From:                         Patrick Murphy
To:                           Adam Britton
Subject:                      RE: Digital Hub expansion
Date:                         Friday, 22 October 2021 3:40:05 PM
Attachments:                  1.3 Peregian Beach Fire Tech Lab - Ground Floor Plan.pdf
                              image001.jpg
                              image002.gif
                              183 PBCH Extension Option 1.pdf


Hi Adam,

We have reviewed the plot ratio and are satisfied that it complies with the scheme requirement.

I am also satisfied that the advice provided below is still applicable.

Regards
Patrick

Patrick Murphy
Coordinator Planning I Development Assessment
Environment and Sustainable Development I Noosa Council

Phone:                     


Email:   
Website:    www.noosa.qld.gov.au
Location: Level 2, 9 Pelican Street, Tewantin
Mail:         PO Box 141 Tewantin Qld 4565
Find Council on Facebook




From: Adam Britton <                                                           >
Sent: Tuesday, 31 August 2021 4:07 PM
To: Patrick Murphy <                                                               >
Subject: FW: Digital Hub expansion

Hi Patrick

We’ve worked on a number of design iterations and expect that the attached (File 183
PBCH Extension Option 1) will be the likely project outcome.

It’s the same as the original floor plan layout previously issued with more elevations and
perspective views.

Can you please confirm advice below and any plot ratio checks.

Any questions let me know.

Thanks
Adam

Adam Britton
Special Projects Coordinator I Infrastructure Services I Noosa Council
Log in to download the original file

T000063 - 4F.6 - Noosa Council Planning Correspondence.pdf · 4.1 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 11 pages

Page 2

Phone
Mobile
Email

Website w no gid. gov.au
Location 9 Pelican Street, Tewantin
Mail PO Box 141 Tewantin, Qld 4565

From: Patick Murphy _ >

Sent: Thursday, 3 June 2021 4:55 PM

To: Adorn ttn cc

Subject: RE: Digital Hub expansion
Hi Adam,
The existing approval allows for:

e Development Permit for Material Change of Use of Premises - Commercial Business
Type 1 Office, Entertainment & Dining Business Type 1 Food & Beverages,
Wellbeing Type 2 - Social and Open Space Type 1 Sport & Recreation

e¢ Development Permit to Reconfigure a Lot - Boundary realignment

It appears that the proposed change does not seek to introduce a new land use and that
the use of the premises will remain consistent with the original approval.

| have reviewed the original reports written by Glen Conforti which identify that
additional car parking was provided as part of the original approval, this suggests that
there is sufficient car parking available to accommodate the proposed changes to the
footprint.

At this stage | have not had a chance to review the plot ratio and will endeavor to do so
over the coming days.

Although | don’t have all the plans associated with the proposed changes it would
appear that the proposed works could be accommodated under a minor change
application.

| anticipate that we will meet to discuss in more detail once you have additional
information/plans on the proposed works.

Regards
Patrick

Patrick Murphy
Coordinator Planning | Development Assessment
Environment and Sustainable Development | Noosa Council

Phone
Emai

Page 3

Website: www,noosa.qid.gov.au

Location: Level 2, 9 Pelican Street, Tewantin
Mail: PO Box 141 Tewantin Qld 4565

Find Council on Facebook

Please consider the environment before printing this email

From: Adam Briton oS

Sent: Tuesday, 25 May 2021 2:02 PM

To: Patrick Mp hy _ ccc

Subject: FW: Digital Hub expansion

Hi Patrick,

As discussed, we're in process of scoping the upgrade of the existing Peregian
community house to allow expansion of the Digital Hub. This project is a combination of
two successful grant applications.

Once the new community centre is built on Rufous St the community group will vacate
the existing community house and upgrade will commence.

We are planning for upgrade works to commence in September with completion ahead
of June 2022.

As we move into scoping the upgrade Id like to make sure we meet all planning
requirements in good time.

Attached is an example of the concepts being reviewed which can form the basis of
planning approval requirements.

Feel free to review and contact me to discuss.

Thanks

Adam

Adam Britton

Special Projects Coordinator | Infrastructure Services | Noosa Council

Phone

Mobile

Email

Website www.noosa.adld.gov.au

Location 9 Pelican Street, Tewantin

Mail PO Box 141 Tewantin, Qld 4565

Page 4

                                                                                                                                                                                                                               rev  date   issued details
                                                                                                                                                                                                                                # 20.05.21 MS Preliminary Sketch Design
                                                                                                                                                                                                                                                                                                                                                                                  Sketch Design


                   legend - proposed scope of work
                                                                                                                                                                                                                                                                                                                                                                Class 9b - public halls / function rooms

                                  content pod
                                                                                                                                                                                                     woodland drive                                                                                                                                             - building sanitary requirements.
                                  -acoustic rated internal walls
                                  -carpet floor, plasterboard ceiling                                                                                                                                                          25,000                                                                                                                           useable floorspace = 408m2
                                                                                                                                                                                                                                                                                                                                                                circulation space = 82m2
                                                                                                                                                                                     5,000                      5,000                                15,000
                                  meeting room
                                  -carpet floor, plasterboard walls +                                                                                                                                                                                                                                                                                           -Types of use-          space
                                  ceiling                                                                                                                                  G                              F                E              D                           C                          B               A
                                  -glazing strip windows to match
                                  existing windows on south east
                                                                                                                                                                                     5,000                      5,000          5,000                  5,000                         5,000              2,400
                                                                                                                                                                                                                                                                                                                                                                theatre (1/1m2)……………….170m2
                                  wall, refer to south east elevation      double glazed sliding doors to                                                                                                                                                                                                                                                       office (1/10m2)…………………170m2
                                                                           assist with acoustic                                                                                                                                                                                                                                                                 store (1/30m2)…………………35m2
                                  big data pod upgrade existing            requirements and reduce
                                  -remove all existing joinery,




                                                                                                                                                                                                                                                                          setback
                                                                           thermal heat load




                                                                                                                                                                                                                                                                           5,930
                                  -new carpet
                                  -new paint
                                                                                                                                                                                                                                                                                                                                                                total design occupancy = 187
                                  -remove amenities                            neighbouring
                                  -partition dividing walls                                                                                                                                                                                                                                                                                                     94 males / 94 females
                                                                                 property
                                  co lab pod new proposed
                                  -new build                                                                                                                                                                                                                                                                                                                    -Total no. sanitary requirements
                                  -rentable office space                   partition walls dividing
                                  -retractable seating                     spaces
                                                                                                                                                                                                                                                                                                                                                                male= 2 wc's + 2ur. + 2 wb's
                                  flexible space if required               57 retractable seats as
                                  -new build                               per Interseat details
                                  -rentable office space                                                                                                                       store           stage +        Co Lab pod                      retractable                 flexible space                                                                        female= 4 wc's + 2 wb's




                                                                                                                             8,045
                                  -partition dividing wall to co lab pod                                                                                                                      projector                                         seating                        (if required)
                                                                                                                                                                               17.65 m2        screen          132.90 m2
                                                                                                                                                                                                                                                                                 37.12 m2                  landscaping
                                  new store/ bar
                                  -new joinery, cupboards +
                                  benchtops
                                  -new commercial standard floor
                                  finish




                                                                                                                                                                                                                                                                                                                                                                  way
                                  -new paint
                                                                           new timber decking
                                  amenities                                                                                                                                                                    breakout                               linkway
                                                                                                                             3,610




                                  -new fitout
                                                                                                                                                                  2,580                                         space                           landscaping/ garden
                                  covered linkway entry/                                                                                                         setback                                        55.70 m2                                                                                                                                                                                   d




                                                                                                                                                                                                                                                                                                                                                                  david low
                                  breakout space                                                                                                                                                                                                                                                                                               2
                                                                                                                                                                                                                                                                                                                                               1
                                  -new/ existing decking
                                  -new roof
                                                                           new acoustic rated
                   refer to architectural drawings for                     internal walls
                   further detail.
                                                                                                                                                                                    content                      main                          big data pod
                                                                                                                             7,490




                                                                                                                                                                                                                                                                                                                                       7,490
                                                                                                                                                                                      pod                      function                             107.80 m2
                                                                                                                                                                                              2
                                                                                                                                                                                    31.60 m                      entry
                                                                           partition walls                                                                                                                      47.45 m2
                                                                           dividing spaces
                                                                           remove and restructure bracing
                                                                           truss walls above
                                                                                                                                                                                                                                                                                                                                               2
                                                                           new double door to




                                                                                                                                                                                                                                                                                                                                       2,400
                                                                                                                                                                                                                                                   breezeway                                           entry 2
                                                                           meeting room                                                                                                                                                              34.69 m2

                                                                                                                                                                                   meeting                                                                                                                                                     3
                                                                                                                             6,180




                                                                                                                                                                                    room                        entry 1
                                                                                                                                                                                     29.50 m  2                                 bar/               female                             male




                                                                                                                                                                                                                                                                                                                                       3,780
                                                                                                                                                                                                                               store               14.45 m2                           14.13 m2
                                                                                                                                                                                                                                                                              2
                                                                                                                                                                                                                                                                      5.25 m
                                                                                                                                                                                                                                                                    pwd
                                                                           revitalise existing timber deck                                                                                                                     18.15 m2
                                                                                                                                                                                                                                                                    5.25 m2

                                                                           new timber deck ramp as                                                                                                                                                                                                                                             4
                                                                                                                                                                                       SM
                                                                           per AS1428                                                                                                     H                                                   landscaping/ garden
                                                                                                                             884




                                                                                                                                                                                                                                               sandstone seating
                                                                           dashed line denotes new                                                                                                                up
                                                                           roofline above                                                                                                                                                     concrete path                                       primary entry
                                                                                                                                                                                                               covered                                                                            & way finding
                                                                           covered linkway to
                                                                                                                                                                                                               linkway
                                                                           Digi Hub


                   *note - structure
                                                                                                                                                                                                                                                    existing
                                                                                                                                                                                                                                                    Digi Hub
                   All structural elements including
                   footings, walls and framing to be in
                   accordance with engineers design and
                   detail




                                                                                                      a: suite 6, 8 kingfisher drive, peregian beach, qld 4573
                                                                                                      p: (07) 5471 3033                                                         Peregian Beach Community House - Fire Tech Lab                                                                                           Scale 1:200

                     sparks architects                                                                www.sparksarchitects.com
                                                                                                                                                                                255 David Low Way, Peregian Beach                         Noosa Shire Council                                    183             MS      Peregian Beach Fire Tech Lab - Ground Floor Plan     SK 1.3            n
                                                                                                      sparks architects pty. ltd. abn 89 124 611 721
                                                                                                      qld architect's registration No. 3974                                     project                                                   client                                                 job no.         drawn   drawing                                              dwg no.
GSPublisherVersion 547.11.64.75

Page 5

                                                                                                                                                                                                                            rev  date   issued details
                                                                                                                                                                                                                             B 07.06.21 MS Preliminary Sketch Design
                                                                                                                                                                                                                                                                                                                                                                                Sketch Design


                   legend - proposed scope of work
                                                                                                                                                                                                                                                                                                                                                               Class 9b - public halls / function rooms
                                                                                                                                                                                                                                                                                                                                                               - building sanitary requirements.
                                 content pod
                                 -acoustic rated internal walls
                                 -carpet floor, plasterboard ceiling                                                                                                                                                        25,000                                                                                                                             useable floorspace = 408m2
                                                                                                                                                                                                                                                                                                                                                               circulation space = 82m2
                                                                                                                                                                                   5,000                   5,000                                  15,000
                                 meeting room
                                 -carpet floor, plasterboard walls +                                                                                                                                                                                                                                                                                           -Types of use-        space
                                 ceiling                                                                                                                                 G                           F                  E              D                           C                            B               A
                                 -glazing strip windows to match
                                 existing windows on south east
                                                                                                                                                                                   5,000                   5,000            5,000                  5,000                          5,000               2,400
                                                                                                                                                                                                                                                                                                                                                               theatre (1/1m2)……………….170m2
                                 wall, refer to south east elevation      double glazed sliding doors to                                                                                                                                                                                                                                                       office (1/10m2)…………………170m2
                                                                          assist with acoustic                                                                                                                                                                                                                                                                 store (1/30m2)…………………35m2
                                 big data pod upgrade existing            requirements and reduce
                                 -remove all existing joinery,




                                                                                                                                                                                                                                                                       setback
                                                                          thermal heat load




                                                                                                                                                                                                                                                                        5,930
                                 -new carpet
                                 -new paint                                                                                                                                                                        A                                                                                                                                           total design occupancy = 187
                                                                                                                                                                                                                  3.1
                                 -remove amenities
                                 -partition dividing walls                                                                                                                                                                                                                                                                                                     94 males / 94 females
                                 co lab pod new proposed                                                                                                                                                    deck
                                 -new build                                                                                                                                                                                                                                                                                                                    -Total no. sanitary requirements
                                 -rentable office space
                                 -retractable seating
                                                                                                                                                                                                                                                                                                                                                               male= 2 wc's + 2ur. + 2 wb's
                                 flexible space if required               57 retractable seats as
                                 -new build                               per Interseat details                                                                                                                                                                            flexible
                                 -rentable office space                                                                                                                      store        stage +        Co Lab pod                        retractable                      space                                                                              female= 4 wc's + 2 wb's




                                                                                                                           8,045
                                 -partition dividing wall to co lab pod                                                                                                                  projector                                           seating                       (if required)
                                                                                                                                                                             17.65 m2     screen          132.90 m2
                                                                                                                                                                                                                                                                              27.10 m2                    landscaping
                                                                                                                                                                   AC
                                 new store/ bar
                                 -new joinery, cupboards +
                                 benchtops
                                 -new commercial standard floor                                                                                                    AC
                                 finish
                                 -new paint

                                 amenities                                new timber decking                                                                                                                                                      linkway
                                                                                                                                                                                 landscape                breakout
                                                                                                                           3,610




                                 -new fitout                                                                                                                                                                                                     24.05 m2
                                                                                                                                                                2,580              seating                 space                            landscaping/ garden
                                 covered linkway entry/                       neighbouring                                                                     setback
                                 breakout space                                                                                                                                                                                                                                                                                               2
                                                                                                                                                                                                                                                                                                                                              1
                                 -new/ existing decking                         property
                                 -new roof
                                                                          new acoustic rated
                                 Proposed Digital Hub                     internal walls
                                 renovation
                                 - new walls, doors, external window                                                                                                              content                   main                           big data pod
                                                                                                                           7,490




                                                                                                                                                                                                                                                                                                                                      7,490
                                 - New internal finishes                                                                                                                            pod                   function                               107.80 m2
                                                                                                                                                                                           2
                                                                                                                                                                                  31.60 m                   entry
                   refer to architectural drawings for
                                                                          partition walls                                                                                                                  47.45 m2
                   further detail.
                                                                          dividing spaces
                                                                          remove and restructure bracing
                                                                          truss walls above
                                                                                                                                                                                                                                                                                                                                              2
                                                                          new double door to




                                                                                                                                                                                                                                                                                                                                      2,400
                                                                                                                                                                                                                                                breezeway                                             entry 2
                                                                          meeting room                                                                                                                                                            34.69 m2

                                                                                                                                                                                 meeting                                                                                                                                                      3
                                                                                                                           6,180




                                                                                                                                                                                  room                     entry 1
                                                                                                                                                                                   29.50 m  2                                bar/               female                                male




                                                                                                                                                                                                                                                                                                                                      3,780
                                                                                                                                                                                                                            store               14.45 m2                             14.13 m2
                                                                                                                                                                                                                                                                              2
                                                                                                                                                                                                                                                                   5.25 m
                                                                                                                                                                                                                                                                 pwd
                                                                          revitalise existing timber deck                                                                                                                   18.15 m2
                                                                                                                                                                                                                                                                 5.25 m2

                                                                          new timber deck ramp as                                                                                                           1:14                                                                                                                              4
                                                                          per AS1428                                                                                                                        ramp                           landscaping/ garden
                                                                                                                           884




                                                                                                                                                                                                                                            sandstone seating
                                                                          dashed line denotes new                                                                                                            up
                                                                          roofline above                                                                                                                                                                                                         primary entry
                                                                                                                                                                                                          covered                                                                                & way finding
                                                                          covered linkway to
                                                                                                                                                                                                          linkway
                                                                          Digi Hub


                   *note - structure


                   All structural elements including
                   footings, walls and framing to be in
                   accordance with engineers design and
                   detail



                                                                                                    a: suite 6, 8 kingfisher drive, peregian beach, qld 4573
                                                                                                    p: (07) 5471 3033                                                         Peregian Beach Community House - Fire Tech Lab                                                                                            Scale 1:200

                     sparks architects                                                              www.sparksarchitects.com
                                                                                                                                                                              255 David Low Way, Peregian Beach                        Noosa Shire Council                                      183             MS      Peregian Beach Fire Tech Lab - Ground Floor Plan   SK 1.3            n
                                                                                                    sparks architects pty. ltd. abn 89 124 611 721
                                                                                                    qld architect's registration No. 3974                                     project                                                  client                                                   job no.         drawn   drawing                                            dwg no.
GSPublisherVersion 565.9.54.75

Page 6

                                                                                                                                                                                   rev  date   issued details
                                                                                                                                                                                    B 07.06.21 MS Preliminary Sketch Design
                                                                                                                                                                                                                                                                                                      Sketch Design




                                                                                                                                      G                  F                    E                  D                 C           B               A


                                                                                                                                              5,000             5,000              5,000                  5,000        5,000         2,400



                                                                                                                                                                         A
                                                           new rain head and                                                                                            3.1

                                                           spitters

                                                           new pebble roof


                                                           new PV array
                                                                                                                                                                                     new
                                                           new concrete up turn                                                                                                   extension
                                                           finish wall wall below




                                                                                                                                                                                                                                      fall



                                                          neighbouring
                                                                                                                                                                                 existing                                                                                    2
                                                                                                                                                                                                                                                                             1
                                                            property
                                                                                                                                                                              peregian beach
                                                                                                                                                                                community
                                                                                                                                                                                  house




                                                                                                                                                                                                                                                                     7,490
                                                                                                                                                                                     fall 9o                                         fall 9o


                                                           new solid roof to match
                                                           existing adjacent roof
                                                                                                                                                                                                                                                                             2
                                                                                                                                              fall 9o




                                                                                                                                                                                                                                                                     2,400
                                                           new PV array to link in
                                                           with existing                                                                                                                                                                                                     3
                                                                                                                                             new                                               fall 9o




                                                                                                                                                                                                                                                                     3,780
                                                                                                                                          extension
                                                                                                                                                o
                                                           new roof to match existing                                                         fall 9

                                                                                                                                                                                                                                                                             4
                                                           new translucent
                                                           polycarbonate roof
                                                                                                                                                                 fall




                   *note - structure

                                                                                                                                                                                     existing
                   All structural elements including
                   footings, walls and framing to be in                                                                                                                             digital hub
                   accordance with engineers design and                                                                                                                              building
                   detail



                                                                           a: suite 6, 8 kingfisher drive, peregian beach, qld 4573
                                                                           p: (07) 5471 3033                                              Peregian Beach Community House - Fire Tech Lab                                                               Scale 1:200

                     sparks architects                                     www.sparksarchitects.com
                                                                                                                                          255 David Low Way, Peregian Beach                      Noosa Shire Council           183             MS      Peregian Beach Fire Tech Lab - Roof Plan   SK 1.4     n
                                                                           sparks architects pty. ltd. abn 89 124 611 721
                                                                           qld architect's registration No. 3974                          project                                                client                        job no.         drawn   drawing                                    dwg no.
GSPublisherVersion 565.9.54.75

Page 7

                                                                                                                                                                                                           rev  date   issued details
                                                                                                                                                                                                                                                                                                                                                                  Sketch Design




                                                                                                                           7,490




                                                                                                                                                                                                                                                                                                                            7,490
                                                                                                                                                                                                            B 07.06.21 MS Preliminary Sketch Design

                                                                          partition walls
                   legend - proposed scope of work                        dividing spaces
                                                                          remove and restructure bracing
                                 content pod                              truss walls above
                                                                                                                                                                                                                                                                                                                                    2
                                 -acoustic rated internal walls
                                                                          new double door to




                                                                                                                                                                                                                                                                                                                            2,400
                                 -carpet floor, plasterboard ceiling                                                                                                                                                                 breezeway
                                                                          meeting room                                                                                                                                                                                                 entry 2
                                                                                                                                                                                                                                       34.69 m2

                                 meeting room                                                                                                                    meeting                                                                                                                                                            3




                                                                                                                           6,180
                                 -carpet floor, plasterboard walls +                                                                                              room                      entry 1
                                 ceiling                                                                                                                                 2
                                                                                                                                                                   29.50 m                                  bar/                     female                          male




                                                                                                                                                                                                                                                                                                                            3,780
                                                                                                                                                                                                           store                     14.45 m2                        14.13 m2
                                 -glazing strip windows to match
                                 existing windows on south east                                                                                                                                                                                         5.25 m2
                                                                                                                                                                                                                                                      pwd
                                                                          revitalise existing timber deck                                                                                                        2
                                                                                                                                                                                                           18.15 m
                                 wall, refer to south east elevation                                                                                                                                                                                  5.25 m2


                                 big data pod upgrade existing            new timber deck ramp as                                                                                            1:14                                                                                                                                   4
                                 -remove all existing joinery,            per AS1428                                                                                                         ramp                              landscaping/ garden




                                                                                                                           884
                                 -new carpet                                                                                                                                                                                    sandstone seating
                                 -new paint
                                 -remove amenities                        dashed line denotes new                                                                                              up
                                                                          roofline above                                                                                                                                                                                          primary entry
                                 -partition dividing walls                                                                                                                                  covered                                                                               & way finding
                                                                          covered linkway to
                                 co lab pod new proposed                                                                                                                                    linkway
                                                                          Digi Hub
                                 -new build
                                 -rentable office space
                                 -retractable seating

                                 flexible space if required
                                 -new build
                                 -rentable office space
                                 -partition dividing wall to co lab pod
                                                                                                                                                                                           exist.covered                            exist.
                                                                                                                                                                                             outdoors                          shared co-worker
                                 new store/ bar                                                                                                                                                                                     space
                                 -new joinery, cupboards +
                                 benchtops
                                 -new commercial standard floor
                                 finish
                                 -new paint                                                                                                                                                          A
                                                                                                                                                                                                    3.1
                                 amenities
                                 -new fitout                                                                                                                                                                         exist. amenities
                                 covered linkway entry/                                                                                                                                                                                                                     exist. pitch
                                 breakout space                                                                                                                                                                                                                              meeting
                                 -new/ existing decking
                                 -new roof

                                 Proposed Digital Hub                                                                                                                                                                                               exist. foyer/                new                     new acoustic wall, door and
                                                                                                                                                                                                              exist.entry
                                 renovation                                                                                                                                                                                                           gallery                   meeting                  external window to match
                                                                                                                                                                                                                                                                                       2
                                                                                                                                                                                                                                                                                 6.29 m                  existing
                                 - new walls, doors, external window
                                 - New internal finishes
                   refer to architectural drawings for
                   further detail.                                                                                                                                                                                                                                          exist. pitch
                                                                                                                                                                                                                                                                             meeting


                                                                                                                                                                             exist. cafe
                                                                                                                                                                                                                                                                                                         new acoustic wall and doors
                                                                                                                                                                                                                                                                                                         to create secondary shared co-
                                                                                                                                                                                                                                                                                                         worker space
                                                                                                                                                                                                                                                     proposed
                                                                                                                                                                                                                                                  shared co-worker
                                                                                                                                                                                                                                                       space




                   *note - structure


                   All structural elements including
                   footings, walls and framing to be in
                   accordance with engineers design and
                   detail




                                                                                                    a: suite 6, 8 kingfisher drive, peregian beach, qld 4573
                                                                                                    p: (07) 5471 3033                                          Peregian Beach Community House - Fire Tech Lab                                                                                                Scale 1:200

                     sparks architects                                                              www.sparksarchitects.com
                                                                                                                                                               255 David Low Way, Peregian Beach                            Noosa Shire Council                                  183             MS          Peregian Beach Digital Hub - Ground Floor Plan   SK 1.5     n
                                                                                                    sparks architects pty. ltd. abn 89 124 611 721
                                                                                                    qld architect's registration No. 3974                      project                                                      client                                               job no.         drawn       drawing                                          dwg no.
GSPublisherVersion 565.9.54.75

Page 8

                                                                                                                                                                                                 rev  date   issued details
                                                                                                                                                                                                  B 07.06.21 MS Preliminary Sketch Design                            #    ??.??.?? ??   ?? ?? ??
                                                                                                                                                                                                                                                                                                         Sketch Design


                    legend
                    CB           colorbond flatsheet
                    FC           6mm fibre cement sheet
                    HWD          hardwood timber
                    RS1          profiled colorbond roof sheet
                    RS2          profiled colorbond translucent
                                 roof sheet on hwd roof frame

                    refer to schedules for details

                    NOTE: all structural elements; including all
                    slabs, columns, beams, footings and
                    framing; to be in accordance with engineer's
                    design and detail.




                                                                             4                                         3                         2                                                        1
                                                                                                                                                                                                          2
                                                                                         3,780                                         2,400                                7,490



                                                                                                                                                                        new alteration
                                                                                           new extension                                                                under existing                                                                    new extension
                                                                                                                                                                            roof
                                  8.5m height
                                     limit                                                                                                                                                                                                                                                         new acoustic rated ceiling

                                                                                                                                                                                                                                                                                                   remove existing louvre vents
               existing 9° pitched roof
               new 9° pitch roof to match existing                                                                                                                                                                                                                                                 new roof structure
               new polycarbonate roof on
               hardwood rafters
               to form linkway to Digital Hub                                                                                                                                                                                                                                                      solar panel array
                                                                                                                                                 9.00°                                                                                                                                             pebble garden roof


                                                                                                                                                                                                                                                                                                   FFL 13 200 new ceiling height
                                                                                                                                                                                                                                    fall
                                                                   fall
                                                                                                                                                                                                                                                                                                   FFL 12 000 doors and windows
                                                                                 FC                        FC
                                                                                                                                                         3,600




                                                                                                                                                                                                                                                  3,600
                                                                                                                               main entry to                            main function                         72.00°                                        co lab pod                             concrete blades
                   existing                                                                                                   function space                               entry
                  digital hub                                      linkway                                                                                                                                                                                                                         new double glazed doors
                                                                                                                                                                                                                                                                                                   for deck access
                                                                                                                                                                                                                                                                                                   FFL 10 200 ground floor


                                                                                                                                                                                                                                                                                                   natural ground line
                                                                                                                                                                                                                                                                                                   shown dashed
                          new timber ramp
                                                                                                                                                                                                                                                                                                   new timber decking
                          1:14 and handrail
                                                                                                                                                                                                                                                                                                   concrete slab to big data pod

                          new doors + meeting room
                                                                                                                                                                                                                                                                                                   3600mm sound partition wall
                          (beyond)

                          existing deck to be revitalised




                                                                                      a: suite 6, 8 kingfisher drive, peregian beach, qld 4573
                                                                                      p: (07) 5471 3033                                                  Peregian Beach Community House - Fire Tech Lab                                                                   1:100
                                                                                                                                                                                                                                                                    Scale ???

                     sparks architects                                                www.sparksarchitects.com
                                                                                                                                                         255 David Low Way, Peregian Beach                    Noosa Shire Council           183           MS        Section A-A                     SK 3.1
                                                                                      sparks architects pty. ltd. abn 89 124 611 721
                                                                                      qld architect's registration No. 3974                              project                                              client                        job no.       drawn     drawing                         dwg no.
GSPublisherVersion 565.9.54.75

Page 9

                                                                                                                                            rev  date   issued details
                                                                                                                                             B 07.06.21 MS Preliminary Sketch Design
                                                                                                                                                                                                                                    Sketch Design




                                         a: suite 6, 8 kingfisher drive, peregian beach, qld 4573
                                         p: (07) 5471 3033                                          Peregian Beach Community House - Fire Tech Lab                                                       Scale

                     sparks architects   www.sparksarchitects.com
                                                                                                    255 David Low Way, Peregian Beach                 Noosa Shire Council              183       MS      Perspectives Sheet 1   SK 4.1
                                         sparks architects pty. ltd. abn 89 124 611 721
                                         qld architect's registration No. 3974                      project                                           client                           job no.   drawn   drawing                dwg no.
GSPublisherVersion 565.9.54.75

Page 10

                                                                                                                                            rev  date   issued details
                                                                                                                                             B 07.06.21 MS Preliminary Sketch Design
                                                                                                                                                                                                                                    Sketch Design




                                         a: suite 6, 8 kingfisher drive, peregian beach, qld 4573
                                         p: (07) 5471 3033                                          Peregian Beach Community House - Fire Tech Lab                                                       Scale

                     sparks architects   www.sparksarchitects.com
                                                                                                    255 David Low Way, Peregian Beach                 Noosa Shire Council              183       MS      Perspectives Sheet 2   SK 4.2
                                         sparks architects pty. ltd. abn 89 124 611 721
                                         qld architect's registration No. 3974                      project                                           client                           job no.   drawn   drawing                dwg no.
GSPublisherVersion 565.9.54.75

Page 11

                                                                                                                                            rev  date   issued details
                                                                                                                                             B 07.06.21 MS Preliminary Sketch Design
                                                                                                                                                                                                                                    Sketch Design




                                         a: suite 6, 8 kingfisher drive, peregian beach, qld 4573
                                         p: (07) 5471 3033                                          Peregian Beach Community House - Fire Tech Lab                                                       Scale

                     sparks architects   www.sparksarchitects.com
                                                                                                    255 David Low Way, Peregian Beach                 Noosa Shire Council              183       MS      Perspectives Sheet 3   SK 4.3
                                         sparks architects pty. ltd. abn 89 124 611 721
                                         qld architect's registration No. 3974                      project                                           client                           job no.   drawn   drawing                dwg no.
GSPublisherVersion 565.9.54.75

Page 12

                                                                                                                                            rev  date   issued details
                                                                                                                                             B 07.06.21 MS Preliminary Sketch Design
                                                                                                                                                                                                                                    Sketch Design




                                         a: suite 6, 8 kingfisher drive, peregian beach, qld 4573
                                         p: (07) 5471 3033                                          Peregian Beach Community House - Fire Tech Lab                                                       Scale

                     sparks architects   www.sparksarchitects.com
                                                                                                    255 David Low Way, Peregian Beach                 Noosa Shire Council              183       MS      Perspectives Sheet 4   SK 4.4
                                         sparks architects pty. ltd. abn 89 124 611 721
                                         qld architect's registration No. 3974                      project                                           client                           job no.   drawn   drawing                dwg no.
GSPublisherVersion 565.9.54.75

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.