3.2. Revegetation
Revegetation is required around the entirety of the rehabilitation area, focusing on a scattered planting
of small – medium trees to re-enhance the canopy coverage after weed control occurs in the area.
Ground covers and native grasses will be densely planted and utilized in areas where environmental
weed grasses are set to be removed. Revegetation of these areas will assist with long term prevention
of weed infiltration and improve existing vegetation health.
3.2.1. Planting Areas
Although reference documents state the rehabilitation area is 4,281m2, an existing dam is present in
the middle of the rehabilitation area, as well as current weed infestations reducing the viable planning
area. The section identified for rehabilitation on the eastern side of the rehabilitation area is also
currently unclear due to the lack of surveyor markings/pegs during the preliminary Site inspection and
GPS inaccuracies. After the initial weed control works are completed and all the viable planting space
can be accounted for, an accurate quantity of tube stock required for revegetation planting is to be
provided.
One of the viable planting areas along the dam at the western side of the rehabilitation area is shown
in Figure 4 below. Another viable planting area is the relatively clear section near the entry gate and
driveway also at the western side of the rehabilitation area (Figure 5). After initial weed control works
and mulching have been completed, infill planting can occur in these areas.
Figure 4. Viable planting area – western side of rehabilitation area.
REHABILITATION MANAGEMENT PLAN | 43 – 45 Summit Rd, Pomona 9
Document Set ID: 22570983
Version: 1, Version Date: 05/09/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.