Minor Change Existing Approval 132004 5744 13 [As Published] · 132004.5744.13

of 17

Text shows just the words. Original shows the document exactly as it was published.

                                                              Officer:            Cameron Smith
                                                              Direct Telephone:   07 53296178
                                                              Our Reference:      132004.5744.13
                                                              Your Reference:     M1717P

               5 March 2025


               Noosa Domain Pty Ltd
               C/- JFP Urban Consultants Pty Ltd
               Kon-Tiki Business Centre
               Tower 1, Level 2, Suite T1-209,
               55 Plaza Parade
               MAROOCHYDORE QLD 4558
               [email protected]



               Dear Sir/Madam,
                                            Decision Notice – Minor Change
                                                         Planning Act 2016

               I refer to your application received on 6 December 2024, requesting a minor change to an existing
               development approval. Council decided your requested changes.
               Details of the decision are as follows:
               1.      APPLICATION DETAILS

                   Application No:               132004.5744.13

                   Street address:               35 Walter Hay Dr Noosaville

                   Real property description:    Part Lot D SP 215280

                   Planning Scheme:              Noosa Plan 2020 (25 September 2020)

               2.      DECISION DETAILS

               The following type of approval was issued on 22 September 2005
               •       Development Permit for a Material Change of Use (Retirement Community – 165
                       Dwelling/Accommodation Units and Ancillary Facilities)
               In relation to the request to make a minor change to the existing approval, Council on 27 February
               2025, decided to approve the requested changes. The changes are detailed below.
               A.      Approve the change.
               B.      Amend conditions 1, 2 and 11.
               C.      Additional condition 93
               3.      CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.



               ABN 97.969.214.121                                                                         PO Box 141
               noosa.qld.gov.au                                                                    Tewantin QLD 4565
               [email protected]                                                                    07 5329 6500
                                                                                                             Page 1 of 17
Document Set ID: 23615315
Version: 3, Version Date: 05/03/2025
Full text of the other 16 pages

Page 2

               4.     ASSESSMENT MANAGER CONDITIONS

               Land Use
               Amended Condition – Approved Plans
               1.     Development authorised by this approval must be undertaken generally in accordance with
                      the Approved Plans listed in the table below.

                         Plan No.        Rev.              Plan/Document Name                  Date

                         1519-WD01       -                 Revised Site Plan prepared by Greg December 2015
                                                           Gibbs

                         0379-SK05       B                 Drainage Design                     October 2004

                         TP-01           P5                Site Plan    prepared   by   Select 22 April 2024
                                                           Architects

                         TP‐02           P3                Proposed Ground Floor Plan 22 April 2024
                                                           (Building A) prepared by Select
                                                           Architects

                         TP-03           P3                Proposed First Floor Plan (Building 22 April 2024
                                                           A) prepared by Select Architects

                         TP-04           P3                Proposed Roof Plan (Building A) 22 April 2024
                                                           prepared by Select Architects

                         TP-05           P1                Proposed Elevations (Building A) 16 May 2017
                                                           prepared by Select Architects

                         TP-06           P4                Proposed Ground Plan (Building B) 22 April 2024
                                                           prepared by Select Architects

                         TP-07           P4                Proposed First Floor Plan (Building 22 April 2024
                                                           B) prepared by Select Architects

                         TP-08           P4                Proposed Roof Plan (Building B) 22 April 2024
                                                           prepared by Select Architects

                         TP-09           P1                Proposed Elevations Sheet 1 16 May 2017
                                                           (Building B) prepared by Select
                                                           Architects

                         TP-10           P1                Proposed Elevations Sheet 2 16 May 2017
                                                           (Building B) prepared by Select
                                                           Architects

                         0379-SK-CC      1A                Community Centre Floor        Plan November 2004
                                                           prepared by Greg Gibbs

                         0379-SK-CC      2A                Community     Centre   Elevations November 2004
                                                           prepared by Greg Gibbs

                         0379-VILLA-A    A                 Type A Villa prepared by Greg November 2004
                                                           Gibbs




                                                                                                Page 2 of 17
Document Set ID: 23615315
Version: 3, Version Date: 05/03/2025

Page 3

                           0379-VILLA-B         A                   Type B Villa prepared by Greg November 2004
                                                                    Gibbs

                           0379-VILLA-C         A                   Type C Villa prepared by Greg November 2004
                                                                    Gibbs

                           0379-VILLA-D         A                   Type D Villa prepared by Greg November 2004
                                                                    Gibbs

                           0379-VILLA-E         A                   Type E Villa prepared by Greg November 2004
                                                                    Gibbs

                           LA-01                B                   Landscape Concept Plan – Entry June 2005
                                                                    prepared by Land Graphics

                           LA-01                B                   Landscape Concept Plan prepared June 2005
                                                                    by Land Graphics

                           1514-WD02            -                   The Singleton Floor Plan prepared December 2015
                                                                    by Greg Gibbs

                           1514-WD04            -                   The Singleton Elevations prepared December 2015
                                                                    by Greg Gibbs

                           1514-WD01            -                   The Singleton Site Plan + Finishes December 2015
                                                                    prepared by Greg Gibbs

                           132004.5744.13 – Maintenance Shed

                           M1717P 45            M1717P 45           M1717P 45                               M1717P 45

                           M1717P 46            M1717P 46           M1717P 46                               M1717P 46

                           CLOU04-1058          CLOU04-1058         CLOU04-1058                             CLOU04-1058

               2.     All buildings shall have a roof pitch of no less than 12 degrees, with roof overhangs at least
                      600mm wide, except for the following:
                      a.      2.1      Elevations that do not front an internal street or the rear outdoor living areas;
                      b.      Areas shown as flat roofs on Drawings 0379 SK AB-04 & 06 and 0379 SK SAB-02A &
                              03A prepared by Greg Gibbs Architects;
                      c.      The 'Maintenance Shed' annotated on the Site Plan Drawing M1717P Rev.C prepared
                              by JFP Urban Consultants.
               3.     Sunhoods shall be provided over all windows facing north, west and east on the ground floor
                      of 2 storey buildings.
               4.     Deleted.
               5.     Buildings shall vary in design, colour and finishes, with building finishes to vary in texture,
                      detailing and the like. A scheme detailing the colour and building finishes shall be submitted
                      to Council prior issue of a Development Permit for Operational Works.
               6.     Broad expanses (15m2 or more) of high contrast shades of white or bright colours or pasts
                      on external walls shall be avoided.
               7.     Soft landscaping (planting) shall be provided over a minimum of 20% of the site area.




                                                                                                             Page 3 of 17
Document Set ID: 23615315
Version: 3, Version Date: 05/03/2025

Page 4

               8.     A minimum of 1 covered car parking space shall be provided for each of the ‘Villa’ dwelling
                      units and ‘Building A’ and ‘Building B’. The covered car parking spaces shall be in proximity
                      to the dwelling units to the reasonable satisfaction of the Council’s delegate.
               9.     The community centre shall be for residents of the retirement village and their visitors. The
                      community centre shall not be for use by the general public.
               10.    The caravan/boat storage parking area and the visitor parking, bin storage to Walter Hay
                      Drive shall maintain a 2 metre landscaped setback from Walter Hay Drive North at a
                      minimum.
               11.    All buildings shall maintain a 15 metre setback from the site's frontage to Walter Hay Drive
                      North and Eenie Creek Road, except for the following
                      a.      The depot building, which shall be set back a minimum of 6 metres from the front
                              boundary to Walter Hay Drive North;
                      b.      The covered car parking areas, which shall be set back a minimum of 3.8 metres from
                              Eenie Creek Road;
                      c.      The electricity substation, which shall be set back a minimum of 8.2 metres from Eenie
                              Creek Road;
                      d.      The maintenance shed, which shall be set back a minimum of 4.3 metres from Eenie
                              Creek Road
               12.    The proposed development shall comply with the noise management strategies contained in
                      the report “Noise Assessment Report Retirement Village corner Walter Hay Drive and Eenie
                      Creek Road, Noosa – Report No. 507 – 611 Revision 2” prepared by Noise Measurement
                      Services, dated 16 June 2005 and include a 2 metre high acoustic barrier constructed along
                      the complete length of the site frontages adjacent Walter Hay Drive. Heights of this acoustic
                      barrier are to be relative to the finished level of the unit’s minimum floor level with a minimum
                      superficial mass of 15 kg/m2.
               13.    On completion of the development, a certificate by an appropriately qualified acoustic
                      consultant shall be submitted to Council demonstrating that the development complies with
                      the noise condition.
               14.    All hot water systems installed shall be either solar systems; electric heat pump systems or
                      gas systems (LPG or natural).
               15.    To meet the needs of people across a range of abilities and ages and be adaptable for the
                      changing needs of people over time, all dwelling and accommodation units shall include the
                      following:
                      1.      Are wheel chair accessible;
                      2.      Are accessible by a lift for those units located above the ground floor;
                      3.      All doors are a minimum of 870 mm wide; and
                      4.      Hallways are a minimum of 1.2m wide; and
                      All entries into the dwelling unit and internal doorways, have no more than a 10mm change
                      in level; and
                      Has an accessible toilet and bathroom, complete with reinforced walls, that can be reached
                      along an accessible path; and
                      A window, no higher than 600mm from the floor is provided in at least 1 bedroom to allow a
                      seated person to look out of and open and close the window; and
                      All power points are placed up from the floor (minimum 600mm) and out from the corner
                      (minimum 500mm) to facilitate disabled access.
               16.    A verification survey of the building is to be carried out by a Licensed Surveyor and a
                      certificate lodged with Council at completion of the work confirming compliance with the



                                                                                                         Page 4 of 17
Document Set ID: 23615315
Version: 3, Version Date: 05/03/2025

Page 5

                      minimum required floor level and the maximum building height above the finished ground
                      level, required by the provisions of the Planning Scheme.
               17.    The development must be undertaken and operated in a manner that causes no detrimental
                      effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
                      lighting nuisance or other emissions.
               18.    The proposed development shall have all kitchen, laundry and bathroom fittings that comply
                      with the AAA Water Conservation rating System as defined by the AS/NZS 6400 (Water
                      Efficient Products – Rating and Labelling 2003) and AS/NZS 3500 (national Plumbing and
                      Drainage Standard part 1.2), with toilets to comply with the AAAA Water Conservation Rating
                      System. All tap ware and shower roses shall not exceed a maximum flow of 9 litres per min.
                      Dishwaters and washing machines are excluded from this requirement.
               19.    The open space and setback areas are to be landscaped in accordance with Council’s Policy
                      on Landscaping Guidelines and a properly prepared landscape plan and prepared by a
                      suitably qualified landscape architect or horticulturalist. Such landscaping is to be completed
                      prior to the premises being occupied and maintained at all times thereafter.
               20.    Landscaping shall be provided in the road reserve and shall include vegetation to screen any
                      fencing (including sound attenuation fencing) along Walter Hay Drive North. This
                      landscaping shall maintain required visibility for traffic and pedestrians. All fencing shall be
                      located in a manner to avoid existing trees and shall be setback a minimum of 2 metres to
                      the road frontages, apart from where constructed on the existing block retaining wall and to
                      Eenie Creek Road frontage where located along the top of the landscaped mound.
               21.    Existing trees on the site and within road reserves are to be retained, except where required
                      to be removed due to building operations or the conduct of the approved use. The landscape
                      plans referred to above are to denote areas of existing vegetation or existing trees proposed
                      to be retained and address the completion of the vegetated buffer required to Walter Hay
                      Drive North and Eenie Creek Road.
               22.    Any advertising sign or device is to comply with the provisions of Council's policies on
                      advertising.
               23.    Security in the form of a cash bond or trading bank guarantee to the sum of $100,000 must
                      be submitted, to secure performance of all conditions of this approval, prior to the issue of a
                      Development Permit for Operational Works. The cash bond or trading bank guarantee will
                      be returned on performance of the conditions of approval less any costs incurred by Council
                      in respect of enforcing performance of this permit.
               24.    Council reserves the right to call upon the bond or guaranteed sum referred to in this approval
                      to effect compliance with conditions.
               25.    The developer must obtain all of the other Development Permits referred to in the Decision
                      Notice, prior to obtaining a Development Permit for building works.
               26.    The relevant period for the Development Permit for a material change of use of premises
                      shall be in accordance with the Integrated Planning Act 1997.
               Building Services
               27.    The swimming pool is to be contained within complying pool enclosures. Direct access from
                      any dwelling unit or building to the swimming pool or spa is not permitted
               Land Development
               River Flooding
               28.    All buildings proposed on site (and areas utilised for carparking purposes associated with the
                      buildings) shall be constructed to comply with Council’s Minimum Floor Height requirements
                      as defined in Council’s Planning Scheme and on Council’s Scheme Maps at the time of issue
                      of the Building Permit.
                       In this regard and as an indication only all buildings should have a Minimum Floor Height of
                       RL 2.5m (AHD), although garaged areas utilised for carparking purposes associated with


                                                                                                       Page 5 of 17
Document Set ID: 23615315
Version: 3, Version Date: 05/03/2025

Page 6

                       the residential use may be reduced by 0.3m. These levels however are subject to change
                       and verification shall be made to Council’s Land Development Section prior to obtaining a
                       Development Permit for Building Works.
               Vehicle Access
               29.    No right turn access to the development from Walter Hay Drive is permitted. A vehicular
                      access driveway to service the development shall be constructed from the Walter Hay Drive
                      North frontage of the site with a minimum width of 6.0m.
               30.    No right turn exit from the site will be permitted.
               31.    The gate shall be located far enough from the frontage to allow appropriate queuing for
                      vehicles awaiting gate opening so they do not affect traffic movements on Walter Hay Drive
                      North. The gate must also be positioned so that refuse vehicles and vehicles that mistakenly
                      enter the site can do a simple manoeuvre to leave the site.
               32.    All internal roads and driveways shall be designed and constructed to Council’s design
                      standards and to grades that prevent vehicles from scraping and/or bottoming whilst also
                      allowing pedestrians movements along the footpath without any level difference. Should any
                      driveways be constructed to grades that do not comply with AS2890.1-2004, Council will
                      require that the driveway be removed and reconstructed to levels that do comply.
                      Please note, a step between the driveway and the footpath areas shall be avoided, as it is
                      preferred to have the footpath continue at a constant grade to minimise the potential for
                      pedestrians to trip or fall.
               33.    All vehicles shall enter and leave the site in a forward direction.
               Vehicle Access Easement
               34.    A vehicle access easement shall be created over the proposed access driveway that gives
                      the Council (cars that mistakenly enter the site to exit) and refuse vehicles access to collect
                      refuse. The easement shall cover all the area required on site for manoeuvring and also
                      ensure that the vehicles can leave in a forward direction and shall benefit Council and burden
                      Lot 2 on SP 162077.
                      In this regard, plans submitted for Operational Works approval shall accurately show the
                      location of the easement.
                      In addition to this the Applicant’s Solicitor shall give Council’s Solicitor an appropriate
                      undertaking in writing that the Title Deed and the easement documents will be lodged at the
                      Land Titles Office and any additional Titles Office forms or requisitions requiring the consent
                      of Council will be attended to promptly.
                      A duly executed copy of the easement shall be submitted to Council for perusal prior to the
                      use commencing.
                      Any changes required by Council’s Solicitor must be corrected immediately.
               Internal Roads and Driveways
               35.    Internal Roads and Driveways shall be in accordance with Plan - Road Network & Parking
                      0379 SK04C dated October 2004 prepared by Greg Gibbs Architects, except as modified
                      herein.
               36.    Privacy screens and landscaping that are proposed will need to be clear of visibility splays
                      required for the speed environment proposed.
               Loading Areas
               37.    Loading zones and the Village bus space shall be constructed in accordance with Plan -
                      Road Network & Parking 0379 SK04C dated October 2004 prepared by Greg Gibbs
                      Architects, except as modified herein. They shall be sized for Small Rigid Vehicles as
                      required by AS2890.1-2004. These spaces shall be sign posted to indicate they are loading
                      zones and bus parking.



                                                                                                       Page 6 of 17
Document Set ID: 23615315
Version: 3, Version Date: 05/03/2025

Page 7

               Off Street Carparking
               38.    Carparking shall be provided within the site as shown on Plan – Road Network & Parking
                      0379 SK04C dated October 2004 prepared by Greg Gibbs Architects and as shown on the
                      Plan – Proposed Site Plan, drawing No TP-01 REV P1 dated 03 December 2020, prepared
                      by Select Architects, except as modified herein.
               39.    The carparking area shall be designed to comply with the provisions of AS 2890.1-2004 for
                      user class 1 with allowance for vehicles to enter and leave the site in a forward gear and with
                      a minimum head clearance (headroom) at any point of 2.2m.
               40.    The proposed turning areas at the end of the aisles shall be line-marked with chevrons and
                      have the words “No Parking” painted on the pavement. A sign shall also be provided to
                      indicate that the area is a “Turning Area Only” and that “No Parking is Permitted”.
               41.    All carparking shall be kept, maintained and line-marked in a condition fit for use.
               42.    All staff carpark spaces shall be clearly defined by line marking each space with the words
                      “Staff Parking Only” and by sign posting each space with a similar wording.
               Vegetation Protection
               43.    All vegetation that exists on site at a level of RL 3.5m (AHD) or higher along Eenie Creek
                      Road (ECR) and Walter Hay Drive North frontages is to be retained to act as a natural
                      vegetative strip and provide screening for any development (with the exception of vegetation
                      needed to be removed for the car spaces located in the ECR mound). Also vegetation in the
                      drainage area to the east of the site is to be retained except for weed removal. In this regard,
                      the applicant is required to clearly delineate areas of vegetation not to be removed on the
                      whole parcel, and submit a plan showing the areas of vegetation to be protected prior to the
                      commencement of any works on site.
               44.    A 15 metre vegetated strip is to be planted along the Walter Hay Drive North road frontage
                      of the site, comprising a densely vegetated drainage swale 10 metres in width and a further
                      5 metres of dense vegetation further within the development. To this end, vegetation is to
                      comprise remnant vegetation having a level of RL 3.5m (AHD) or higher and rehabilitated
                      vegetation comprising species endemic to the immediate area densely planted to provide a
                      complete visual screen to any development within proposed Lot 2.
               45.    Vehicular pavements within the drip zone of any of the existing trees on site to be retained
                      shall be designed as a pervious pavement (such as grass paving cells or similar), as this will
                      allow water that falls on this surface to penetrate to the trees root system. The pavement
                      shall be constructed so as not to damage the tree or their root system and in this regard
                      temporary fencing shall be provided around the trees during construction to help protect
                      them.
                      Plans shall be submitted to the Council for approval that clearly show the type and extent of
                      the pervious pavement and the temporary fencing prior to obtaining a Development Permit
                      for Operational Works.
               Frontage Works
               46.    Footpath improvements such as topsoiling, grassing, and tree planting are required to the
                      Walter Hay Drive North frontage of the site in accordance with Planning Scheme Policy PSP1
                      Landscaping Guidelines. Grass shall be couch, free of weeds.
               47.    A new 2.5m wide concrete path shall be constructed along the Walter Hay Drive North
                      frontage of the site from the pedestrian refuge north to the end of the property in accordance
                      with Council’s design standards and to an alignment that protects any underground services.
               48.    Pram ramps shall be installed at the intersection of the pathway with the new access in
                      accordance with Council’s Standard Drawing 9006. Where the pathway desire line crosses
                      splitter islands the path will be at road level.




                                                                                                       Page 7 of 17
Document Set ID: 23615315
Version: 3, Version Date: 05/03/2025

Page 8

               49.    All pathways and pram ramps (internal and external) shall be designed and constructed to
                      ensure pedestrian safety using non-slip materials and to produce an evenly graded surface
                      finish.
               50.    All redundant vehicular crossings to the site shall be removed and replaced by kerb &
                      channel, footpath paving and landscaping such as trees and grasses in accordance with
                      Council’s Standard specifications prior to commencement of the use permitted by this permit.
               Pathway Contributions
               51.    A pathway contribution of $49,774 towards external major pathways, in accordance with
                      Planning Scheme Policy PSP41 Coastal Major Pathway Contributions, shall be paid to the
                      Council prior to obtaining a Development Permit for Operational Works. This amount will be
                      subject to variations in the Consumer Price Index, All Groups Brisbane from June 2005 until
                      the date of payment.
               Undergrounding Power
               52.    The power supply both external and internal shall be underground. This work shall be at no
                      cost to Council.
               Stormwater Drainage
               53.    All stormwater drainage from the site shall be collected on site and discharged generally in
                      accordance with Plan - Drainage Design 0379 SK 05B dated October 2004 prepared by Greg
                      Gibbs Architects, so there is no net increase in stormwater runoff from the site up to a Q100
                      event. Plans of the drainage design shall be prepared by a Registered Professional Civil
                      Engineer and submitted to Council prior to obtaining a Development Permit for Operational
                      Works.
               54.    Roof runoff from any new dwelling unit or apartment shall be directed to a rainwater storage
                      system or tank (minimum storage 1400 litres per dwelling unit (villa) and 1000 litres per
                      service or non-serviced apartment) that is plumbed to service the toilets in the new dwelling
                      and landscaping areas. The design of the rainwater storage system shall be to the
                      satisfaction of the Manager Plumbing Services.
               55.    Overflows from rainwater tanks may be discharged into the gravel drains proposed.
               56.    An approved maintenance plan for the treatment system shall be incorporated in the
                      Management Scheme for the development and a copy of this shall be provided for Council’s
                      records prior to commencement of the approved Use.
               57.    All site stormwater drainage shall be by means of a gravity system.
               Sewer and Water
               58.    The site shall be connected to Council’s existing sewerage reticulation systems and be
                      constructed in accordance with Council’s standards and requirements at no cost to Council.
               59.    All internal water and sewerage reticulation to be designed and constructed in accordance
                      with Noosa Shire Council Engineering Design Guidelines (PSP6).
               60.    A concept plan detailing proposed internal water and sewer reticulation network is to be
                      submitted for approval prior to preparation of Operational Works Drawings.
               61.    An application for Operational Works, Water Supply and Sewerage detailing proposed
                      internal water supply and sewerage reticulation works is to be lodged with Council in respect
                      of the proposed development.
               62.    After completion of internal water and sewerage reticulation, all works shall be considered
                      as “private sewers and water mains” and responsibility for operation and maintenance shall
                      be the property owners.
               63.    The water connection to the water reticulation system shall extend to the property boundary
                      and be metered.




                                                                                                     Page 8 of 17
Document Set ID: 23615315
Version: 3, Version Date: 05/03/2025

Page 9

               64.    Fire hydrants are to be provided throughout the development in accordance with Council
                      Engineering Design Standards and in accordance with Queensland Fire Service Standards.
               65.    The existing sewer rising mains that is located in the adjoining road reserve at the north of
                      the site and the ‘zone of influence’ (taken as the area within a 45-degree angle measured
                      from the invert of the sewer main to the finished surface level) shall be accurately located
                      and determined by a licensed Surveyor and shown on all plans submitted for Operational
                      Works approval.
               Service Easements
               66.    If not already in place, a registered easement shall be created over any stormwater drainage
                      systems within the site that collect stormwater from a Council road or convey stormwater
                      from any adjoining property.
               67.    The Applicant’s Solicitor shall give Council’s Solicitor an appropriate undertaking in writing
                      that the Title Deed and any easement documents will be lodged at the Land Titles Office and
                      any additional Titles Office forms or requisitions requiring the consent of Council will be
                      attended to promptly.
                       A duly executed copy of the easement shall be submitted to Council for perusal prior to the
                       use commencing.
                       Any changes required by Council’s Solicitor must be corrected immediately.
               Headworks Contributions
               68.    Contributions shall be paid to Council in accordance with Planning Scheme Policies PSP28
                      and PSP30 on Water Supply Headworks Contributions and Sewerage Headworks
                      Contributions respectively and at the rates applicable at the time of payment. An estimate
                      only of the contribution rates under the current policies is outlined below. These amounts
                      will adjusted in line with changes to the Consumer Price Index, All Groups Brisbane from
                      June 2005 until the date of payment.

                        Water Supply     $419,854

                        Sewerage         $258,718

                        TOTAL            $678,572

                       All headworks contributions must be paid prior to the issue of a Development Permit for
                       Operational Works.
                       Alternatively a trading bank guarantee shall be submitted to Council plus 20%. Should the
                       headworks contributions not be paid at the due time, Council shall call upon the trading bank
                       guarantee in full.
                       In the event that the Development Permit for Material Change of Use of Premises lapses or
                       is cancelled, the contribution or trading bank guarantee will be returned.
               Earthworks
               69.    Fill shall be compacted to the requirements of AS3798-1996 ‘Guidelines on Earthworks for
                      Commercial and Residential Developments’. Any existing fill that does not meet the
                      requirements of this standard shall be removed prior to additional filling or building works
                      commencing.
               70.    A Geotechnical Engineer or similar qualified expert shall assess the soil condition on site,
                      determine the soil classification and make recommendations on the type of foundation
                      system(s) best suited for the proposed development. This information shall be submitted to
                      the Council for assessment and approval prior to obtaining a Development Permit for
                      Operational Works.




                                                                                                      Page 9 of 17
Document Set ID: 23615315
Version: 3, Version Date: 05/03/2025

Page 10

               Erosion and Sediment Control
               71.    Any person acting on this permit shall prevent erosion and sediment export from leaving the
                      site. Site control measures such as silt fencing, controlled gravel access to the site and
                      controlled disposal of waste, will be necessary. In this regard plans detailing the methods of
                      controlling erosion and sediment are required to be submitted to the Council for approval
                      prior to obtaining a Development Permit for Operational Works.
               General
               72.    Prior to works commencing contractors shall submit a Traffic Management Plan showing
                      measures to be put in place during construction for approval by Council’s Works Directorate.
               73.    A suitably qualified Registered Professional Engineer shall prepare engineering drawings
                      and specifications for all engineering works that will become Council infrastructure, which
                      shall be submitted in conjunction with an application for a Development Permit for
                      Operational Works. In this regard a DXF/DWG file on GDA94 zone 56 grid of the proposed
                      cadastre layout is to be submitted in conjunction with any application for Operational Works.
               74.    Digital detailed design drawings and calculations shall be submitted with any application for
                      a Development Permit for Operational Works in respect of roadworks and stormwater
                      drainage works. To avoid conflict with underground pipes or services, all existing and
                      proposed services required by the development shall be shown on the plans.
               75.    To facilitate production of As Constructed drawings it is suggested that all design drawings
                      are submitted in the Asset Design and As Constructed (ADAC) digital format. (Guidelines on
                      the use of ADAC are available at www.adac.com.au).
               76.    Any damage caused to any public utility during the course of construction shall be repaired
                      to Council’s standards and at no cost to Council. Particular care shall be exercised when
                      working near the rising main in the road reserve to the north of the site.
               77.    Any alteration of any public utility or other facilities necessitated by the development of the
                      land or associated construction works external to the site shall be at no cost to Council.
               78.    As Constructed drawings and data shall be certified by a qualified experienced Civil Engineer
                      for design intent, and a Licensed Surveyor shall certify the cadastre and the location, level
                      and type of all services and structures. All of which shall be submitted to Council for checking
                      and for Council’s records.
               79.    The data must fully detail levels for all engineering works including but not limited to drainage
                      structures, finished ground levels and pavement surface levels. The data shall be submitted
                      in the Asset Design and As Constructed (ADAC) digital format. (Guidelines on the use of
                      ADAC are available at www.adac.com.au).
               80.    Approval of works shall not be granted until all As Constructed information has been supplied
                      and accepted by Council.
               Environmental Health
               81.    The developer must provide waste storage and disposal facilities in accordance with
                      Planning Scheme Policy “Waste Management Multi-Dwellings and Commercial and
                      Industrial Premises”, including an external imperviously paved area correctly sized for all
                      refuse and recycling containers and suitably screened from public places and neighbouring
                      properties. A roofed wash down area is required with a cold-water tap, hose and drain outlet
                      connected to sewer.
               82.    Refuse containers must be provided in accordance with the requirements of the
                      Environmental Protection (Interim Waste) Regulation 1996 and (Waste Management)
                      Regulation 2000, for the storage and collection of refuse.
               83.    A clinical waste service provided by a licensed clinical waste contractor must be provided for
                      the activities.




                                                                                                       Page 10 of 17
Document Set ID: 23615315
Version: 3, Version Date: 05/03/2025

Page 11

               84.    The development must allow refuse-loading areas to be located off street. All vehicles
                      associated with the collection of waste/recyclables, shall enter and leave the site in a forward
                      direction.
               85.    A Waste Management Plan (Operational) in accordance with Planning Scheme Policy
                      “Waste Management Multi-Dwellings and Commercial and Industrial Premises”, must be
                      submitted for the day-to-day operation of the complex and approved by Council’s
                      Environmental Health Section prior to issue of development permit for operational works.
                      The Plan shall include the following information: -
                      85.1 The types of waste that will be generated from the activities approved within the
                           development.
                      85.2 Estimated volumes or tonnage of recyclables within the generated waste stream
                      85.3 Estimated volumes or tonnage of waste generated from the activities.
                      85.4 Methods to be used for dealing with garden waste.
                      85.5 Initiatives to minimize waste either by waste prevention, reduction, re-use or recycling.
                      85.6 Description of procedures involving disposing of refuse to bins; the storage of bins and
                           the collection of bins by the contractor and who is responsible for each transfer of the
                           waste.
                      85.7 A description of the design details of waste storage and recycling areas including size,
                           location, elevation and floor plan, methods of bin washing and of prevention of storm
                           water contamination.
                      85.8 A description of types and volume of waste storage containers to be used.
                      85.9 The waste and recycling storage area shall include the provision of containers for all
                           waste and recycling materials including putresable matter, non-recycling waste, paper
                           and cardboard, glass, aluminium and steel cans, waste oil, styrofoam boxes, etc, and
                           bin washing facilities.
                      85.10 A detailed description of vehicular access to collect waste. Where collection is off
                           street, access must allow vehicles to enter and leave the site in a forward direction.
               86.    A Waste Management Plan (Demolition/Construction) in accordance with Planning Scheme
                      Policy “Waste Management Multi-Dwellings and Commercial and Industrial Premises”, shall
                      be submitted for the demolition and construction phases of the development and approved
                      by Council’s Environmental Health Section prior to the issue of the development permit for
                      operational works. The Plan shall contain the following information:


                          MATERIALS ON-SITE               DESTINATION

                                                          Re-use and Recycling            Disposal

                          Expected waste Estimated On-site                   Off-site         *specify
                          materials      volume    *specify                  *specify         contractor and
                                         (m³)      proposed re-use           contractor and landfill site
                                                   or        on-site         recycling outlet
                                                   recycling
                                                   methods

                          Excavation
                          material

                          Green waste

                          Bricks



                                                                                                      Page 11 of 17
Document Set ID: 23615315
Version: 3, Version Date: 05/03/2025

Page 12

                          Concrete

                          Timber-please
                          specify

                          Plasterboard

                          Metals - please
                          specify

                          Asbestos

                          Other - please
                          specify

                      Note: Details of site area to be used for onsite separation, treatment and storage (including
                      weather protection) shall be provided on the plan drawings accompanying your application.
               87.    Noise emission from swimming pool and spa equipment (including heating equipment) shall
                      comply with the following requirements:
                      87.1. The equipment shall be installed and located in a manner that prevents excessive noise
                            in accordance with Council’s Local Law No. 12 - Control of Nuisances. Infringement
                            Notices (on-the-spot fines) may apply for offences.
                      87.2. A person must not use equipment on any day if it makes or causes noise to be made
                            –
                              87.2.1. From 10pm to 7am: Which is audible outside the most exposed part of an
                                      affected building
                              87.2.2. From 7am to 7pm: More than the lower of either –
                                       •    50 dB(A)
                                       •    5 dB(A) above the background noise level
                              From 7pm to 10pm: More than 3 dB(A) above the background noise level.
               88.    Noise emission from air conditioning equipment shall comply with the following requirements:
                      88.1. The equipment shall be installed and located in a manner that prevents excessive noise
                            in accordance with Council’s Local Law No. 12 - Control of Nuisances. Infringement
                            Notices (on-the-spot fines) may apply for offences.
                      88.2. Submission of written certification from a suitably qualified person confirming that the
                            noise levels comply when measured at either the residential boundary or outside the
                            most exposed part of an affected building, whichever is the closest to the equipment.
                            This is required immediately after installation of the equipment and prior to any
                            occupation of the building, and in a format approved by Council.
                      88.3. A person must not use equipment on any day if it makes or causes noise to be made
                            –
                              88.3.1. From 10pm to 7am: More than the lower of either –
                                       •    40 dB(A)
                                       •    3 dB(A) above the background noise level
                              88.3.2. From 7am to 7pm: More than the lower of either –
                                       •    50 dB(A)
                                       •    5 dB(A) above the background noise level
                              88.3.3. From 7pm to 10pm: More than 3 dB(A) above the background noise level.


                                                                                                     Page 12 of 17
Document Set ID: 23615315
Version: 3, Version Date: 05/03/2025

Page 13

               89.    Noise from building works associated with residential development shall comply with the
                      following –
                      89.1. Limited to between 7:00am to 6:30pm Monday to Saturday.
                      89.2. All reasonable measures are taken to minimise noise emissions.
                      89.3. Not permitted on Sunday or public holidays.
               90.    A lighting assessment prepared by a professional Lighting Consultant that addresses the
                      proposed levels of illuminance to the external environment to prevent glare and other light
                      nuisance to both on site occupants and sites beyond the boundaries, is to be submitted prior
                      to the issue of the development permit for operational works. The report is to include lighting
                      for roads, access paths, security, bowling green, swimming pool, and Community Centre and
                      show compliance with Australian Standards AS-1158 - Lighting for Roads and AS 4282 -
                      Control of Obtrusive Effects of Outdoor Lighting.
               91.    All refrigeration plant including motors, should be situated within the building or suitably
                      provided with noise reduction measures and located as to prevent a noise nuisance in
                      accordance with the nuisance provisions of the Environmental Protection Regulation 1998.
                      On the spot fines apply for such offences
               92.    Liquid waste generated by industry, small business and commercial enterprises is referred
                      to as Trade Waste and shall comply with the following:
                      92.1. A Trade Waste Permit shall be obtained prior to the discharge of trade waste to
                            Council’s sewerage system.
                      92.2. All trade waste requirements complying with Council’s Trade Waste Policy and
                            including pre-treatment devices, must be shown on hydraulic plans submitted to
                            Council for approval prior to issuing the development permit for building work.
                      92.3. Vehicular access shall be provided to each grease arrestor and/or pre-treatment device
                            for cleaning and servicing by Council’s contractor, and must allow vehicles to enter and
                            leave the site in a forward direction. Where access is restricted, a pump out line to an
                            approved location is required.
                      92.4. Trade waste requirements must be in place, inspected and approved prior to
                            commencement of trading or operation.
                              Bin wash down areas exceeding 600mm square shall be roofed with the floor falling to
                              a bucket trap waste gully, before entering Councils sewerage system. Council’s Trade
                              Waste Officer to meet with developer to discuss future uses of the premises.
                      Additional Conditions – 27 February 2025 – 132004.5744.13
               93.    The approved “Maintenance Shed” as shown on the Approved Plans, external colours and
                      finishes must be of muted/environmental tones that blend with the natural environment and
                      low-reflective roofing and cladding materials.
               5.     REFERRAL AGENCIES

               Not Applicable
               6.     ADVISORY NOTES

               The following Advisory Notes are for information purposes only and do not form conditions of
               approval:
               1.     Approval of this development application will trigger an Infrastructure Charge in accordance
                      with the Coastal Major Road Network Infrastructure Charges Plan for the estimated amount
                      of $115,109. This amount will subject to variations in the Consumer Price Index, All Groups
                      Brisbane from June 2005 until the date of payment. An Infrastructure Charge Notice will be
                      issued in accordance with Chapter 5 of the Integrated Planning Act 1997.




                                                                                                      Page 13 of 17
Document Set ID: 23615315
Version: 3, Version Date: 05/03/2025

Page 14

               2.     Payment via credit card transaction will not be an acceptable method of payment for
                      development contributions conditioned in this permit or for infrastructure charge notices
                      issued separately.
               3.     We advise ‘interested parties’ i.e. ‘developer’, ‘owner’, ‘tenant’ to consider their
                      responsibilities under the Disability Discrimination Act (DDA) in regard to the installation of
                      disabled access and the provision of disabled facilities, and that access to this building and
                      the provision of sanitary facilities may need to comply with the requirements of Section D
                      Part D3 and Section F Clause F2.4 of the Building Code of Australia.
               4.     Referral to Queensland Fire & Rescue Authority would be required at the Building Application
                      stage.
               5.     Where any food premises is to be included in the development, the following is required:
                      5.1 Plans and an application should be made to Council’s Environmental Health
                          Section for approval prior to any building approval, fitting out or use of the
                          premises.
                      5.2 Construction and use of the food premises should comply with Council’s Food
                          Premises Policy and the Food Safety Standards.
                      5.3 Toilets for customers and staff should be provided in accordance with the
                          Building Code of Australia. Obtain advice from a building certifier.
                      5.4 Plans and approval is required for any mechanical exhaust ventilation system
                          which should comply with AS1668. A certificate is required from the installer
                          certifying the system complies with the Standard.
                      5.5 Licence and registration is required for any food premises listed in Schedule 1,
                          Food Hygiene Regulation 1989, prior to use of those premises.
                      5.6 A detailed statement indicating the purpose of the food premises, type of food
                          sold, proposed menu and number of persons served, is to accompany the plans
                          approval application.
               6.     The operator of any beauty treatment and/or hairdressing business should comply with the
                      Infection Control Guidelines of the Public Health (Infection Control for Personal Appearances
                      Services) Act 2003.
               7.     The development should be undertaken and operated in a manner that causes no detrimental
                      effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
                      lighting, air-borne hazards, atmospheric pollutants (including dust or odours) nuisance or any
                      other emissions in accordance with the nuisance provisions of the Environmental Protection
                      Regulation 1998 or Council’s Local Law No. 12 – Control of Nuisances.
               8.     In accordance with the Environmental Protection (Water) Policy 1997, all sand, silt, mud,
                      paint, cement, concrete, builder’s waste or rubbish should not be permitted to enter or be
                      placed where it could reasonably be expected to move into a roadside gutter, storm water
                      drain or a watercourse. On the spot fines apply for such offences.
               9.     The Environmental Protection Regulation 1998 and Local Law No.12 prohibit a builder from
                      making noise from:-
                              Monday to Saturday, before 7:00am or after 6:30pm
                              Sunday or public holiday, at any time.
                              A maximum penalty of $1,500 applies to an offence under these provisions.
               10.    Pursuant to the Building and Construction Industry (Portable Long Service Leave) 1991 Act
                      if the cost of operational works exceeds $80,000, then a portable long service levy is required
                      to be paid. In accordance with Section 77.(1) of the Act, Council is required to sight the
                      approved form issued by the Building and Construction Industry (Portable Long Service
                      Leave) Authority that confirms that the requirements of the Act have been satisfied. A
                      statutory declaration outlining the cost of the operational works must be submitted to Council
                      with the lodgement of any application for operational works over the site.


                                                                                                      Page 14 of 17
Document Set ID: 23615315
Version: 3, Version Date: 05/03/2025

Page 15

               Infrastructure Charges
               11.     This Change to an Existing Approval will trigger an “Infrastructure Charge Notice” to be
                       issued in accordance with Council’s “Charges Resolution” made pursuant to the planning
                       legislation and regulations current at the time of issue.
               Aboriginal Cultural Heritage Act 2003
               12.     There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
                       approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
                       The ACH Act establishes a cultural heritage duty of care which provides that: “A person who
                       carries out an activity must take all reasonable and practicable measures to ensure the
                       activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply with the
                       duty of care. Substantial monetary penalties may apply to individuals or corporations
                       breaching this duty of care. Injunctions may also be issued by the Land and Resources
                       Tribunal, and the Minister administering the ACH Act can also issue stop orders for an activity
                       that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value
                       of Aboriginal cultural heritage.
                     You should contact the Cultural Heritage Unit on 07 3247 6212 to discuss any obligations under
                     the ACH Act.
               7.      PROPERTY NOTES

               Not Applicable
               8.      VARIATION APPROVAL DETAILS

               Not Applicable
               9.      FURTHER DEVELOPMENT PERMITS REQUIRED

                    Type of Development Permit                  Subject of the required Development Permit
                    required

                    Development Permit for Building works       All Building Works

                    Development Permit for Operational          Landscaping, car parking, access, site civil works,
                    Works                                       stormwater drainage, frontage works, sewer
                                                                reticulation (including new mains, relocations,
                                                                diversions, pump stations and rising mains), water
                                                                reticulation, site earthworks.

               10.     SUBMISSIONS

               Not Applicable
               11.     RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.
               During the appeal period, you as the applicant may suspend your appeal period and make written
               representations to Council about the conditions contained within the development approval. If
               Council agrees or agrees in part with the representations, a negotiated decision notice will be
               issued. Only one negotiated decision notice may be given.




                                                                                                        Page 15 of 17
Document Set ID: 23615315
Version: 3, Version Date: 05/03/2025

Page 16

               12.      OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available on line at
               www.noosa.qld.gov.au or at Council Offices.
               Yours faithfully,




               Cameron Smith
               Development Planner
               Enc:     Referral Agency Response
                        Appeal Rights
                        Approved Plans/Documents




               DECISION NOTICE HISTORY
               •     Original Decision Notice – 22 September 2005.
               •     Negotiated Decision Notice – 15 December 2005 Change to
                     conditions 2, 5, 12, 16, 20, 29, 47, 53 & 54; delete condition 4:
                     refuse to change conditions 15, 58, 59.

               •     Decision Notice - Minor 132004.5744.004 – 28 January 2016 –
                     Amend condition 1.

               •     Decision Notice – Minor – 132004.5744.09 – 30 August 2017 –
                     Amend conditions 1, 8 & 38.

               •     Decision Notice – 132004.5744.11 – 23 February 2021; amend
                     condition 1 & 38.

               •     Decision Notice – 132004.5744.12 – 28 June 2024, amend
                     condition 1,

               •     Decision Notice – 132004.577.13 – 27 February 2025; amend
                     conditions 1, 2 & 11, additional condition. 93.




                                                                                                     Page 16 of 17
Document Set ID: 23615315
Version: 3, Version Date: 05/03/2025

Page 17

                                                                              Appeal Rights
                                                                              PLANNING ACT 2016 & PLANNING REGULATION 2017




               Chapter 6 Dispute resolution                                                   (3) The appellant or, for an appeal to a tribunal, the registrar must,
                                                                                                  within the service period, give a copy of the notice of appeal to –
               Part 1 Appeal rights
                                                                                                  (a) the respondent for the appeal; and
               229 Appeals to tribunal or P&E Court
                                                                                                  (b) each co-respondent for the appeal; and
               (1) Schedule 1 of the Planning Act 2016 states –
                                                                                                  (c) for an appeal about a development application under schedule
                   (a) Matters that may be appealed to –
                                                                                                      1, table 1, item 1 – each principal submitter for the
                         (i)   either a tribunal or the P&E Court; or                                 development application; and
                         (ii) only a tribunal; or                                                 (d) for and appeal about a change application under schedule 1,
                                                                                                      table 1, item 2 – each principal submitter for the change
                         (iii) only the P&E Court; and
                                                                                                      application; and
                   (b) The person-
                                                                                                  (e) each person who may elect to become a co-respondent for the
                         (i)   who may appeal a matter (the appellant); and                           appeal, other than an eligible submitter who is not a principal
                                                                                                      submitter in an appeal under paragraph (c) or (d); and
                         (ii) who is a respondent in an appeal of the matter; and
                                                                                                  (f)   for an appeal to the P&E Court – the chief executive; and
                         (iii) who is a co-respondent in an appeal of the matter; and
                                                                                                  (g) for an appeal to a tribunal under another Act – any other
                         (iv) who may elect to be a co-respondent in an appeal of the
                                                                                                      person who the registrar considers appropriate.
                              matter.
                                                                                              (4) The service period is –
               (2) An appellant may start an appeal within the appeal period.
                                                                                                  (a) if a submitter or advice agency started the appeal in the P&E
               (3) The appeal period is –
                                                                                                      Court – 2 business days after the appeal has started; or
                   (a) for an appeal by a building advisory agency – 10 business
                                                                                                  (b) otherwise – 10 business days after the appeal is started.
                       days after a decision notice for the decision is given to the
                       agency; or                                                             (5) A notice of appeal given to a person who may elect to be a co-
                                                                                                  respondent must state the effect of subsection (6).
                   (b) for an appeal against a deemed refusal – at any time after the
                       deemed refusal happens; or                                             (6) A person elects to be a co-respondent by filing a notice of election,
                                                                                                  in the approved form, within 10 business days after the notice of
                   (c) for an appeal against a decision of the Minister, under chapter
                                                                                                  appeal is given to the person.
                       7, part 4, to register premises or to renew the registration of
                       premises – 20 business days after a notice us published under          231 Other appeals
                       section 269(3)(a) or (4); or
                                                                                              (1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
                   (d) for an appeal against an infrastructure charges notice – 20                the Supreme Court decides a decision or other matter under this
                       business days after the infrastructure charges notice is given             Act is affected by jurisdictional error, the decision or matter is non-
                       to the person; or                                                          appealable.
                   (e) for an appeal about a deemed approval of a development                 (2) The Judicial Review Act 1991, part 5 applies to the decision or
                       application for which a decision notice has not been given –               matter to the extent it is affected by jurisdictional error.
                       30 business days after the applicant gives the deemed
                                                                                              (3) A person who, but for subsection (1) could have made an
                       approval notice to the assessment manager; or
                                                                                                  application under the Judicial Review Act 1991 in relation to the
                   (f)   for any other appeal – 20 business days after a notice of the            decision or matter, may apply under part 4 of that Act for a
                         decision for the matter, including an enforcement notice, is             statement of reasons in relation to the decision or matter.
                         given to the person.
                                                                                              (4) In this section –
               Note –                                                                             decision includes-
                   See the P&E Court Act for the court’s power to extend the appeal
                                                                                                  (a) conduct engaged in for the purpose of making a decision; and
                   period.
                                                                                                  (b) other conduct that relates to the making of a decision; and
               (4) Each respondent and co-respondent for an appeal may be heard
                   in the appeal.                                                                 (c) the making of a decision or failure to make a decision; and
               (5) If an appeal is only about a referral agency’s response, the                   (d) a purported decision; and
                   assessment manager may apply to the tribunal or P&E Court to
                                                                                                  (e) a deemed refusal.
                   withdraw from the appeal.
                                                                                                  non-appealable, for a decision or matter, means the decision or
               (6) To remove any doubt. It is declared that an appeal against an
                                                                                                  matter-
                   infrastructure charges notice must not be about-
                                                                                                  (a) is final and conclusive; and
                   (a) the adopted charge itself; or
                                                                                                  (b) may not be challenged, appealed against, reviewed, quashed,
                   (b) for a decision about an offset or refund-
                                                                                                      set aside or called into question in any other way under the
                         (i)   the establishment cost of trunk infrastructure identified in           Judicial Review Act 1991 or otherwise, whether by the
                               a LGIP; or                                                             Supreme Court, another court, a tribunal or another entity; and
                         (ii) the cost of infrastructure decided using the method                 (c) is not subject to any declaratory, injunctive or other order of
                              included in the local government’s charges resolution.                  the Supreme Court, another court, a tribunal or another entity
                                                                                                      on any ground.
               230 Notice of appeal
                                                                                              232 Rules of the P&E Court
               (1) An appellant starts an appeal by lodging, with the registrar of the
                   tribunal or P&E Court, a notice of appeal that-                            (1) A person who is appealing to the P&E Court must comply with the
                                                                                                  rules of the court that apply to the appeal.
                   (a) is in the approved form; and
                   (b) succinctly states the grounds of the appeal.                           (2) However, the P&E Court may hear and decide an appeal even if
                                                                                                  the person has not complied with the rules of the P&E Court
               (2) The notice of appeal must be accompanied by the required fee.




                                                                                                                                                 Page 17 of 17
Document Set ID: 23615315
Version: 3, Version Date: 05/03/2025

Used in these records

About this file

File size
212 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Minor Change Existing Approval 132004 5744 13 [As Published].pdf · 212 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.