Decision Notice - Approved by Delegation of Authority MCU21 0221

of 1

Page text shows just the words. Original shows the document exactly as it was published.

Officer: 	Patrick Murphy
Direct Telephone: 	61753296436
Our Reference:	MCU21/0221
Your Reference:	n/a
10 March 2022
SD Stewart & RL Stewart
C/- Brennan Planning Pty Ltd
44 Maple St
COOROY  QLD  4563
[email protected]
Dear Sir/Madam,
Decision Notice
Planning Act 2016
I refer to your application and advise that on 10 March 2022, Council decided to approve the application, subject to conditions.
Details of the decision are as follows:
application details
Application No:	MCU21/0221
Street address:	797 Ringtail Creek Rd Pomona Qld 4568
Real property description:	Lot 4 RP 213871
Planning Scheme:	Noosa Plan 2020 (25 September 2020)
Decision details
Council decided to issue the following type of approval:
Development Permit for Material Change of Use - Dwelling house
CURRENCY PERIOD of approval
The currency period for this development approval is stated in the conditions below.
assessment manager conditions
PLANNING
When Conditions must be Complied With
Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to the use commencing, and then compliance maintained at all times while the use continues.

Approved Plans
Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions.
Plan No.	Rev.	Plan/Document Name	Date
0521SS sheet 1		Site Plan  - Accolade Building Design	02.02.2022
0521SS sheet 2		Floor Plan  - Accolade Building Design	02.02.2022
0521SS sheet 3		Elevations  - Accolade Building Design	02.02.2022
0521SS sheet 4		Sections  - Accolade Building Design	02.02.2022
N/A	1	Ecological Assessment Report prepared by Equilibrium Ecology	14/12/2021
N/A	1	Bushfire Hazard Assessment prepared by Equilibrium Ecology	25/10/2021
Currency Period
This development approval lapses if the use has not happened by 10 March 2028 unless an application to extend the currency period is approved by Council.
Nature of use
The premises must be used in accordance with The Noosa Plan definitions for a Dwelling and must be for the exclusive use of one household only.
The site must not be used as Multiple Dwelling and/or Short Term Accommodation or any other residential use as defined by The Noosa Plan, except a Dwelling.
The existing shed detailed on Accolade Building Design - Site Plan Sheet 1 is to be decommissioned prior to the use of the dwelling commencing.
Performance Bond
Security in the form of a cash bond or trading bank guarantee to the sum of $10,000 must be submitted to Council, to secure performance of all conditions of this approval, prior to the issue of a Development Permit for Building Works. The cash bond or trading bank guarantee will be returned on performance of the conditions of approval less any costs incurred by Council in respect of enforcing performance of this permit. Council reserves the right to call upon the bond or guaranteed sum to effect compliance with conditions.
Retention of Existing Trees
All trees and vegetation identified for retention must be protected in accordance with AS 4970, Protection of trees on development sites.
Vegetation areas for protection must:
Be protected in accordance with the approved Sheet 1 - Site Plan.
Be protected with a 1.8m high temporary safety fence or temporary barrier mesh or three-strand plain wire with pickets at 3m centres.
Have the fence installed and maintained for the entire period of construction.
Have ‘Exclusion Zone’ (‘No Go’) signage fixed to the fence at 10m centres.
Have no construction material, equipment or personnel entering the area except to undertake approved rehabilitation activities.
*(Refer to Advisory Note)
Vegetation Removal
All tree and vegetation removal works must be undertaken by a qualified person*.
*(Refer to Advisory Note)
A qualified person * must be engaged for the duration of the works to:
Ensure works are carried out in accordance with Sheet 1 – Site Plan listed within this Decision Notice.
Oversee installation of all tree protection fencing prior to commencement of any works onsite (including any clearing).
Supervise tree protection within the development site and frontages, prior to, during and following construction in accordance with AS 4970, Protection of trees on development sites.
Oversee approved tree removal in proximity to retained trees.
Undertake a risk assessment of all trees within striking distance of the development works and site and carry out hazard removal and amenity pruning in accordance with AS 4373, Pruning of amenity trees.
*(Refer to Advisory Note)
Fauna Management
A qualified person* must be engaged to manage fauna prior and during clearing to:
Ensure works are carried out in accordance with the Nature Conservation Act 1992.
Undertake pre-clearing inspections including fauna relocation and removal or blocking of all vacant hollows.
Ensure clearing works avoids nesting times of animals and birds.
Co-ordinate staging and sequence of clearing with fauna protection.
Protect and recover fauna during clearing operations (not previously removed).
Manage the translocation of animals and recovery procedures in accordance with relevant legislation.
*(Refer to Advisory Note)
Land Rehabilitation
A “no clearing zone” must be established and maintained over the land area located outside the Asset Protection Zone identified as Exempt Vegetation Clearing and Extent of Vegetation Clearing on Sheet 1 – Site Plan on the Approved Plans. The following activities must not be carried out within the no clearing zone:
clearing, cutting down, poisoning, lopping or pruning of native vegetation which is indigenous to, or planted within, the zone
soil/spoil dumping and/or compacting
soil excavation, other than for planting indigenous native plants.
The following exceptions apply:
declared plants under the Land Protection (Pest and Stock Route Management) Act 2002 and sub-ordinate Regulation 2003, and any Council Listed Environmental Weeds, Exotic Grasses and other plants identified in writing by Council
indigenous native trees which pose a well-founded threat to persons or property as approved in writing by Council
controlled bushfire burns to maintain ecological processes subject to submission of a Bushfire Management Plan and agreed in writing by Council.
A qualified person* must manage plant pest (weeds) to:
Ensure plants listed as Class 1 and 2 declared pests within Council’s Pest Management Plan are controlled and prevented from spreading.
Oversee management techniques that minimise regrowth, prevent damage to non-target species, retain conservation values and maintains site stability.
*(Refer to Advisory Note)
Bushfire Management
The development must be carried out in accordance with the Bushfire Hazard Assessment report listed within this Decision Notice.
A copy of the Bushfire Hazard Assessment report listed within this Decision Notice must be provided to the nearest fire authority.
The site must be provided with a water storage reservoir having a minimum 5000 litres of water for emergency firefighting purposes. Such storage must be provided in addition to the water supply capacity required for the use and must be provided in the form of either an accessible dam, swimming pool, or rainwater tank. If by rainwater tank, water storage for firefighting purposes must be provided either in a separate rainwater tank or a reserve section in the main water supply tank on which:
the domestic take off from the tank is at or above the 5,000 litre point; and
standard rural fire brigade fittings are fitted to the tank outlet for access by four wheel drive rural services vehicles
The site must be provided with an auxiliary power supply such as a petrol driven fire fighter pump (or generator), together with a hose of sufficient length to easily reach around to all sides of the building.
Certification must be submitted to Council from a qualified person* which certifies that the development has been constructed in accordance with the bushfire management conditions of this Decision Notice.
*(Refer to Advisory Note)
referral agencies
Not applicable.
Advisory notes
The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions:
Qualified Person
For the purpose of preparing a Fauna Management Plan, a qualified person is considered to be an ecologist with a minimum of 3 years current experience in the field of fauna assessment and management.
Undertaking, supervising tree works and preparing arboriculture certification, is considered to be a person with a minimum three years current experience in tree protection, hazard identification/mitigation and Specifying Trees – a guide to assessment of tree quality (NATSPEC) assessment and either:
International Society of Arboriculture (ISA) certification; or
A Diploma of Arboriculture.
Managing Fauna protection is considered to be a certified Fauna Spotter Catcher.
For the purpose of preparing a Bushfire Management Plan, and for certifying compliance with the bushfire requirements of this Decision Notice, a qualified person is considered to be an ecologist with a minimum of 3 years current experience in the field of bushfire assessment and management.
Retention of Existing Trees
The existing trees on adjoining properties must be retained and protected during construction wherever achievable. To avoid doubt, this advisory note is not intended to exclude the operation of Chapter 3 of the Neighbourhood Dispute Resolution Act 2011 following construction of the development which is the subject of this development approval.
Removal of Existing Trees and Vegetation
Stockpiling mulch to the appropriate volume and separation is required for fire mitigation as well as optimum weed seed sterilisation.
Infrastructure Charges
All developments and/or changes to existing developments may require payment of “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution” made pursuant to the planning legislation and regulations current at the time of issue. For further information, please refer to https://www.noosa.qld.gov.au/planning-development/development-tools-guidelines/infrastructure-charges
property notes
MCU21/0221– No Clearing Zone
A “no clearing zone” applies to this property for the purpose of vegetation protection. The landowner must maintain the property in accordance with the ecological preservation conditions of Council Approval MCU21/0221.
MCU21/0221 – Bushfire Management
To ensure the safety of people and property on this property is maintained, all buildings and structures must be sited and/or constructed in accordance with the bushfire management conditions of Council Approval MCU21/0221 and associated Operational Work approvals.
VARIATION approval details
Not applicable.
further development permits required
Type of Development Permit Required	Subject of the required Development Permit
Development Permit for Building Works	All building work.
submissions
Not applicable.
RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the Planning Act 2016 is attached.
During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval. If Council agrees or agrees in part with the representations, a negotiated decision notice will be issued. Only one negotiated decision notice may be given.
OTHER DETAILS
If you wish to obtain more information about the decision, electronic copies are available on line at www.noosa.qld.gov.au or at Council Offices.

Yours faithfully,

Nadine Gorton
Development Planner

Enc:	Appeal Rights
Approved Plans/Documents

	Appeal Rights PLANNING ACT 2016 & PLANNING REGULATION 2017

Chapter 6 Dispute resolution
Part 1 Appeal rights
229 Appeals to tribunal or P&E Court
(1)	Schedule 1 of the Planning Act 2016 states –
(a)	Matters that may be appealed to –
(i)	either a tribunal or the P&E Court; or
(ii)	only a tribunal; or
(iii)	only the P&E Court; and
(b)	The person-
(i)	who may appeal a matter (the appellant); and
(ii)	who is a respondent in an appeal of the matter; and
(iii)	who is a co-respondent in an appeal of the matter; and
(iv)	who may elect to be a co-respondent in an appeal of the matter.
(2)	An appellant may start an appeal within the appeal period.
(3)	The appeal period is –
(a)	for an appeal by a building advisory agency – 10 business days after a decision notice for the decision is given to the agency; or
(b)	for an appeal against a deemed refusal – at any time after the deemed refusal happens; or
(c)	for an appeal against a decision of the Minister, under chapter 7, part 4, to register premises or to renew the registration of premises – 20 business days after a notice us published under section 269(3)(a) or (4); or
(d)	for an appeal against an infrastructure charges notice – 20 business days after the infrastructure charges notice is given to the person; or
(e)	for an appeal about a deemed approval of a development application for which a decision notice has not been given – 30 business days after the applicant gives the deemed approval notice to the assessment manager; or
(f)	for any other appeal – 20 business days after a notice of the decision for the matter, including an enforcement notice, is given to the person.
Note –
See the P&E Court Act for the court’s power to extend the appeal period.
(4)	Each respondent and co-respondent for an appeal may be heard in the appeal.
(5)	If an appeal is only about a referral agency’s response, the assessment manager may apply to the tribunal or P&E Court to withdraw from the appeal.
(6)	To remove any doubt. It is declared that an appeal against an infrastructure charges notice must not be about-
(a)	the adopted charge itself; or
(b)	for a decision about an offset or refund-
(i)	the establishment cost of trunk infrastructure identified in a LGIP; or
(ii)	the cost of infrastructure decided using the method included in the local government’s charges resolution.
230 Notice of appeal
(1)	An appellant starts an appeal by lodging, with the registrar of the tribunal or P&E Court, a notice of appeal that-
(a)	is in the approved form; and
(b)	succinctly states the grounds of the appeal.
(2)	The notice of appeal must be accompanied by the required fee.
(3)	The appellant or, for an appeal to a tribunal, the registrar must, within the service period, give a copy of the notice of appeal to –
(a)	the respondent for the appeal; and
(b)	each co-respondent for the appeal; and
(c)	for an appeal about a development application under schedule 1, table 1, item 1 – each principal submitter for the development application; and
(d)	for and appeal about a change application under schedule 1, table 1, item 2 – each principal submitter for the change application; and
(e)	each person who may elect to become a co-respondent for the appeal, other than an eligible submitter who is not a principal submitter in an appeal under paragraph (c) or (d); and
(f)	for an appeal to the P&E Court – the chief executive; and
(g)	for an appeal to a tribunal under another Act – any other person who the registrar considers appropriate.
(4)	The service period is –
(a)	if a submitter or advice agency started the appeal in the P&E Court – 2 business days after the appeal has started; or
(b)	otherwise – 10 business days after the appeal is started.
(5)	A notice of appeal given to a person who may elect to be a co-respondent must state the effect of subsection (6).
(6)	A person elects to be a co-respondent by filing a notice of election, in the approved form, within 10 business days after the notice of appeal is given to the person.
231 Other appeals
(1)	Subject to this chapter, schedule 1 and the P&E Court Act, unless the Supreme Court decides a decision or other matter under this Act is affected by jurisdictional error, the decision or matter is non-appealable.
(2)	The Judicial Review Act 1991, part 5 applies to the decision or matter to the extent it is affected by jurisdictional error.
(3)	A person who, but for subsection (1) could have made an application under the Judicial Review Act 1991 in relation to the decision or matter, may apply under part 4 of that Act for a statement of reasons in relation to the decision or matter.
(4)	In this section –
decision includes-
(a)	conduct engaged in for the purpose of making a decision; and
(b)	other conduct that relates to the making of a decision; and
(c)	the making of a decision or failure to make a decision; and
(d)	a purported decision; and
(e)	a deemed refusal.
non-appealable, for a decision or matter, means the decision or matter-
(a)	is final and conclusive; and
(b)	may not be challenged, appealed against, reviewed, quashed, set aside or called into question in any other way under the Judicial Review Act 1991 or otherwise, whether by the Supreme Court, another court, a tribunal or another entity; and
(c)	is not subject to any declaratory, injunctive or other order of the Supreme Court, another court, a tribunal or another entity on any ground.
232 Rules of the P&E Court
(1)	A person who is appealing to the P&E Court must comply with the rules of the court that apply to the appeal.
(2)	However, the P&E Court may hear and decide an appeal even if the person has not complied with the rules of the P&E Court

[word/footer1.xml]
Page 5 of 7

[word/footer2.xml]
PO Box 141		P. (07) 5329 6500	[email protected]	
	TEWANTIN  QLD  4565	F. (07) 5329 6501	www.noosa.qld.gov.au
				Page 1 of 7

[Attachment: image3.png (image text)]
ee) NOOSA COUNCIL
Log in to download the original file

Decision Notice - Approved by Delegation of Authority MCU21 0221.docx · 323 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.