Amendment 4. Revised Construction Program.
Operation Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7
Site Establishment #
New Access Path #
Construct Working Platform #
Install Micro Piles Terrace #
Construct Moving Working
Platform over lift access tunnel #
Install Micro Piles to Lift shaft and #
access tunnel
Construct Pile Caps #
Excavate to Soffit level of Access #
walkway Concrete roof.
Construct Suspended Concrete
Slab Roof over Access Tunnel #
Complete excavation of lift shaft
and access walkway and fill over #
to re-establish original ground
above access tunnel
Erect Scaffolding #
Construct Lift Shaft and walkway
#
Extend existing main house deck
and lift shaft glazing/waterproofing #
Install Lift equipment &
commission Lift #
“We manage the trees that you care about and remove the trees you worry about”
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Compiled Approved Plans OPW17/0561.01.pdfRelated documentApplication case desk ↗
About this file
- File size
- 9.3 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.