TPC 1673 Decision (May 1984)

of 3

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

P.C. Rodger
ECR/KH/PPCL673

29th May, 1984

Mr D.J. Tatton,
P.O. Box 41, _
NOOSA HEADS, Q. 4567

Dear Sir,

Re: Allots 180, 181 & 182 Section VII,

 

Your application seeking the consent of the Council to erect
a multiple dwelling of twelve (12) units on _ the
abovedescribed land was considered by the Council at its May,
1984 meeting.

It was a decision of the Council, having considered relevant
matters, that the application as submitted be approved. The
conditions to which the consent granted is subject are as
shown below: -

Ls Compliance with all relevant Town Plan Provisions,
Bylaws and Policies.

a Permanent covered car parking to be provided on the
site for twelve (12) vehicles together with space
sufficient for three (3) visitors' vehicles. Areas
on which vehicles will be driven and/or parked to
be provided with a flexible or other pavement
surfaced with bitumen seal coat, asphaltic or other
concrete properly constructed and maintained to
good engineering standards to the satisfaction of
the Council's Engineer. Plans and specifications
for such areas including footpath crossings to be
submitted prior to issue of a Building Permit.
Vehicular access to and from the site to be
designed so as to ensure that sufficient area is
available for manoeuvring and turning to permit
forward movement to and from the road.

3. A concrete invert and paved access to connect to
the existing bitumen road pavement to be
constructed to the satisfaction of the Council's
Engineer.

4, Connection to Council's sewerage system.
Log in to download the original file

TPC 1673 Decision (May 1984).pdf · 497 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 2 pages

Page 2

Letter T.P.C. 1673 Cont'd ~ page 2 -

5.

6.

10.

ll.

Connection to Council's water supply facility at
the applicant's expense.

Stormwater, including that from roofed and paved
areas to be disposed of by underground means to
Council's existing disposal facilities.

Comply with the reasonable requirenents of the
Regional Fire Safety Officer.

The approval given herein does not absolve the
applicant from the responsibility of submitting for
approval, working drawings complying with the
Building Act 1975 as amended am the Standard
Building Bylaws. Such drawings shall be
substantially in accordance with the Town Planning
Consent approval and related drawings and approval
pursuant to the Building Act shall be obtained
prior to any building works being carried out on
the site. This consent approval does not imply
that building approval will be granted.

The approval herein is for Town Plan Consent only
and does not imply that Council consent will be
granted to an application under the Group Titles
Act or Building Unit Titles Act.

In accordance with Clause 3 (2) of Part IT of
Council Bylaws, Chapter XLIV (‘Town Planning),
Council's approval is valid for a period of two (2)
years at the expiration of which period the Council
may take action to revoke its approval if in the
opinion of the Council, substantial progress has
not been made in erecting the building or other
structure the subject of the consent permit; or
the land, the subject of the consent permit, is not
being used substantially in accordance with the
purposes for which consent was granted.

An identification survey of the subject site is to
be carried out by an authorised surveyor and is to
be submitted to Council at the time of the
foundation inspection by the Council's Building
Surveyor or immediately thereafter. Such survey
shall set out the boundaries of the site and the
position of the building(s) on the site.

Page 3

Letter T.P.C. 1673 Cont'd - page 3 -

12.

13.

14,

15.

16.

17.

18.

19.

To ensure compliance with any and all conditions of
this approval, Council will require that you enter
into a Bank Bond to guarantee performance. The
value of such bond would be determined and would
need to be lodged prior to issue of a building
permit and any costs incidental thereto will be the
applicant's responsibility.

The conditions of this permit are to be completed
prior to occupancy of the building and if this is
not done, Council reserves the right to call on
bond moneys lodged to carry out the works involved.

Provision shall be made for the storage and removal
of refuse in accordance with the Council's policies
and to the requirements of the Council's Health
Surveyor.

The location of points for mail delivery
(Letterboxes) shall be to the requiranents of
Australia Post, generally in accordance with its
policy on the matter.

The electricity supply facilities to the site shall
be upgraded to the requirements of the S.F.Q.E.B.

The development should be carried out in accordance
with minimum floor levels and filling levels to the
requirements of the Council's Shire Engineer.

The offer to contribute to water supply
augmentation in the amount of $5,400 is accepted.
Such contribution shall be made prior to the issue
of a building permit.

The development shall be carried out so as not to
interfere with the existing circumstances or
stability of a concrete canal revetment wall and
associated works on the boundary of the site
adjoining the canal.

Yours faithfully,

2

D.J. Philpot,
SHTRE CLERK,

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.