 August
2025
Prepared by RECOR
044 A Stormwater Details 26 August
2025
Prepared by RECOR
LD1 F General Notes, Sheet Layout & Site 02/12/2025
Location prepared by Anembo Consultants
LD2 F Project Specifications prepared by Anembo 02/12/2025
Consultants
LD3 F Project Specifications, Annual 02/12/2025
Maintenance & Finishes Schedule
prepared by Anembo Consultants
LD4 F Plant Schedules prepared by Anembo 02/12/2025
Consultants
LD5 F Typical Details prepared by Anembo 02/12/2025
Consultants
LP1 F Landscape Plan (Ground 1/2) prepared by 02/12/2025
Anembo Consultants
LP2 F Landscape Plan (Ground 2/2) prepared by 02/12/2025
Anembo Consultants
LP3 F Landscape Plan (First Level) prepared by 02/12/2025
Anembo Consultants
LP4 F Landscape Plan (Second Floor) prepared 02/12/2025
by Anembo Consultants
LP5 F Landscape Plan (Roof) prepared by 02/12/2025
Anembo Consultants
Currency Period
2. This development approval lapses if the requirements of the conditions have not been
completed and lodged with Council by 11 August 2027, unless an application to extend the
currency period is approved by Council.
SITE SPECIFIC CONDITIONS
Bonds
3. A site control and/or compliance bond of $10,000 is to be submitted to Council prior to the
pre-start meeting. The pre-start meeting will only be held once Council's Construction
Engineering Officer has confirmation that the bond monies have been received by Council.
The bond will be refunded less any costs incurred by Council in ensuring compliance with
these conditions or any additional inspections incurred for substandard work or work
undertaken not in accordance with this permit.
4. Bonds must:
a. meet the requirements of Council’s relevant Planning Scheme Policy for performance
and uncompleted works;
Page 9 of 22
Document Set ID: 24037249
Version: 8, Version Date: 18/12/2025
Page 10
b. be calculated using a schedule of works and relevant bond equation;
c. be lodged with Council and accompanied by the Bond Administration Fee/s; and
d. be requested for release by writing to Council, when relevant approval requirements
have been met.
PRIOR TO COMMENCEMENT OF WORKS
Engineering
5. All necessary approvals from external service providers (e.g., Unitywater) and external
parties on which the development works are proposed have been obtained and a copy
supplied to Council.
6. A condition report of the drainage system must be completed for agreement at the prestart
meeting. The condition report is to include a CCTV inspection of the existing field inlet
(labelled as “7/1”) to the next downstream structure, inclusive.
7. A condition report including photographs of the frontage of the site must be completed and
submitted to council at the prestart meeting / prior to any works commencing.
8. Certificates demonstrating currency of public liability insurance and works insurance covering
the works must be submitted to Council prior to the prestart meeting.
9. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. Civil engineering works;
b. Landscape works;
c. Erosion and sediment control works; and
d. Other relevant parties.
10. A Construction Management Plan must be submitted to Council prior to the pre-start meeting
and must specifically address the following:
a. Traffic Management during all aspects of the construct phase including:
i. A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
Control Devices (MUTCD) detailing all temporary signage and traffic control
measures prior to construction.
ii. Maintenance of safe vehicle and pedestrian access across the frontage of the
site both during daily construction and after daily construction has ceased.
iii. Proposed fencing to the site during the construction phase of the development.
iv. Adequate parking arrangements for construction workers.
v. No queuing of trucks is permitted on residential streets, especially prior to
7.00am. Further parked trucks must have engines turned off
Maintenance and protection of water quality and existing drainage lines through the construction
site through the implementation of appropriate erosion and sediment control measures.
Works programme identifying key components of the works and their respective durations.
Establishment of a communication protocol with the general public, adjoining owners, emergency
services and local businesses to advise of agreed construction times, impacts on traffic and
services and other relevant issues.
Include a post out to the local residents and businesses advising of the proposed development,
the expected time frames and the site contact details.
Include signage in prominent locations on the boundaries of the site advising of the proposed
development, the expected time frames and the site contact details.
Page 10 of 22
Document Set ID: 24037249
Version: 8, Version Date: 18/12/2025
Page 11
identification of complaint management procedures including:
i. contact details for the on-site manager; and
ii. dispute resolution procedures.
11. Any changes to the details associated with the supervising RPEQ or Principal Contractor
during construction, must be notified to council in writing within five business days of the
change occurring.
12. Any conflict between the development and an existing or proposed service must be referred
to the relevant service authority for determination prior to commencement of works.
DURING CONSTRUCTION
Engineering
13. The developer must meet any costs to repair damage to any Council asset during
construction, where damage is a result of the development works. Damage to assets must
be repaired immediately where it creates a hazard to the community. In circumstances where
the damage does not create a hazard to the community, it must be repaired immediately on
completion of the works associated with the development.
14. All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
who is independent of the Developer and Principal Contractor, and they must certify that all
works conform to the Operational Works permit. Where municipal works are involved, such
confirmation must be submitted for the respective hold points prior to any site inspection by
Council Officers.
15. All works must be constructed and work procedure undertaken in accordance with:
a. The approved plans/documents and conditions detailed in this Decision Notice.
b. All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines.
c. The relevant conditions of the higher order Material Change of Use approval viz
MCU24/0153 to which this approval relates.
d. The latest version of the Healthy Waterways document “Water Sensitive Urban Design
Technical Design Guidelines for South East Queensland” for all water quality devices
to be constructed on site.
Retention of Existing Trees and Vegetation
16. All trees and vegetation identified for retention must be protected in accordance with AS
4970, Protection of trees on development sites.
17. A qualified person * must be engaged for the duration of the works to:
a. Supervise tree protection within the development site and frontages, prior to, during
and following construction in accordance with AS 4970, Protection of trees on
development sites.
b. Supervise and undertake necessary tree protection for all trees affected by the
development on neighbouring Lots. This includes tree identified in the approved
arborist report as outside project scope within the neighbouring properties east of the
development site. Where trees within neighbouring properties are found to be unsafe
due to works relating to this development approval, the developer is solely responsible
for the removal and replacement of these trees.
c. Oversee approved tree removal in proximity to retained trees.
*(Refer to Advisory Note)
Vegetation Clearing
18. Removal of trees and vegetation must be undertaken by a qualified person* and must
include:
Page 11 of 22
Document Set ID: 24037249
Version: 8, Version Date: 18/12/2025
Page 12
a. No damage to vegetation for retention.
b. Legal disposal of all removed vegetation and debris.
Fauna Management
19. Prior to felling or pruning, all trees are to be checked for wildlife (i.e. koalas, possums, birds
etc.) If wildlife is present, the tree vegetation must not be felled or pruned until the wildlife
has left vegetation or has been relocated by a qualified fauna spotter catcher.
*(Refer to Advisory Note)
Landscaping Works
20. Landscape works must be supervised, undertaken and certified by qualified persons*. All
works must be completed in accordance with this Decision Notice.
(* Refer to Advisory Note)
21. Public amenity trees* must:
a. Meet AS 2302 – Tree Stock for landscape use.
b. Be located in accordance with engineering requirements for safe vehicle and
pedestrian sight lines.
*(Refer to Advisory Note)
22. Turfed areas must be free of pest, diseases and weeds and level with adjoining surfaces.
Roadworks (External Roadworks & Road Widening Works)
23. All pavement widening or construction of new pavement must join neatly to the existing
pavement so that there are no irregularities in line or level resulting at or adjacent to the join
for the length of the construction. Where necessary the existing pavement must be brought
to a satisfactory standard to allow for the above.
24. All street surfacing must consist of a minimum depth of 30mm of an approved hot mixed
asphaltic concrete, unless other pavement types are approved as feature areas in
intersection thresholds, speed control devices, turning areas, indented parking etc.
Pavement Design and Construction
25. The pavement designs shown on the engineering drawings are not approved. To attain
approval for the pavement design, the following details must be submitted and certified by
an RPEQ with the proposed pavement design.
a. The design CBR must be based on the four day soaked CBR value for the subgrade
material.
b. The design subgrade CBR must be representative of each homogenous insitu section
of finished subgrade. With respect to each section:
i. For four or less test results, the design CBR must be taken as the least estimated
insitu CBR result.
ii. For five or more test results, the design CBR must be taken as the 10th percentile
of all estimated insitu CBR results.
c. The samples must be taken generally in the position of the outer wheel path on both
sides of the proposed road. A sketch plan showing the location of all tests must be
submitted with the test results for pavement design approval.
d. Where imported material has been (or is proposed to be) used for subgrade
replacement, and the depth of the imported material is less than 300mm, the pavement
design CBR must be based on the testing results of the insitu material and not the
imported material.
Page 12 of 22
Document Set ID: 24037249
Version: 8, Version Date: 18/12/2025
Page 13
26. At the time of subgrade inspection, the subgrade must exhibit no visible signs of deformation
under proof rolling by a fully loaded water truck. The pavement subgrade will not be passed
until this requirement has been achieved.
27. Pavement design for privately owned works must be undertaken in accordance with the
relevant standards. Structural integrity of the driveway and car park areas will remain the
responsibility of the property owner/developer and must be certified by an RPEQ.
Works within Road Reserve/Reinstatement
28. Safe pedestrian and vehicle access on all streets in the vicinity of the development must be
maintained at all times. Should footpath/road closures be necessary to carry out construction
works, Council’s Engineering Officer must be notified prior to the proposed closure and all
requirements complied with.
29. All frontage works must match neatly with existing road and verge/footpath features.
Additional works beyond the frontage may be required to provide an acceptable transition to
existing road and verge/footpath profiles.
30. Electrical conduits or other services proposed to be installed within existing and proposed
road reserves under existing sealed carriageways, concrete pathways, concrete/sealed
driveways or significant vegetation must be installed by boring. Trenching is not permitted,
unless specifically approved by Council.
Pathways
31. All pathways must be constructed in accordance with the following requirements:
a. All footpath/cycleway must comply with Council’s Standard Drawing SEQ R-065.
b. Provision must be made for disabled access at all kerb crossings associated with
pathways, in accordance with Council's current standards.
c. All paths must have a slip resistant surface.
d. Expansion and contraction joints must provide a flush finish. Installation of joints by
saw cutting is preferred to ensure a smooth ride for cyclists.
e. The required work includes any modifications to ensure the footpath finishes flush with
all existing service covers and the like, or alternatively these services are raised or
altered, so as not to create a pedestrian safety hazard.
32. Pathways must:
a. terminate in a manner that ensures smooth transition to existing surfaces for public
safety.
b. be designed and constructed to comply with the Disability Discrimination Act (DDA),
Access to Premises Standard, Austroads and relevant sections of AS1428 Design for
access and mobility.
Site Access and Driveways
33. Driveway crossovers must be constructed in accordance with council’s Standard Drawings
RS-049, RS-050 and any associated addendum.
34. Any existing unnecessary or redundant property accesses must be removed, and the kerb,
footpath and verge area reinstated to match the existing footpath and/or verge treatments.
Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed
or turf and must be maintained by the developer until established.
35. The following must be complied with during the construction of the required
crossover/driveway:
a. The driveway surfacing must consist of either an approved hot mixed asphaltic
concrete or patterned/plain concrete.
Page 13 of 22
Document Set ID: 24037249
Version: 8, Version Date: 18/12/2025
Page 14
b. The driveway must be constructed so as not to concentrate stormwater runoff onto
neighbouring properties.
c. Underground service conduits for water supply, electricity and any other services must
be provided as part of the access driveway.
d. Where there is an existing pedestrian path, a matching crossfall must be provided for
the driveway on the alignment of the path, for the full width of the path.
e. The property access must be located a minimum of 1m clear of existing power poles,
streetlights or other signage. The developer is responsible for any necessary relocation
of existing services to provide this clearance and must contact the relevant service
authorities and comply with their requirements in relation to these works.
Earthworks and Retaining Walls
36. All earthworks shall be undertaken in accordance with the provisions of AS 3798 Guidelines
on Earthworks for Commercial and Residential Development, with geotechnical testing
undertaken in accordance with Section 8 of the Standard, and to a minimum of ‘Level 1’ as
defined in Appendix B. Test results as required by AS 3798, and a certificate of quality and
uniformity of fill shall be provided by a RPEQ and submitted to Council prior to the
commencement of the use.
37. All earthworks and associated batters/retaining structures, both above and below ground
level, both temporary and permanent, must be contained entirely within the subject site
unless written permission from the respective landowner(s) is provided to Council.
38. Fall protection must be provided to retaining walls that are over 1m high.
39. Slope and batters are a maximum grade of:
a. 1 in 6 where in proximity to waterbodies.
b. 1 in 4 for grassed areas.
c. 1 in 3 for planted areas.
d. 1 in 2 for combined structural engineering and planting solutions.
Stormwater Drainage
40. Appropriate scour protection must be provided at the outlet of all stormwater pipes including
temporary outlets.
41. Works associated with this permit must not adversely impact on the existing drainage
conditions on other properties (e.g., by blocking or interfering with natural overland flows).
42. Construction of all internal stormwater drainage works must comply with the relevant
section/s of Australian Standard AS/NZS 3500.3.
Erosion and Sediment Control
43. Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection
Regulation 2019) must not be released from the site or to waters within the site, or be likely
to be released should rainfall occur, unless all reasonable and practicable measures are
taken to prevent or minimise the release and concentration of contamination.
44. Sediment and erosion control measures must be in place prior to works commencing. If such
measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such
fines can be issued if sediments from the site are found to enter or have the potential to enter
Council’s stormwater system, natural waterways, any downstream stormwater filtration
system or adversely impacting on other properties. The sediment and erosion control design
and measures have NOT been approved, it is the site's Supervising Engineer who is
responsible for ensuring that the sediment and erosion control measures have:
a. Been duly designed by an RPEQ or CPESC and constructed in accordance with "best
practise" methods;
Page 14 of 22
Document Set ID: 24037249
Version: 8, Version Date: 18/12/2025
Page 15
b. Been revised by an RPEQ or CPESC to address the issues raised by changes in the
projected construction schedule and/or methods;
c. Been revised to address predicted rainfall events; and
d. Achieve the desired environmental outcomes.
Council may request further controls to be installed should the implemented measures be
found inefficient.
45. The erosion and sediment control measures must be designed, installed and maintained in
accordance with the supervising engineer instructions and the current best practice
standards.
(*) Refer to Advisory Note
46. The developer must ensure non-essential exposure of soil is prevented by restricting the
extent of disturbance and minimising the duration of soil exposure to adverse weather
conditions and effectively turf, cover or stabilise any disturbed area without delay and prior
to rainfall occurring.
47. The developer must ensure sediment does not leave the site or enter onto adjoining
properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or
machinery. It is essential to implement appropriate approved erosion and sediment control
measures throughout the site during all phases of construction including vehicle shakedown
pad/grid (or similar) at the access to the construction site. Where sediments or other
contaminants are deposited on a road, they must be removed so as not to enter Council’s
drainage system or waterways.
48. Prior to the completion of the development and commencement of use, all site surfaces must
be effectively stabilised using methods which have achieved effective short-term stabilisation
and which will continue to achieve effective stabilisation in the medium to long-term.
For the purpose of this condition, an effectively stabilised surface is defined as one that does
not, or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion
or lead to sedimentation, or lead to water contamination.
Damage to Services and Assets
49. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
FOLLOWING CONSTRUCTION AND PRIOR TO THE COMMENCEMENT OF THE USE
Supervision/Certification
50. Prior to commencement of use the following (prepared by respective qualified persons* and
certifying compliance with approvals) must be submitted to Council:
a. Landscaping certification confirming all works have been constructed in accordance
with conditions of approval.
Certification
51. Upon completion of the work a certificate must be issued by an RPEQ certifying that the
works have been constructed in accordance with the Operational Works permit.
Page 15 of 22
Document Set ID: 24037249
Version: 8, Version Date: 18/12/2025
Page 16
As Constructed Plans and ADAC XML Files (Council)
52. Prior to acceptance of civil works to become Council assets “On Maintenance”, satisfactory
“As-Constructed” records must be submitted to Council. The bundle of “As Constructed”
a. As-Constructed Engineering Drawings. Data is to be submitted in an electronic drawing
file format (.dwg), with all plans clearly endorsed “As-Constructed”, along with the
accompanying hardcopies (PDFs of the As-Constructed .dwg drawing files), and;
b. ADAC XML Digital File. ADAC File format (ADAC - Asset Design As Constructed)
prepared in accordance with industry standards and recorded in “MGA - UTM56 /
GDA94” projection.
Please Note: Further information and advice relating to the as-constructed drawing
presentation, as-constructed survey capture and associated guidelines for preparation
of a compliant ADAC XML digital file are available on the webpage titled “As-
Constructed Guidelines” and accessible at the Noosa Council Website: Planning &
Development / Development Tools & Guidelines / As-Constructed Guidelines.
c. The “As-Constructed” drawings will require certification by a:
i. Qualified experienced Civil Engineer (RPEQ) confirming design intent and
conformance with applicable standards and specifications, along with the
relevant descriptions of assets, services and structures and;
ii. Registered Cadastral Surveyor (Qld) in regard to the cadastral and locational
information, levels and applicable survey datum.
d. The data must be in accordance with Council’s “Planning Scheme Policy 6 –
Engineering Design Standards”, and fully detail the levels for all engineering works
including but not limited to the drainage network and structures, finished ground and
pavement surface levels.
On Maintenance
53. All municipal works must be accepted ‘On Maintenance’ by Council in accordance with
Council’s relevant Planning Scheme Policy prior to the commencement of the use. To
achieve ‘On Maintenance’, the supervising RPEQ must submit to Council:
a. certification that all works have been undertaken and completed in accordance with the
requirements of this Permit.
b. as Constructed details in accordance with Council’s Planning Scheme Policy.
c. maintenance and operational manuals for all proprietary or site-specific devices
Off Maintenance
54. Prior to requesting an Off Maintenance inspection, the developer must provide a written
request for the Off Maintenance inspection.
55. A re-inspection fee in accordance with Council’s Fees and Charge Register will be charged
where:
a. a Council inspection reveals works do not comply with approval requirements.
b. submitted certification falsely states works comply with approval requirements.
56. A final inspection and approval of the new driveway and completed reinstatement works by
Council’s Inspector is required. Please contact Council on 5329 6500 to arrange for the
inspection.
Page 16 of 22
Document Set ID: 24037249
Version: 8, Version Date: 18/12/2025
Page 17
5. REFERENCE DOCUMENTS
Plan No. Rev. Plan/Document Name Date
24265-001 0 Proposed Unit Development prepared by 30/09/2024
tectonic
- - Technical Memorandum 26 August 2025
Prepared by RECOR
LD1 D General Notes, Sheet Layout & Site Location 21/03/25
prepared by Anembo Consultants
LD2 D Project Specifications prepared by Anembo 21/03/25
Consultants
LD3 D Project Specifications, Annual Maintenance & 21/03/25
Finishes Schedule prepared by Anembo
Consultants
LD4 D Plant Schedules prepared by Anembo 21/03/25
Consultants
LD5 D Typical Details prepared by Anembo 21/03/25
Consultants
LP1 D Landscape Plan (Ground 1/2) prepared by 21/03/25
Anembo Consultants
LP2 D Landscape Plan (Ground 2/2) prepared by 21/03/25
Anembo Consultants
LP3 D Landscape Plan (First Level) prepared by 21/03/25
Anembo Consultants
LP4 D Landscape Plan (Second Floor) prepared by 21/03/25
Anembo Consultants
LP5 D Landscape Plan (Roof) prepared by Anembo 21/03/25
Consultants
6. REFERRAL AGENCIES
Not applicable.
7. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:
MATERIAL CHANGE OF USE
Aboriginal Cultural Heritage Act 2003
1. There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who
carries out an activity must take all reasonable and practicable measures to ensure the
activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply with the
Page 17 of 22
Document Set ID: 24037249
Version: 8, Version Date: 18/12/2025
Page 18
duty of care. Substantial monetary penalties may apply to individuals or corporations
breaching this duty of care. Injunctions may also be issued by the Land and Resources
Tribunal, and the Minister administering the ACH Act can also issue stop orders for an activity
that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value
of Aboriginal cultural heritage.
You should contact the Cultural Heritage Unit to discuss any obligations under the ACH Act.
Equitable Access and Facilities
2. The plans for the proposed building work have NOT been assessed for compliance with the
requirements of the National Construction Code - Building Code of Australia (Volume 1) as
they relate to people with disabilities. Your attention is also directed to the fact that in addition
to the requirements of the National Construction Code as they relate to people with
disabilities, one or more of the following may impact on the proposed building work:
a. the Disability Discrimination Act 1992 (Commonwealth);
i. the Anti-Discrimination Act 1991 (Queensland); and
ii. the Disability (Access to Premises – Buildings) Standards.
Development Compliance Inspection
3. Prior to the commencement of the use, please contact Council's Development Assessment
Branch to arrange a Development Compliance Inspection.
Advertising Devices
4. All Advertising Devices must comply with Schedule 10 of Subordinate Local Law No.1
(Administration) 2015 including both temporary and permanent signage. All freestanding,
pylon or pole signs or signage that is illuminated requires approval from Council prior to being
installed. All signage identified in s6 of Schedule 10 of Subordinate Local Law No. 1 is
prohibited from being erected in the Shire.
Infrastructure Charges
5. All developments and/or changes to existing developments may require payment of
“Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
made pursuant to the planning legislation and regulations current at the time of issue. For
further information, please refer to https://www.noosa.qld.gov.au/planning-
development/development-tools-guidelines/infrastructure-charges
Performance Bond Agreement
6. An applicant for a development application may make an agreement with an assessment
manager, referral agency or other person to establish the responsibilities, or secure the
performance, of a party to the agreement about a development condition.
Submission of Amended Plans Required
7. The conditions of this Decision Notice require resubmission of plans to Council with
amendments. Please address the amended plan/s to Council’s Development Assessment
Branch with the Reference No. MCU24/0106 & OPW24/0202.
Building and Construction Industry (Portable Long Service Leave) Levy
8. The QLeave levy must be paid prior to the issue of a development permit where it is required.
Council will not be able to issue a Decision Notice without receipt of details that the Levy has
been paid.
Qualified Person
9. For the purpose of preparing a Geotechnical Report, and for certifying geotechnical stability
for the development, a qualified person is considered to be a person who:
a. is a Registered Professional Engineer of Queensland (RPEQ); and
i. has a degree in civil engineering or engineering geology; and
Page 18 of 22
Document Set ID: 24037249
Version: 8, Version Date: 18/12/2025
Page 19
ii. has a minimum of 5 years experience in the field of geotechnical engineering or
engineering geology.
Co-ordination of Operational Works Assessment
10. Additional application fees apply to Operational Work applications where the different
aspects of the works are lodged separately. Significant savings in application fees will result
if all works are lodged in a single application.
Preparation of a Preliminary Construction Management Plan
11. A preliminary Construction Management Plan must be submitted with the Operational Works
application and must address the following:
a. Safley managing pedestrian traffic on all adjacent footpaths
i. appropriate traffic signage in accordance with the Manual of Uniform Traffic
Control Devices (MUTCD)
ii. provision for safe pedestrian access across the frontage of the site both during
daily construction and after daily construction has ceased.
Road Reserve Permit
12. This development permit provides the applicant with written authority to undertake the
development in accordance with the conditions. Any additional activities that are undertaken
inside Council’s road reserve for the purpose of acting on this development permit may
require a Road Reserve Permit. These additional activities may include, but are not limited
to, hoarding, pedestrian diversions, laneway closures, etc. To apply for a Road Reserve
Permit, or for more information, Contact Council’s Road Reserve Officer at
[email protected] Act 2014 – Fire Ant Control
13. Developers must remain vigilant for the presence of fire ants. Under the Biosecurity Act 2014,
individuals and businesses are responsible for ensuring that they follow the movement
controls for specific organic materials to help prevent the spread of fire ants within South
East Queensland’s fire ant biosecurity zones. Movement of a fire ant carrier from within a fire
ant biosecurity zone may need a biosecurity instrument permit. More information is available
on https://www.fireants.org.au/treat/business-andindustry/movement-controls
OPERATIONAL WORKS
Building and Construction Industry (Portable Long Service Leave) Levy
14. The QLeave levy must be paid prior to the issue of a development permit where it is required.
Council will not be able to issue a Decision Notice without receipt of details that the Levy has
been paid.
General Advisory Notes
15. As this driveway is a private structure, the owner bears full responsibly for the standard of its
construction, maintenance and any liabilities associated with its construction. It is
recommended that professional advice be sought for the construction of the driveway to
ensure that the driveway is constructed in accordance with standard drawings RS-049, RS-
050 and any associated addendum.
16. Council has undertaken an audit check of the Operational Works drawings in relations to the
proposed works. A detailed check of the calculations and drawings has not been undertaken,
as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of
the engineering design. Council reserves the right to require further amendments and/or
additions at a later date should design errors become apparent.
17. Council reserves the right to call up any performance bond held or levy charges against the
property, should emergency works be required to be undertaken by Council to make the site
safe due to inactivity on the development site for extended periods of time.
Page 19 of 22
Document Set ID: 24037249
Version: 8, Version Date: 18/12/2025
Page 20
18. Should any changes or modifications to the approved plans be required as a result of
construction constraints, a “Request to change an existing approval” under the Planning Act
2016 must be made. Amended plans clearly indicating the changes must be lodged with this
application along with the appropriate fees.
Prestart, On and Off Maintenance Inspections Request
19. Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5
business days’ notice of preferred inspection time.
20. If Council officers are required to undertake additional inspections of the same works, a
reinspection fee will be applicable in accordance with Council’s Fees and Charges register
applicable at the time.
21. A minimum maintenance period of 12 months will apply to all municipal works and thereafter
until such time as the works are performing in accordance with the approved design unless
noted otherwise.
Environmental Advisory Notes
22. The Environmental Protection Act 1994 states that a person must not carry out any activity
that causes, or is likely to cause, environmental harm unless the person takes all reasonable
and practicable measures to prevent or minimise the harm. Environmental harm includes
environmental nuisance. In this regard persons and entities, involved in the civil, earthworks,
construction and landscaping phases of this development are to adhere to their ‘general
environmental duty’ to minimise the risk of causing environmental harm.
Erosion and Sediment Control
23. Accepted best practice standards include International Erosion Control Association
Australasia Best Practice Erosion and Sediment Control.
24. Qualified Person, for the purpose of erosion and sediment control is a Certified Professional
in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional
Engineer of Queensland (RPEQ).
25. As a general rule, a site is determined to have achieved effective short-term stabilisation if
at the time of the plan sealing inspection:
a. Methods of stabilisation are:
• appropriate for slopes and slope lengths; and
• are consistent with best practice environmental management practices such as in
the Manual for Erosion and Sediment Control or the IECA Manual; and
b. Stormwater runoff from the site is not currently, and is not likely to result in visible
evidence of sedimentation or erosion, or lead to water contamination.
Biosecurity Act 2014 – Fire Ant Control
26. Developers must remain vigilant for the presence of fire ants. Under the Biosecurity Act 2014,
individuals and businesses are responsible for ensuring that they follow the movement
controls for specific organic materials to help prevent the spread of fire ants within South
East Queensland’s fire ant biosecurity zones. Movement of a fire ant carrier from within a fire
ant biosecurity zone may need a biosecurity instrument permit. More information is available
on https://www.fireants.org.au/treat/business-andindustry/movement-controls.
8. PROPERTY NOTES
Not applicable.
9. VARIATION APPROVAL DETAILS
Not applicable.
Page 20 of 22
Document Set ID: 24037249
Version: 8, Version Date: 18/12/2025
Page 21
10. FURTHER DEVELOPMENT PERMITS REQUIRED
Type of Development Permit Required Subject of the required Development Permit
Development Permit for Building Works All building work.
11. SUBMISSIONS
Not applicable.
12. RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Planning Act 2016 is attached.
During the appeal period, you as the applicant may suspend your appeal period and make written
representations to Council about the conditions contained within the development approval. If
Council agrees or agrees in part with the representations, a negotiated decision notice will be
issued. Only one negotiated decision notice may be given.
13. OTHER DETAILS
If you wish to obtain more information about the decision, electronic copies are available online at
www.noosa.qld.gov.au or at Council Offices.
Yours faithfully,
Andrew Gaffney
Senior Development Planner | Development Assessment
Development & Regulation
Enc: Appeal Rights
Infrastructure Charge Notice
Approved Plans/Documents
DECISION NOTICE HISTORY
• Original Decision Notice – 11 August 2025.
• Negotiated Decision Notice – 15 December 2025, with an amendment to Decision Details, amend condition 3 of MCU and
include additional conditions 3-56 for OPW,
Page 21 of 22
Document Set ID: 24037249
Version: 8, Version Date: 18/12/2025
Page 22
Appeal Rights
PLANNING ACT 2016 & PLANNING REGULATION 2017
Chapter 6 Dispute resolution (3) The appellant or, for an appeal to a tribunal, the registrar must,
within the service period, give a copy of the notice of appeal to –
Part 1 Appeal rights
(a) the respondent for the appeal; and
229 Appeals to tribunal or P&E Court
(b) each co-respondent for the appeal; and
(1) Schedule 1 of the Planning Act 2016 states –
(c) for an appeal about a development application under schedule
(a) Matters that may be appealed to –
1, table 1, item 1 – each principal submitter for the
(i) either a tribunal or the P&E Court; or development application; and
(ii) only a tribunal; or (d) for and appeal about a change application under schedule 1,
table 1, item 2 – each principal submitter for the change
(iii) only the P&E Court; and
application; and
(b) The person-
(e) each person who may elect to become a co-respondent for the
(i) who may appeal a matter (the appellant); and appeal, other than an eligible submitter who is not a principal
submitter in an appeal under paragraph (c) or (d); and
(ii) who is a respondent in an appeal of the matter; and
(f) for an appeal to the P&E Court – the chief executive; and
(iii) who is a co-respondent in an appeal of the matter; and
(g) for an appeal to a tribunal under another Act – any other
(iv) who may elect to be a co-respondent in an appeal of the
person who the registrar considers appropriate.
matter.
(4) The service period is –
(2) An appellant may start an appeal within the appeal period.
(a) if a submitter or advice agency started the appeal in the P&E
(3) The appeal period is –
Court – 2 business days after the appeal has started; or
(a) for an appeal by a building advisory agency – 10 business
(b) otherwise – 10 business days after the appeal is started.
days after a decision notice for the decision is given to the
agency; or (5) A notice of appeal given to a person who may elect to be a co-
respondent must state the effect of subsection (6).
(b) for an appeal against a deemed refusal – at any time after the
deemed refusal happens; or (6) A person elects to be a co-respondent by filing a notice of election,
in the approved form, within 10 business days after the notice of
(c) for an appeal against a decision of the Minister, under chapter
appeal is given to the person.
7, part 4, to register premises or to renew the registration of
premises – 20 business days after a notice us published under 231 Other appeals
section 269(3)(a) or (4); or
(1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
(d) for an appeal against an infrastructure charges notice – 20 the Supreme Court decides a decision or other matter under this
business days after the infrastructure charges notice is given Act is affected by jurisdictional error, the decision or matter is non-
to the person; or appealable.
(e) for an appeal about a deemed approval of a development (2) The Judicial Review Act 1991, part 5 applies to the decision or
application for which a decision notice has not been given – matter to the extent it is affected by jurisdictional error.
30 business days after the applicant gives the deemed
(3) A person who, but for subsection (1) could have made an
approval notice to the assessment manager; or
application under the Judicial Review Act 1991 in relation to the
(f) for any other appeal – 20 business days after a notice of the decision or matter, may apply under part 4 of that Act for a
decision for the matter, including an enforcement notice, is statement of reasons in relation to the decision or matter.
given to the person.
(4) In this section –
Note – decision includes-
See the P&E Court Act for the court’s power to extend the appeal
(a) conduct engaged in for the purpose of making a decision; and
period.
(b) other conduct that relates to the making of a decision; and
(4) Each respondent and co-respondent for an appeal may be heard
in the appeal. (c) the making of a decision or failure to make a decision; and
(5) If an appeal is only about a referral agency’s response, the (d) a purported decision; and
assessment manager may apply to the tribunal or P&E Court to
(e) a deemed refusal.
withdraw from the appeal.
non-appealable, for a decision or matter, means the decision or
(6) To remove any doubt. It is declared that an appeal against an
matter-
infrastructure charges notice must not be about-
(a) is final and conclusive; and
(a) the adopted charge itself; or
(b) may not be challenged, appealed against, reviewed, quashed,
(b) for a decision about an offset or refund-
set aside or called into question in any other way under the
(i) the establishment cost of trunk infrastructure identified in Judicial Review Act 1991 or otherwise, whether by the
a LGIP; or Supreme Court, another court, a tribunal or another entity; and
(ii) the cost of infrastructure decided using the method (c) is not subject to any declaratory, injunctive or other order of
included in the local government’s charges resolution. the Supreme Court, another court, a tribunal or another entity
on any ground.
230 Notice of appeal
232 Rules of the P&E Court
(1) An appellant starts an appeal by lodging, with the registrar of the
tribunal or P&E Court, a notice of appeal that- (1) A person who is appealing to the P&E Court must comply with the
rules of the court that apply to the appeal.
(a) is in the approved form; and
(b) succinctly states the grounds of the appeal. (2) However, the P&E Court may hear and decide an appeal even if
the person has not complied with the rules of the P&E Court
(2) The notice of appeal must be accompanied by the required fee.
Page 22 of 22
Document Set ID: 24037249
Version: 8, Version Date: 18/12/2025
Used in these records
Negotiated Decision Notice MCU24 0153 & OPW24 0202 (As Published).pdfRelated documentApplication case desk ↗
Negotiated Decision Notice MCU24 0153 & OPW24 0202 (As Published).pdfRelated documentApplication case desk ↗
Negotiated Decision Notice MCU24 0153 & OPW24 0202.pdfRelated documentApplication case desk ↗
Negotiated Decision Notice MCU24 0153 & OPW24 0202.pdfRelated documentApplication case desk ↗
About this file
- File size
- 221 KB (small file)
- File type
No other editions are linked here.