Compiled Approved Plans OPW17/0561.01

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
                    Australian Tree Contractors & Arboricultural Consultants Pty Ltd

P O Box 1411, Noosaville DC Queensland 4566.
Mobile: 0431586371
Email: [email protected]
Web: www.australianconsultarborist.com.au


     ACCESS AND PARKING

          The access for construction materials and equipment will be from Park
          Road via the existing driveway to No. 10 Park Road. The Builder is to
          submit written consent for the use of this access driveway and garage from
          the owner of No. 10 Park Road. Access for personnel will be via Allambi
          Rise and Park Road. Offsite parking will be required for most construction
          personnel.

          Most workers vehicles shall be parked in Allambi Rise or in the existing
          driveway and carport of 12 Park Road which is accessed by the 9A
          driveway Allambie Rise.

          All construction access is to be obtained from Allambi Rise via the existing
          easement subject to the following exceptions:

          a) A crane may be used for delivering prefabricated materials and the
              pier digging machine to the site.
          The use of the crane in Park Road is to occur on two (2) separate
          days only, first for the delivery of the pier digging machine and any
          prefabricated materials, the second to retrieve the pier digging
          machine and provide any further prefabricated materials as required.
          Traffic control is to be provided for the use of the crane in Park Road,
          in accordance with the builders Traffic Management Plan.

          b) Access from Park Road to the site is to be used for a concrete
             pumping pipe to be located at the base of the rock retaining wall on
             the boundary of 10 Park Road, laid upon a composted wood chip
             mulch 600mm wide and 150mm thick. Any mulch contaminated by
             concrete or wastes shall be removed from the site. Any remaining
             clean mulch may be left in situ and spread to 50mm thickness.




       “We manage the trees that you care about and remove the trees you worry about”

Used in these records

About this file

File size
9.3 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Compiled Approved Plans OPW17_0561.01.pdf · 9.3 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.