NOOSA COUNCIL IDAS Development Application Decision Notice                                                   6 of 14


41.    The existing pathway between the two existing lots shall have lighting installed from Goodchap Street to
       the rear boundary of Lot 4. This lighting shall have a high energy efficient rating to the reasonable
       satisfaction of Council and be designed to meet appropriate safety standards and not to adversely impact
       residences in the area.
Vegetation Protection & Preservation
42.    Vehicular pavements within the drip zone of any of the existing trees on site to be retained shall be
       designed as a pervious pavement (such as grass paving cells or similar), as this will allow water that falls
       on this surface to penetrate to the trees root system. The pavement shall be constructed so as not to
       damage the tree or their root system and in this regard temporary fencing shall be provided around the
       trees during construction to help protect them.
      Plans shall be submitted to the Council for approval that clearly show the type and extent of the pervious
      pavement and the temporary fencing prior to obtaining a Development Permit for Operational Works.
Frontage Works
43.    Tree planting is required to the Goodchap Street frontage of Proposed Lot 5 in accordance with Planning
       Scheme Policy PSP03 Landscaping Plants & Guidelines.
Roof Water & Stormwater Drainage
44.    Roof runoff from any new building shall be directed to a rainwater storage system or tank (minimum
                                                        2
       storage the greater of 5000 litres or 15 litres/m of roof area ) that is installed to ensure water from the
       tank is used for external uses (such as watering gardens, irrigation, ornamental ponds, water features,
       outdoor cleaning, etc) and for use in flushing of toilets internal to the building. All rainwater tanks are to
       be designed and installed in accordance with the Queensland Development Code (QDC), Part 25 –
       Rainwater Tanks, and shall be part of the plumbing application in conjunction with the building approval.
       The location and capacity of the tanks shall be clearly shown on the plans submitted for Building Works /
       Operational Works approval and any overflow shall be directed to an approved discharge point.

45.    All stormwater drainage (including roof water overflow from the rainwater storage system) shall be
       collected and discharged so there is no net increase in stormwater runoff from the site

46.    A Stormwater Management Plan shall be submitted to Council in conjunction with an operational works
       application to demonstrate how water quality and quantity objectives are to be met. This Management
       Plan shall set the objectives and include a plan indicating location and sizing of the devices prosed. The
       operational works application shall be in accrordance with this plan and buildings shall be modified if
       required to accommodate the necessary treatment infrastructure.
       All other clean stormwater, such as roof water, can be collected on site and discharged through a single
       underground drain line directly into the existing drainage system, bypassing the grease/oil arrestor and
       treatment system.
       A maintenance plan for the treatment devices shall be complied with for the duration of the approved
       uses.
       A Development Permit for Building Works shall not be granted until a Development Permit for Operational
       Works has been issued in regard to the drainage scheme.
47.    All site stormwater drainage shall be by means of a gravity system.
Sewer Mains
48.    All parts of the site shall be connected to Council’s existing sewerage reticulation systems and be
       constructed in accordance with Council’s standards and requirements at no cost to Council.
Town Water Supply
49.    All parts of the site shall be connected to Council’s existing town water supply and be constructed in
       accordance with Council’s standards and requirements at no cost to Council.

50.    For Multiple Uses (including Building Format Plans, Group Title Plans, etc) the development shall be
       served by:

       50.1. A single Body Corporate water meter to measure the total water consumption (including fire hose
             reels, but excluding fire hydrants and fire sprinkler systems), and

       50.2. Individual water meters to each tenement capable of being separately rated, and

       50.3. A fire service (fully testable single detector check with metered bypass), where applicable, for flows
             to fire hydrants and fire sprinkler systems (excluding fire hose reels).




MSOffice c:\docume~1\shesse\locals~1\temp\bcl technologies\easypdf 5\@bcl@ac08479b\@[email protected]

Used in these records

About this file

File size
63 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

SUPERSEDED Negotiated Decision Notice [As Published].pdf · 63 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.