52. Prior to acceptance of civil works to become Council assets “On Maintenance”, satisfactory
“As-Constructed” records must be submitted to Council. The bundle of “As Constructed”
a. As-Constructed Engineering Drawings. Data is to be submitted in an electronic drawing
file format (.dwg), with all plans clearly endorsed “As-Constructed”, along with the
accompanying hardcopies (PDFs of the As-Constructed .dwg drawing files), and;
b. ADAC XML Digital File. ADAC File format (ADAC - Asset Design As Constructed)
prepared in accordance with industry standards and recorded in “MGA - UTM56 /
GDA94” projection.
Please Note: Further information and advice relating to the as-constructed drawing
presentation, as-constructed survey capture and associated guidelines for preparation
of a compliant ADAC XML digital file are available on the webpage titled “As-
Constructed Guidelines” and accessible at the Noosa Council Website: Planning &
Development / Development Tools & Guidelines / As-Constructed Guidelines.
c. The “As-Constructed” drawings will require certification by a:
i. Qualified experienced Civil Engineer (RPEQ) confirming design intent and
conformance with applicable standards and specifications, along with the
relevant descriptions of assets, services and structures and;
ii. Registered Cadastral Surveyor (Qld) in regard to the cadastral and locational
information, levels and applicable survey datum.
d. The data must be in accordance with Council’s “Planning Scheme Policy 6 –
Engineering Design Standards”, and fully detail the levels for all engineering works
including but not limited to the drainage network and structures, finished ground and
pavement surface levels.
On Maintenance
53. All municipal works must be accepted ‘On Maintenance’ by Council in accordance with
Council’s relevant Planning Scheme Policy prior to the commencement of the use. To
achieve ‘On Maintenance’, the supervising RPEQ must submit to Council:
a. certification that all works have been undertaken and completed in accordance with the
requirements of this Permit.
b. as Constructed details in accordance with Council’s Planning Scheme Policy.
c. maintenance and operational manuals for all proprietary or site-specific devices
Off Maintenance
54. Prior to requesting an Off Maintenance inspection, the developer must provide a written
request for the Off Maintenance inspection.
55. A re-inspection fee in accordance with Council’s Fees and Charge Register will be charged
where:
a. a Council inspection reveals works do not comply with approval requirements.
b. submitted certification falsely states works comply with approval requirements.
56. A final inspection and approval of the new driveway and completed reinstatement works by
Council’s Inspector is required. Please contact Council on 5329 6500 to arrange for the
inspection.
Page 16 of 22
Document Set ID: 24037249
Version: 8, Version Date: 18/12/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Negotiated Decision Notice MCU24 0153 & OPW24 0202 (As Published).pdfRelated documentApplication case desk ↗
Negotiated Decision Notice MCU24 0153 & OPW24 0202 (As Published).pdfRelated documentApplication case desk ↗
Negotiated Decision Notice MCU24 0153 & OPW24 0202.pdfRelated documentApplication case desk ↗
Negotiated Decision Notice MCU24 0153 & OPW24 0202.pdfRelated documentApplication case desk ↗