Appendix B- Geotechnical Investigation
Attached to the e-mail MCU15/0070 Stormwater & Geotech reports Email 2 of 3.
Project No. 115-17158 April, 2015 Ref: 1-17158, 2015-04-08, BR VER 1 Page | 14 John Jamieson – GEOTECHNICAL INVESTIGATION - Proposed Residence, 38 Park Crescent, Sunshine Beach * * * If the recommendations of this report are followed and included in the design and construction of the proposed building, we believe the construction will not adversely affect the existing slope stability of the site. 7.0 ADDITIONAL GEOTECHNICAL INVESTIGATION It is recommended that additional investigation be carried out following demolition of the existing residence. The investigation should include a ‘deep’ borehole to further identify the subsurface conditions at depth for piling design.