               13.    All deck and balcony areas must not be enclosed with shutters, louvres, glass panelling or
                      the like thus remaining as open structures, except where required to satisfy any privacy
                      condition of this Decision Notice.
               14.    External colours and finishes must be of an understated colour scheme and low-reflective
                      roofing and cladding materials.
               15.    All air conditioning units or other mechanical equipment must be fully enclosed or screened
                      such that they are not visible from the street frontages nor adjoining properties.
               16.    Waste storage areas, clothes drying areas and external storage areas must be screened
                      from view of the street.
                      Protection of Privacy
               17.    The upper level balconies located on the eastern elevation of Units 3-6 must include either
                      balcony planter boxes, balustrading or fixed external screens, positioned in such a way to
                      obscure direct views into the habitable room windows or private open space areas of the
                      adjoining property. Any fixed external screen(s) must not extend more than 50% of the length
                      of the balcony.
                      Water & Sewer Connections
               18.    An underground connection to reticulated water and sewerage must be provided to the
                      premises in accordance with the standards and requirements of Northern SEQ Distributor–
                      Retailer Authority (Unitywater).
               19.    A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater)
                      must be submitted to Council that certifies an underground connection to reticulated water
                      and sewerage has been provided to the premises.
                      Noise – Services and Pool Equipment
               20.    Written certification is required from a suitably qualified person confirming that sound
                      pressure levels from all mechanical plant and equipment comply with the following:
                      a.      Air-conditioning and Refrigeration
                                  i.   7am to 10pm: Maximum level allowable = background + 5dB(A)
                                 ii.   10pm to 7am: Maximum level allowable = background + 3dB(A)
                      b.      Pumps, Service Room
                                  i.   7am to 7pm: Maximum level allowable = background + 5dB(A)
                                 ii.   7pm to 10pm: Maximum level allowable = background + 3dB(A)
                                iii.   10pm to 7am: No audible noise.
               21.    The certification must be submitted to Council, which certifies that operational noise from any
                      fixed plant and equipment complies and with the requirements of this Decision Notice.
                      External Works
               22.    Elanda Street must be upgraded for the length of its frontage to the subject site. The works
                      must be undertaken in accordance with an Operational Works approval and must include in
                      particular:
                      a.      construction of kerb and channelling to the development side only
                      b.      widening and sealing of the existing road pavement to the centreline of Elanda Street.
                      c.      construction of a pedestrian footpath in accordance with the conditions of this Decision
                              Notice
                      d.      relocation of the existing overhead electricity pole
                      e.      removal of the existing property access and reinstatement of the kerb, footpath and
                              verge area to match the balance of the site frontage, including the provision of topsoil
                              and turf where the existing verge is grassed


                                                                                                        Page 4 of 22
Document Set ID: 24037249
Version: 8, Version Date: 18/12/2025

Used in these records

About this file

File size
221 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Negotiated Decision Notice MCU24 0153 & OPW24 0202 (As Published).pdf · 221 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.