Operational Waste Management Plan
Proposed Transport Depot
At 5 – 13 Production Street, Noosaville

On Behalf of Evolution MIT Services P/L TTE
Log in to download the original file

24BRW0157 OWMP Final.pdf · 7.1 MB (large file)

The download may take up to a minute.

Full text of the other 43 pages

Page 2

         About TTM
         For 30 years, we’ve been at the centre of the Australian
         development and infrastructure industry. Our unique
         combination of acoustics, data, transport and waste
         services is fundamental to the success of any
         architectural or development project.
         We have over 50 staff, with an unrivalled depth of
         experience. Our industry knowledge, technical
         expertise and commercial insight allow us to deliver an
         exceptional and reliable service.
         T: (07) 3327 9500
         F: (07) 3327 9501
         E: [email protected]




       Revision Record

          Issue     Author                  Reviewed/Approved                     Development Stage /      Date
           No.                                                                    Revision Description

                                                                                  Developed Design
           1.       N. Lee                  S. Kenny                                                     09/07/2024
                                                                                  OWMP – Draft
                                                                                  Developed Design
           2.       N. Lee                  S. Kenny                                                     10/07/2024
                                                                                  OWMP – Submissible




© 2020 - TTM Consulting Pty Ltd ABN 65 010 868 621
Level 8, 369 Ann Street, Brisbane. PO Box 12015 George Street Brisbane QLD 4003

Page 3

Contents
1     Introduction ..........................................................................................................................................4
      1.1.         Background .................................................................................................................................. 4
      1.2.         Client Brief and Scope .................................................................................................................. 4
      1.3.         Site Analysis .................................................................................................................................. 5
      1.4.         Development Summary ................................................................................................................ 6
2.    Regulatory Refuse Management Requirements......................................................................................7
      2.1.         Regulatory and Governance Considerations ................................................................................ 7
      2.2.         Anticipated Refuse Volumes ........................................................................................................ 8
      2.3.         Refuse Bin, Equipment Requirements and Specification ............................................................. 9
      2.4.         Refuse Disposal ..........................................................................................................................10
      2.5.         Refuse Storage Arrangements ....................................................................................................13
      2.6.         Refuse Transfer ..........................................................................................................................15
      2.7.         RCV and Bin Servicing Arrangements .........................................................................................16
3.    Recommended Operational Refuse Management ................................................................................ 17
      3.1.         On-going Management ..............................................................................................................17
Appendix A         OWMP Compliance Checklist ................................................................................................. 22
Appendix B         Site Plans and Swept Path Analysis......................................................................................... 26
Appendix C         Systems and Specifications .................................................................................................... 35
      C.1          Specified Refuse Management Equipment ................................................................................36
Appendix D           Refuse Signage ..................................................................................................................... 38
      D.1          Refuse Signage ...........................................................................................................................39
      D.2          Other Refuse, Facility and Safety Signage ..................................................................................40
Appendix E         Terms and Abbreviations ....................................................................................................... 41




Site: 5 – 13 Production Street, Noosaville                                                                                                                     2
Reference: 24BRW0157

Page 4

Table Index
Table 1.1: Scope Items ....................................................................................................................................... 4
Table 1.2: Development Summary ..................................................................................................................... 6
Table 2.1: Conditions of Approval ...................................................................................................................... 7
Table 2.2: Refuse Generation Rates ................................................................................................................... 8
Table 2.3: Refuse Calculations ........................................................................................................................... 8
Table 2.4: Bin Requirements .............................................................................................................................. 9
Table 2.5: Additional Equipment........................................................................................................................ 9
Table 2.6: Disposal of Frequently Generated Refuse ....................................................................................... 10
Table 2.7: Disposal of Specialist Waste Streams .............................................................................................. 11
Table 2.8: Disposal of Infrequently Generated Waste ..................................................................................... 12
Table 2.9: Refuse Storage Area Design Requirements ..................................................................................... 14
Table 3.1: Implementation Checklist................................................................................................................ 17
Table 3.2: Occupation / Operation Checklist ................................................................................................... 19
Table 3.3: Review and Amendment Checklist .................................................................................................. 20

Figure Index
Figure 1.1: Site Location..................................................................................................................................... 5
Figure 2.1: Potential Refuse Storage Area Layout ............................................................................................ 13




Site: 5 – 13 Production Street, Noosaville                                                                                                                3
Reference: 24BRW0157

Page 5

1            Introduction
1.1.         Background
TTM Consulting has been engaged by Integral Construction Pty Ltd on behalf of Evolution MIT Services P/L
TTE to prepare an Operational Waste Management Plan (OWMP) to support the proposed transport depot
located at 5 – 13 Production Street, Noosaville. It is understood that development application reference
MCU23/0155 has been conditionally approved by Noosa Council.
This OWMP has been prepared to satisfy the requirement of Development Permit for Material Change of
Use – Transport Depot Condition numbers 17 and 18. It is understood that this OWMP will be submitted to
council for approval.

1.2.         Client Brief and Scope
The proposed development intends to adequately cater for the anticipated refuse generation volumes while
adhering to regulatory requirements. This includes adequate segregation and storage of regulated waste
streams such as used hydraulic oils and other items not suitable for landfill such as tyres.
The content of this OWMP is intended to provide information on the typical movement of waste streams
from generation to collection. Information on each refuse stream expected to be generated is provided.
The items covered within the OWMP are described in Table 1.1.
Table 1.1: Scope Items
 Item                                        Description
 Refuse streams                              Identification of refuse streams & anticipated development refuse volumes likely to be produced
 Refuse separation                           Recommendations for appropriate segregation methods for each refuse stream
 Refuse collections                          Assessment of refuse collection vehicle (RCV) access and manoeuvring
 Refuse storage                              Detailed analysis of refuse storage facilities and design
 Refuse transfer                             Assessment of refuse transfer between refuse storage and collections areas
 Refuse disposal                             Recommendations for refuse disposal within the development
 Refuse management equipment                 Identification of recommended and optional refuse management systems and equipment
                                             Recommendations for operational efficiency and ongoing management, including refuse
 Refuse management operations
                                             minimisation, tenant education and safety
 Building design                             Recommendations for design of refuse management facilities

Detailed information including site plans and drawings, recommended refuse management equipment and
system specifications, common refuse signage as well as a list of terms and abbreviations are provided in the
appendices.
The recommendations in this report relate to the operational phase of the development only. Additional
requirements for refuse management during or after demolition or construction phases are not included and
require a dedicated plan.




Site: 5 – 13 Production Street, Noosaville                                                                                             4
Reference: 24BRW0157

Page 6

1.3.         Site Analysis
The site is located at 5 – 13 Production Street, Noosaville and is formally described as Lot 256 on Plan
MCH4539 and Lots 257 and 274 on Plan MCH4891 as depicted in Figure 1.1.
The site has a single road frontage with all vehicular ingress and egress occurring via Production Street.
The existing structures on the subject site will be demolished or removed from site.




                                                                Site Location




Figure 1.1: Site Location
Source: Nearmap, Dated: 10/04/2024




Site: 5 – 13 Production Street, Noosaville                                                                   5
Reference: 24BRW0157

Page 7

    1.4.         Development Summary
    The proposed transport depot consists of a single building, divided into workshop and ancillary office with
    external at grade staff car and bike parking. Additionally, fleet parking and charging areas to support a fleet of
    32 fully electric buses.
    Table 1.2 below provides a summary of the floor areas within the development.
    Table 1.2: Development Summary
     Description                                                                         Measure
     Office                                                                              183.1m2 GFA
     Workshop                                                                            274.2m2 GFA
•    Total                                                                            − 457.3m2 GFA




    Site: 5 – 13 Production Street, Noosaville                                                                    6
    Reference: 24BRW0157

Page 8

2.           Regulatory Refuse Management
             Requirements
This section provides the detailed refuse calculations and describes the arrangements for the collection,
storage, transfer and disposal of refuse within the development as deemed to satisfy council’s current
assessment benchmarks. This includes associated bin quantities, storage capacities, equipment details,
collection frequencies and site access details.

2.1.            Regulatory and Governance Considerations

2.1.1.       Council’s Refuse Planning Scheme
This plan has been prepared to align with Noosa Council’s assessable outcomes of 9.4.10 Waste
Management Code and SC6.10 – PSP9 Waste Management of the Noosa Plan 2020 as mandated by council’s
conditions of approval.
Specific design details addressed to achieve compliance with Noosa Council PSP9 Waste Management
requirements is located in Appendix A.
Table 2.1 details the conditions of approval relating to waste.
Table 2.1: Conditions of Approval
 Condition
 Waste Management
 17.         A waste storage area must be designed and maintained in accordance with Planning Scheme Policy PSP9 Waste
             Management and the Noosa Plan’s Waste Management Code.
             The waste storage area must be:
                       a. imperviously paved and correctly sized for all refuse and recycling containers;
                       b. bunded and graded so that wastewater and bin leakage drain to the sewer;
                       c. provided with a conveniently located hosecock and backflow prevention device, connected to a water
                       supply to service the area; and
                       d. roofed or otherwise covered.
 18.         A Waste Management Plan must be prepared that details the type and quantity of waste material that is likely to be
             generated by the development; where and how the waste will be stored, disposed of and procedures for handling the
             waste. The Waste Management Plan must be submitted and approved by Council prior to the issue of a Development
             Permit for Operational Works.




Site: 5 – 13 Production Street, Noosaville                                                                                     7
Reference: 24BRW0157

Page 9

2.2. Anticipated Refuse Volumes
Given the intended use of the site as a transport depot for electric vehicles, historical refuse generation data
based on transport depots for internal combustion engines is not considered to provide accurate estimation
for refuse produced by this site. As such, the generation rates used for the calculation of refuse produced
have been applied based on a review of information provided for a comparable existing site operated by the
proposed site operators.
While internal areas may differ between the operator’s sites, the ratio of staff members required per bus
within the fleet remains consistent. As a result, the generation rate utilised is based on the total volume of
generation from a comparable site, divided by the number of buses in the fleet to provide a generation rate
‘per bus’. TTM note the generation rate applied relates to general waste and commingled recycling only and
excludes specialist waste streams such as fluids and tyres. Further details of the specialist waste streams is
provided in Sections 2.3 – 2.5.
A collection frequency of once per week is proposed for general waste and commingled recycling is based on
a storage capacity of 7 days between services. The proposed collection frequency aligns with Council’s
Minimum Service Levels.


Table 2.2: Refuse Generation Rates
 Generation Rate                             Measure               General Waste     Recycling     Days of Operation
 Operator Specific                       L / Bus / Day                  5                5                  7



Table 2.3: Refuse Calculations
                                                                                   General Waste   Commingle Recycling
               Area Description                        Measure          Quantity
                                                                                      L/Week           L/Week
 Operator Specific                                       Per Bus            32         1,120             1,120
 Volumes per Day (L / Day)                                                             160                160
 Volumes per Collection (L / Collection)                                               1,120             1,120
                                                   Collections per Week                 1                  1
                                                   Storage Capacity                   7 Days             7 Days
 Collection and Equipment Details
                                                   Equipment Size                     1100L              1100L
                                                   Equipment Quantity Required          1                  1




Site: 5 – 13 Production Street, Noosaville                                                                          8
Reference: 24BRW0157

Page 10

2.3.         Refuse Bin, Equipment Requirements and Specification
Table 2.4 and Table 2.5 outline the number of bins and additional equipment required for the development
based on the expect refuse generation volumes.
As refuse volumes may vary from over time, bin numbers and sizes may need to be altered to suit the
building operation.
Table 2.4: Bin Requirements
 Refuse Stream                                    Bin / Storage – Size or Type                        Number Required
 General Waste                                               1100L                                             1
 Commingled Recycling                                        1100L                                             1


Table 2.5: Additional Equipment
 Description                                 Quantity       Capability / Specification – See Appendix C for Detail

                                                            Receptacles for the immediate disposal of refuse into separate streams.
 Individual Stream Receptacles                  TBD
                                                            Typically, bins up to 60L in volume. Further details in Section 2.4.1.
                                                            2 x 200L drums to be stored on bunded pallet for the storage of waste
 Waste Liquids Receptacles                        2
                                                            brake and hydraulic fluids.
                                                 TBD        May be used to assist in the manual transfer of refuse to the bulk bins in
 Refuse / Cleaners Trolleys
                                              (Optional)    the refuse room for final disposal.
                                             1 per office
                                                space       Typically, 1 bin is provided per office space and stored in an operationally
 Secure Destruct Paper
                                                            convenient location such as near a printer.
                                              (optional)




Site: 5 – 13 Production Street, Noosaville                                                                                           9
Reference: 24BRW0157

Page 11

2.4.         Refuse Disposal
The tables in this section summarise general recommended disposal arrangements for frequently generated
and infrequently generated refuse for each development component. Section 2.4.1 describes the frequently
generated and site-specific refuse streams that require capacity for storage prior to collections or specialist
handling and storage. Section 2.4.2 describes the infrequently generated refuse streams that are generated
in relatively low volumes, and where minimal provision for storage can be easily managed by collection
frequency and ad hoc storage arrangements.

2.4.1. Frequently Generated Refuse
Table 2.6: Disposal of Frequently Generated Refuse
 Refuse Stream          Disposal Details
 WASTE

 General Waste          Depending on the type of activities of the individual areas of the development, different wastes will be
                        produced. Waste bins should always be lined with bags and the bags tied before removal. The site operator
                        will be required to provide receptacles in a sufficient quantity to temporarily store one days’ worth of refuse in
                        each relevant refuse generating area of the development. After each day of operation or as required, refuse
                        will be transferred by staff / cleaners to the refuse enclosure and decanted into the appropriate bulk bin.
                        The number of and location of bins provided will be determined during tenancy fit out and careful
                        consideration should be given to the placement and types of bins to optimise source separation. A
                        commingled recycling bin should be positioned wherever a general waste bin is positioned.
                        Bins should be placed in office and workshop areas as well as on small bins for wastes generated on buses.
 Organic (Food)         Limited volumes of food waste may be generated within break areas / lunchroom from staff breaks or catered
 Waste                  teambuilding events. While the Noosa area has limited commercial options available for food waste collection,
                        separating organic or food waste from general waste is recommended to reduce the total amount of general
                        waste produced. Separation may be considered and begin at any stage during the operational phase of the
                        development.
                        Onsite composting may be considered where appropriate staff resources are available to manage the
                        composting process.
                        Where food waste is separated, caddy bins or bins no larger than 20L should be used in high volume situations
                        such as communal kitchens, for disposal of food waste. The bins are then transferred to the refuse room for
                        collection. The content is then manually decanted into bins or composting equipment provided within the
                        refuse enclosure.
 RECYCLING

 Commingled,            The site operator will be required to provide receptacles for each separate refuse stream in a sufficient
 including              quantity to temporarily store one days’ worth of refuse in each relevant refuse generating area of the
  • glass               development. After each day of operation or as required, refuse will be transferred by staff / cleaners to the
                        refuse enclosure and decanted into the appropriate bulk bin. Items for recycling must not be bagged and
  • aluminum
                        disposed in loose form. This can be done by decanting the materials from the individual receptacles into the
  • steel cans          bulk bin.
  •    tins             The number of and location of bins provided will be determined during tenancy fit out and careful
  •    cardboard        consideration should be given to the placement and types of bins to optimise source separation. A
  •    semi rigid       commingled recycling bin should be positioned wherever a general waste bin is positioned.
       plastics         Bins should be placed in office and workshop areas as well as on small bins for buses.
                        Container deposit / refund schemes are currently in place in Queensland. Various models exist including bottle
                        return facilities and (automated) reverse vending machines.
                        Occupants should be encouraged to separate containers that qualify for the schemes from the waste or
                        recycling streams and send back to a return point. Storage space or dedicated bins within the office or break
                        rooms can be provided.




Site: 5 – 13 Production Street, Noosaville                                                                                             10
Reference: 24BRW0157

Page 12

Table 2.7: Disposal of Specialist Waste Streams
 Refuse Stream          Disposal Details
 REGULATED WASTE STREAMS
 Tyres                  Tyres are a problematic waste stream, defined as a Category 2 Regulated waste stream under the
                        Environmental Protection Regulation 2019. Tyres must be disposed of correctly, and only to a place
                        appropriately licensed to receive them.
                        It is expected tyre waste will be generated on an ongoing ad hoc basis. Tyres will be removed by the tyre
                        maintenance contractor with limited storage of tyres located on-site. The tyre maintenance contractor must
                        provide evidence of lawful transport and disposal to the site operator as requested and this clause should
                        form part of any maintenance contracts.
                        While tyres do not have specific storage requirements on site, any interim on-site storage arrangements must
                        comply with the Fire and Rescue Service Act 1990 and Public Health Act 2005 to address any potential fire or
                        mosquito breeding risk.
 Other Regulated        Regulated waste must not be placed in a bin or skip for disposal to landfill. Regulated waste must be handled
 Waste                  with due care, separated and securely stored for collection by a specialist waste contractor. Please refer to
  •    waste oils       local and QLD government websites for further information.
  •    solvents         When organising for the disposal of hazardous or regulated waste, site operators are responsible for
                        classifying it and ensuring that:
  •    coolant
                         • The transporter is appropriately licensed.
  •    caustic
       brake fluid       • The waste is being sent to a facility that can lawfully take it.
  •    batteries         • All collection receipts are kept.
                        Waste Oil
                        All containers must be drained of all residue oil before they can be recycled. Wherever possible, waste oils
                        should be recycled. Waste oils should be collected in a secure, clearly labelled drums or tanks that are stored
                        in an undercover and bunded area.
                        Solvents
                        Solvents are hazardous to the environment and are often flammable and volatile materials. Waste solvent is
                        primarily generated from cleaning equipment and parts. Solvents should be stored in tightly sealed containers
                        in an enclosed area of cabinet. Solvents must not enter the stormwater or sewerage system and should be
                        collected by a designated contractor.
                        Coolants
                        Improper disposal of used coolant or refrigerant, such as air conditioning refrigerant, can result in
                        contamination of soils, groundwater or stormwater and is hazardous to the environment and should not be
                        dumped illegally any water bodies. Coolants should be stored in drums and containers on a sealed, bunded
                        and undercover area.
                        Coolants should not be mixed with any other liquid wastes and should be collected and treated separately.
                        Batteries
                        Electric vehicles (EVs) contain large and powerful batteries which pose significant hazards to those not trained
                        in their maintenance. All EV battery maintenance is expected to occur offsite in a facility that specialises in this
                        work.
                        A small volume of batteries may be generated from office-based electronics. Batteries are highly volatile and
                        must be disposed of separately and never in the general waste or commingled recycling bins.
                        TTM recommends a disposal point is provided by site operators and located in a suitable internal space.




Site: 5 – 13 Production Street, Noosaville                                                                                               11
Reference: 24BRW0157

Page 13

2.4.2.       Infrequent Waste
Table 2.8: Disposal of Infrequently Generated Waste
 Refuse Stream              Disposal Details
 Garden Organics            Garden organic refuse, also referred to as green waste will be produced from landscaped areas or potted
 refuse / Green             plants around this development. The volume of green waste is produced on a largely weather or seasonal
 Waste                      dependent basis and based on plant selections. Green waste is usually removed by the designated
                            maintenance contractor. Interim storage is not provided.
                            The engaged contractor will be required to send this material to a composting or resource recovery facility
                            rather than to a landfill.
 Hard Waste / Bulky         The bulk bins provided will also be utilised for bulky waste disposal. Where items are unsuitable for bulk
 Goods                      bin disposal or where significant volumes are generated, such as during refits or rewraps of buses,
                            coordinated collection arrangements will be made and goods items moved to a designated loading point
                            for collection.
                            When storing bulky goods in a loading area, it is recommended that items are placed on a pallet for
                            efficient loading via a pallet jack or forklift onto the RCV.




Site: 5 – 13 Production Street, Noosaville                                                                                           12
Reference: 24BRW0157

Page 14

2.5.         Refuse Storage Arrangements
All general waste and commingled recycling will be stored within 1100L bulk bins housed inside the refuse
enclosure which directly adjoins the workshop.
The refuse enclosure includes a bunded washdown area for the cleaning of bins. As outlined in Table 2.9, the
design of the bin washing amenity meets the criteria outlined in condition of approval 17.
The refuse enclosure is sufficiently sized to accommodate 1100L bins with lifting pockets to enable service by
front loading RCV providing flexibility in servicing strategy.
Waste oils will be stored within 200L drums on a bunded pallet within the workshop area or equivalent bunded
storage arrangement. Waste oils may be relocated within the workshop as operationally convenient through
the use of a forklift or pallet jack.
Figure 2.1 shows a potential layout configuration of the refuse enclosure and demonstrates an indicative
location for the holding of waste oils.




Figure 2.1: Potential Refuse Storage Area Layout
Source: Tyson Design Studio, Project: Noosa Bus Depot, 5-13 Production Street, Noosaville, Drawing: Floor Plan, Drawing Number:
1580-DA02, Rev: E – TTM Layout Markup




Site: 5 – 13 Production Street, Noosaville                                                                                    13
Reference: 24BRW0157

Page 15

Table 2.9 outlines the refuse storage area design criteria addressed in order to minimise odours, deter
vermin, protect surrounding areas, and make it a user-friendly and safe area.
Table 2.9: Refuse Storage Area Design Requirements
   Positioning Considerations
   Positioned in immediate proximity of the designated loading point
   Is in a purpose-built storage area which is designed to be unattractive to vermin and used solely for the storage of refuse leaving
   the site or specifically designed for service vehicle use only.
   Not located adjacent to or within any habitable portion of a building or place used in connection with food preparation (including
   food storage).
   Is positioned away from entrances to shops or residential premises
   Is over 5m from any door, window or fresh air intake within the development or any adjoining site.
   Visual Amenity Considerations
   Is enclosed on all sides except for the access points to ensure bins are not visible from a public place, neighbouring properties,
   passing vehicles or pedestrian traffic external to the site.
   Is designed to minimise their visual impact on the surrounding areas.
   Functional Design Considerations
   Is of sufficient size to accommodate the bins with sufficient clearance around the combined bin area
   Access openings wide enough to allow for the easy removal of the largest container to be stored.
   Permits unobstructed access for removal of the containers to the service point.
   The height of the bin storage area allows for waste bins to be opened and closed.
   Does not have any steps or lips.
   Adequate artificial lighting.
   Bin Washing and Room Cleaning Considerations
   A hose cock fitted with backflow prevention device provided inside the enclosure or immediately adjoining for cleaning bins and
   the enclosures.
   The walls, ceilings, floors and equipment are to be designed and constructed of impervious material with a smooth finish to
   allow for easy cleaning.
   The floors to be bunded and graded to fall to a drainage point.
   Drainage points connected to sewer in accordance with trade waste requirements.
   Roofed and designed to prevent entry by rainwater.




Site: 5 – 13 Production Street, Noosaville                                                                                              14
Reference: 24BRW0157

Page 16

2.6.         Refuse Transfer
Staff / cleaners will transfer all refuse generated from the various areas within the building or from refuse
collected from buses to the refuse enclosure for final disposal.
The collecting contractor will collect all bins directly from the refuse enclosure and manoeuvre a short
distance to the RCV lifting mechanism, and return to the enclosure after service.
The refuse transfer path has been designed to allow for:

   Refuse Transfer Path Design Requirements
   The bins to be transferred via hard stand pathway.

   Allows bins to be easily manoeuvred.

   Does not impede traffic flow.

   Does not extend through any habitable parts of a building or food premise

   Does not have any lips, stairs or steps for bins to be manoeuvred easily.




Site: 5 – 13 Production Street, Noosaville                                                                      15
Reference: 24BRW0157

Page 17

2.7.         RCV and Bin Servicing Arrangements
All refuse will be collected by Private Contractor. Bins may be serviced utilising a Rear Loading RCV or, where
lifting pockets are fitted to bins, by Front Loading RCV. All RCV’s will enter the site in a forward gear via the
bus entry driveway on Production Street and circulate the development to the refuse enclosure. A single
reverse manoeuvre may be performed to reduce the bin transfer distance. Once the collections service is
complete, the contractor will return bins to the refuse enclosure. The RCV will then circulate the
development and exit the site via the bus exit driveway onto Production Street in a forward gear.
The site has been designed for ease of manoeuvreing of a 12.5m bus, which exceeds the expected length of
the likely service vehcile. Further details and swept path analysis on vehicle access and on-site manoeuvring
can be found in the traffic impact assessment report prepared by Modus Transport and Traffic Engineering
document number MOD23176QLD, submitted with the development application submission.
The bin servicing area has been designed with the following features:

 Refuse Servicing Area Design Requirements
 Has sufficient access and clearance for the waste and recycling collection vehicles to service the bins, including no overhead
 obstructions.

 Allows bins to be serviced safely while minimising the impediment to vehicle movements during servicing.

 Is clearly separated from car parking bays, footpaths and pedestrian access.

 Is devoid of stairs, lips or ramps and allows bins to be manoeuvred easily.

 Does not block the entry and exit to the property.

 Is not adjacent to a kitchen or eating area for public use.

 Is over 5m from any door, window or fresh air intake within the development or any adjoining site.

 Is screened sufficiently to minimise the view of bins from neighbouring properties or passing vehicles and pedestrian traffic
 external to the site.

 Is positioned away from entrances to shops or residential premises.




Site: 5 – 13 Production Street, Noosaville                                                                                        16
Reference: 24BRW0157

Page 18

3.           Recommended Operational Refuse
             Management
This section does not contain information relevant for regulatory assessment.
This section relates to the outcomes and waste management practices of the development during the
operational phase as recommended by TTM. It is intended for use as a live document by the occupants of
the development to assist with the ongoing management of the development.



3.1.         On-going Management
The tables below relate to a cycle of ongoing implementation, operation, review and amendment of the
refuse strategy. These tables are intended to serve as a live document to be completed and updated during
the operational phase of the development and therefore intentionally left blank.

Responsibilities have to be assigned for all on-going refuse management related activities during the
operation of the development. TTM recommend the appointment of dedicated personnel to champion
refuse management and sustainability. The following lists (Table 3.1 to Table 3.3) are designed to help
manage and assign responsibilities and monitor the refuse operations. On-going management of the refuse
strategy will maintain efficient services, a safe environment and improve on sustainability outcomes.



3.1.1.       Implementation Phase
Refuse management tasks during the implementation of the refuse strategy are required prior to and during
the early stages of building occupancy. An opportunity to revisit these tasks is provided at set intervals with
the review of the refuse strategy.
Table 3.1: Implementation Checklist
 Task                                                            Assigned   Remarks
 Verify the as-built form of all refuse related areas.
 This task does not refer to building certification but is
 typically undertaken by a specialist waste consultant prior
 to building certification. This provides an opportunity to
 identify variances in building form versus design and
 recommend alternate or mitigating refuse management
 strategies.
 This task may also be required during building refits and
 change of use in tenancies.
 Appoint personnel to oversee or undertake refuse
 management tasks.
 A facilities or operations manager is typically appointed and
 overesees most operational tasks, engaging contractors for
 specialist tasks.




Site: 5 – 13 Production Street, Noosaville                                                                  17
Reference: 24BRW0157

Page 19

 Task                                                              Assigned   Remarks
 Conduct internal safety review.
 An internal safety review is required to be undertaken to
 identify potential hazards in the implementation of the
 refuse strategy and risk mitigation opportunities.
 This includes the use of any refuse management
 equipment installed, as well as refuse transfer paths
 Development of policy and procedures
 Must be undertaken after safety review and abide by all
 relevant occupational health and safety legislation,
 regulations and guidelines to ensure site safety for visitors,
 staff and contractors.
 Also includes assessment of any manual handling risks and
 preparation of a manual handling control plan for waste
 and bin transfers.
 Engage refuse collection contractors.
 Private contractor must conduct a site visit for the
 purposes of risk assessing the site prior to conducting
 services. Contractors must ensure that a full risk
 assessment of equipment, surfaces and related gradients is
 complete and procedural documentation is provided to the
 appropriate personnel.
 Install signage in all refuse disposal and storage points.
 Signage is required to be installed to educate building
 occupants on location of disposal and refuse storage
 points. Additionally, to identify the accepted items
 disposed of in each refuse. The installed signage should be
 colour coded in accordance with AS 4123.7 – 2006 Mobile
 waste containers. Examples of signage are provided in the
 appendices.
 Education and Training.
 Provision of equipment manuals, induction, training, health
 and safety procedures, risk assessments and personal
 protective equipment (PPE) to all staff / contractors
 associated with all waste management activities in order to
 control hazards.
 The step is repeated through the operational phase of the
 development as required due to changes is users or
 personnel.
 Consider fit out and move-in refuse.
 Higher volumes of waste are generated during the initial
 move-in or final fit out. This typically includes large volumes
 of cardboard. Additional bins or collections may be
 required. This also applies to refits.
 Baseline Refuse Auditing
 A baseline audit once the development reaches 80%
 occupancy undertaken by a specialist waste consultant is
 recommended to identify refuse volumes and stream
 composition. This information is then used to establish
 potential recoverable material percentage based on initial
 waste practices and set recycling rate targets.




Site: 5 – 13 Production Street, Noosaville                                              18
Reference: 24BRW0157

Page 20

3.1.2.       Occupation / Operational Phase
Refuse management tasks during the occupation or operational phase of the development relate to the day
to day and business as usual operational tasks that must be undertaken to execute the refuse strategy.
Table 3.2: Occupation / Operation Checklist
 Task                                                               Assigned   Remarks
 Facilitate disposal from throughout the building and buses.
 Appointed staff are required to transfer refuse generated
 throughout the building and the buses to the refuse storage
 area for final disposal, this includes litter removal.
 General cleaning.
 Regular cleaning and maintenance of all refuse management
 facilities is important to maintain a safe and hygienic
 environment for visitors, staff and contractors.
 General cleaning is required for all refuse holding and transfer
 areas including
  • Refuse bins, rooms and storage areas
  • Refuse transfer areas including lifts and staircases
  • Any other refuse management equipment
 Perform spot checks on bin contents and refuse streams.
 Appointed staff regularly check for compliance and stream
 contamination. Early intervention prevents the development of
 poor practice and lost resources. Feedback and education is
 provided to the relevant parties (see below).
 Ongoing education and communication.
 On-going education is important to ensure people continue to
 use the facilities as originally intended and to avoid ongoing
 contamination of recoverable refuse streams.
 Appointed personnel should be actively involved in education
 of occupants and encouraging participation in recycling
 activities. Widespread communication of the achievements of
 the refuse strategy and areas for improvement encourage
 participant buy-in.




Site: 5 – 13 Production Street, Noosaville                                                           19
Reference: 24BRW0157

Page 21

3.1.3.       Review and Amendment Phase
The review and amendment refuse management tasks relate to tasks undertaken on a routine (e.g.
quarterly, bi-annually or annually) or ad hoc basis. At the completion of the review and amendment phase,
the cycle restarts with the implementation of the amended refuse strategy.
Table 3.3: Review and Amendment Checklist
 Task                                                              Assigned   Remarks
 Coordination of specialised cleaning contractors as required.
 Typical specialised cleaning services may include cleaning
 internal areas of compaction equipment (if selected); this
 reduces risk of blockage, odour and risk of fire.
 Maintenance and servicing of refuse management equipment
 as per schedule.
 Frequency depends on equipment, building operation and
 manufacturer specification. Routine maintenance reduces
 downtime and detrimental impact of unscheduled equipment
 breakdown.
 Coordination of specialised equipment contractors as required.
 May extend to ad hoc services requiring specialist equipment
 such as bulky / hard waste removal.
 Internal safety review.
 Routine safety reviews are required to identify changes to the
 site, work practices or legislation that may impact existing
 policies and procedures.
 Reviews should include visual inspection of equipment and
 user PPE.
 Any policy or procedure updates arising from a safety review
 must be immediately communicated.
 Audit operational refuse volumes and composition.
 As similarly undertaken at the beginning of occupancy a review
 by a specialist waste consultant is recommended to identify
 refuse volumes and stream composition. This information is
 then used to establish potential recoverable material
 percentage and identify opportunities for improvement in
 refuse strategy.
 Alternatively, an internal audit may be undertaken by visual
 inspection during on-site waste management handling
 activities. For example, cleaners may observe contents of waste
 receptacles when decanting caddies in larger bins and
 recording results, this method is less accurate than a
 comprehensive audit, however, give immediate indicative
 results and may be undertaken on an ongoing basis.
 Review bin quantities and refuse management equipment.
 Reviewing bin quantities and equipment is required ensure
 operational sustainability of refuse volumes and equipment
 remains fit for purpose. Consideration should be given where
 alternate equipment may provide improved outcomes.
 This review may form part of the external audit process (above)
 as recommendations made.




Site: 5 – 13 Production Street, Noosaville                                                              20
Reference: 24BRW0157

Page 22

 Task                                                               Assigned   Remarks
 Review service frequency and methodology on 6 monthly
 intervals with collecting contractor.
 The service frequency and service methodology should be
 reviewed to ensure the optimum cost efficiency in services
 provided and explore options for additional services.
 Any potential changes to the bin numbers or bin sizes should
 be made in liaison with the appointed contractor to confirm
 cost or contract implications.
 Review of recycling rate target to target continual
 improvement.
 Once benchmarked performance has been assessed against the
 existing targeted recycling rate a new target can be established
 that strives for continual improvement.
 Any changes in targeted recycling rates and the achievements
 of the refuse strategy should be widely communicated to all
 uses.
 Update and amend OWMP based on review outcomes.
 On completion of the refuse strategy review the OWMP should
 be updated to reflect refuse strategy amendments and to
 enable implantation of refuse strategy.




Site: 5 – 13 Production Street, Noosaville                                               21
Reference: 24BRW0157

Page 23

Appendix A                              OWMP Compliance Checklist




Site: 5 – 13 Production Street, Noosaville                          22
Reference: 24BRW0157

Page 24

 Noosa Council SC6.10.5 – Waste Management Design Criteria (PSP9 Waste Management - Noosa Plan 2020)
 Item     Requirement                                                                                       Compliance / Comment
          Preliminary considerations prior to designing waste management facilities may include:
               a) types of waste generated from the site;
               b) presence or absence of service staff or on site management;
               c) distance waste needs to be moved to a waste storage area and/or collection area;
 1.            d) mechanism or pathway used to move bins to the waste storage area;                         Details throughout
               e) the need for a bin wash facility;                                                         OWMP
               f) whether the collection service will be kerbside or on private property; and
               g) whether a central waste storage area will be used prior to relocation of the bin to a
                    bin collection point.
 2.       Council may consider the following matters in assessing applications under the Planning Act
          2017:
               a) the types of waste generated;
               b) waste generation rates;
               c) minimum service levels;
                                                                                                            Details provided
               d) the types of waste storage bins;
                                                                                                            throughout OWMP
               e) location of waste storage areas and bin wash areas;
               f) required size of waste storage areas
               g) safe vehicle and pedestrian access to bins; and
               h) nuisance issues.

 3.       Types of Waste Generated – Consideration of the following matters will determine the types of
          waste storage bins and the minimum service level required;
                                                                                                            Details provided
              a) whether the waste will be putrescible or dry waste;
                                                                                                            throughout OWMP
              b) whether the waste will be recyclable waste; and
              c) whether the waste will be heavy or light.
 4.       Waste Generation Rates - Refer to SC6.10 - Appendix 1 which provides a guide to likely waste      Noosa Councils
          generation for various uses.                                                                      minimum service levels
                                                                                                            applied to operator
                                                                                                            specific generation.
 5.       Minimum Service Levels – Table SC6.10.5.1 indicates minimum service levels for uses. Council
                                                                                                            Complies – 1 Service
          may seek to vary the requirements having regard to the size, location and level of occupancy of
                                                                                                            per week proposed.
          the use.
 6.       Specialised Waste Storage Bins – SC6.10 - Appendix 2 describes two types of specialised waste
                                                                                                            Private contractor
          storage bins available through Council’s contractor.
                                                                                                            proposed.




Site: 5 – 13 Production Street, Noosaville                                                                                         23
Reference: 24BRW0157

Page 25

 Item     Requirement                                                                                        Compliance / Comment
 7.       Size and location of Waste Storage Areas –
               a) The following matters will be considered in determining an appropriate size for waste
                     storage areas:
                           1. Types of waste and storage required:
                                • bins for putrescible waste;
                                • bins for recyclables;
                                • drums for waste cooking oils;
                                • bales for cardboard;
                                • bags or bins for green waste; and
                                • any other specialised waste storage bins needed, eg: medical waste; and
                                                                                                             Complies –
                           2. Sufficient space between waste storage bins to allow for manoeuvring and
                                washing of bins, where appropriate noting that the bin store must be large
                                                                                                             Details throughout
                                enough for the bins to sit next to each other, not behind each other.
                                                                                                             OWMP
               b) Adequate lighting needs to be provided to allow the usage of the bin store after dark
               c) Internal waste rooms should be well ventilated and have a smooth easily cleanable
                     floor
               d) Suitable drainage, with water discharging into a sewer drain, must be installed to
                     allow the washing of bins and a tap with hose connection available.
               e) Waste storage areas can be roofed or unroofed.
               f) Waste storage areas contain bunded and non-bunded areas depending on their size
                     and the type of waste to be stored. Where bunded areas are required:
                      1. waste oil containers must be stored within bunded areas; and
                      2. bins must be washed within the bunded area.
 8.       Screening of Waste Storage Areas - Waste storage areas are required to be screened and can         Complies – All refuse
          be attractively designed to minimise their visual impact on the streetscape and surrounding        storage is provided
          areas. Examples exist within our shire of such storage areas.                                      within enclosures.
 9.       Indoor Waste Storage –
          a) Waste and waste storage bins must not be placed:
                      1. where they may impede safe use of any exit, exit corridor, doorway or stairway;
                      2. under stairways; or
                      3. near any existing or potential heat source.                                         N/A – External
          b) Waste storage bins must be made of non-combustible materials.                                   enclosure provided.
          c) Indoor waste storage areas must:
                      1. be well ventilated;
                      2. be well lit; and
                      3. have “hazardous waste” and “no smoking” signs installed.
 10.      Design Standards for Vehicle Access – Within the development site:                                 Complies – Site
          a) design specifications must be sufficient to carry a wheel load of 7 tonnes per axle; and        designed for 12.5m
          b) turning circles are designed in accordance with AUSTROADS: design single unit truck/bus         buses, minimal
                (12.5 metres) template; and                                                                  reversing required.
          c) vehicles must be able to move in a forward direction at all times or be able to enter and
                exit the development in a forward direction; or
          d) a turning bowl or a “T” or “Y” shaped manoeuvring area is provided, which allows the
                vehicle to turn with no more than a three point turn; and
          e) for bin collection from within a building or structure:
                      1. height clearance must be sufficient to allow for safe travel and lifting for
                            vehicles and bins); and
                      2. the grade of access/egress ramps must not exceed 1:8.




Site: 5 – 13 Production Street, Noosaville                                                                                           24
Reference: 24BRW0157

Page 26

 Item     Requirement                                                                                   Compliance / Comment
 11.      Specialised Equipment and Facilities –                                                        N/A – Standard disposal
          a) Council may require or accept specialised equipment in some circumstances, including:      and collection methods
                    1. refuse chutes where the building is 3 storeys or greater; and                    proposed.
                    2. compaction equipment to minimise storage area.
          b) Compaction equipment may be accepted for the following wastes:
                    1. mixed waste (other than glass);
                    2. cardboard or paper;
                    3. plastic or aluminium containers; and
                    4. putrescible waste - provided a specialised refrigerated compactor is used.
          c) Plans for the installation of compactors must be submitted for the approval of Council’s
              Waste Management Officer.




Site: 5 – 13 Production Street, Noosaville                                                                                  25
Reference: 24BRW0157

Page 27

Appendix B                              Site Plans and Refuse Storage Area
                                        Layout Plan




Site: 5 – 13 Production Street, Noosaville                                   26
Reference: 24BRW0157

Page 28

                                                                                                                                                                                                                                                                                                                                                                   Rev         Description                          Date
                                                                                                                                                                                                                                                                                                                                                                   A   Preliminary Issue                           08/05/24
                                                                                                                                                                                                                                                                                                                                                                   B   Preliminary Issue                           09/05/24
                                                                                                                                                                                                                                                                                                                                                                   C   Design Review 01                            14/05/24

                                                                                                                          Production                                       Street                                                                                                                                                                                  D
                                                                                                                                                                                                                                                                                                                                                                   E
                                                                                                                                                                                                                                                                                                                                                                       Design Review 02
                                                                                                                                                                                                                                                                                                                                                                       Design Review 03
                                                                                                                                                                                                                                                                                                                                                                                                                   24/05/24
                                                                                                                                                                                                                                                                                                                                                                                                                   30/05/24


                                                                                                                                                                                                                                                                                                                                                                Development Schedule
                                                                                                    PP                                                                                                                                                                                                                                      PP
                                     19000                                  8000                5700                                                                                                                                            6000                                16200                                   7500             1000
                                                                                                                                                                                                                                                                                                                                                                GFA
                                                                                                                                                                                                                                                                                                                                                                Workshop                                         274.2m²
                                 31500 mm       0° 00' 00"                                                                                         31500 mm       0° 00' 00"                                                                                               33000 mm        360° 00' 00"                                                         Office                                           183.1m²
                                                                                                                                                                                                                                                                                                                                                                Total:                                           457.3m²




                                                                                                                                                                                                                                                                                                                                 2000
                                                                                                                                                                                                                                                                                                                                                                Parking
                                                                                                                                 Transformer enclosure
                                                                                                                                                                                                                                                                                                                                                                Carpark spaces                                            26
                                                                                                                                                                                                                                                                                                                                                                Motor cycle spaces                                         3




                                                                                                                                                                                                                                                                                                                                 5400
                       Emergency bus park                                                                                                                                                                                                                                                                                                                       Bycicle spaces                                             5
                                                                                                                                                                                                                                                                                                                                                                Landscaping
                                                                                                                                                                     12        11         10        9        8             7                                   6       5        4      3           2          1
                                                                                                                                                                                                                                                                                                                                                                Landscaping area (700.8m²)                          11.5%
                                                                                                                                                7300
                                                                                                                                                                                          2500 - typ'                                                                                                                                                           Site
                                                                                                                              7300                                                                                                                                                                                                                              Site Area                                         6096m²




                                                                                                                                                                                                                                                                                                                                 6200
                                                                                                                                                                                                                                                                                        2000              6200                                                  Site Cover (567m²)                                  9.3%
                                                                                             7300
                                                                                                                                                                                                                                                                                                                                                                RPD
                                                                         7300                       1400                                                                                                                                                                                                                                                        Lot 256 on MCH4539                         Area: 2096m²
                                                                                            900 2500                                                                      13        14         15       16       17                  18          19     20     21          22   23
                                                                                                                                                                                                                                                                                                                                                                Lot 257 on MCH4891                         Area: 2000m²
                                                   7300                            1400 2500                                                                                                                                                                                                                                                                    Lot 274 on MCH4891                         Area: 2000m²




                                                                                                                                                                                                                                                                                                                                 5400
                                                                                                                                                              B
                                                                                                                                           C1                      C1
                              7300                                                                                                                                                                                                                                                                                                                              Legend




                                                                                                                                           B
                                                                                                                         C1




                                                                                                                                           B
                                                                                                                                                                                                                                                                                                                                                                                               Stormwater




                                                                                                                         B
                                                                                        C1



                                                                                                                         B
                                                                                                                                                                                                                                                                                                                                                                                               Sewer




                                                                                                                                                                                                                                                                                             24
                                                                                                                                                                                                                                                                                                                                                                                               Water
                                                                                        B




                                                                    C1
                                                                                        B




                                                                                                                                                                                                                                                                     Bicycles                                       1200          6500                                                         O/H Power




                                                                                                                                                                                                                                                                                             25
                                                                    B




                                              C1                                                                                                                                                                                                                                                                                                                                               U/G Telco
                                                                    B




                                                                                                                                                                                                                       63500 mm
                                                                                                                                                                                                                                                                                                                                                                                               Building Pad




                                                                                                                                                                                                                                                                                             26
                                                                                                                                                                               1
                                               B
                                               B




                                                                                                                                                                                     Biore sin
                         C1                                                                                                                                                                                                                                                                                                                                                                    Walkway
63480 mm




                                                                                                     63488 mm




                                                                                                                                                                                                                                                                                                                                             63510 mm
                                                                                                                                                                                         ba
                                                                                                                                                                                          tentio
                                                                                                                                                                                                                                                   e
                                                                                                                                                                                                                                             Offic
                          B




                                                                                                                                                                                                                                                                                                                                                                                               Concerete Pavement
                          B




                                                                                                                                                                                                                                                                                                  MC1
                                                                                                                                                                                                                                                                                                        MC2
                                                                                                                                                                                                                                                                                                              MC3
                                                                                                                                                                                                    1093




                                                                                                                                                                                                                       90° 00' 00"
                                                                                                                                                                                                n
                                                                                                                                                                                                                                                                                                                                                                                               Landscaping




                                                                                                                                                                                                        0
270° 00' 00"




                                                                                                     270° 00' 00"




                                                                                                                                                                                                                                                                                                                                             90° 00' 00"
                                                                                                                                                                                                                                                                                                                                                                                               Bioretention Basin
                                                                                                                                                                                     C1                                                                                                                                                                            Do not scale drawings. Use written dimensions only
                                                                                                                                                                                                                                                                                            Bins                                                                   Contractor to verify all dimensions & levels on site prior




                                                                                                                                                                                B
                                                                                                                                                         C1                                                                                                                                                                                                        to commencing any work or making any shop drawings




                                                                                                                                                                                          2

                                                                                                                                                                                                             4650
                                                                                                                                                         B
                                                                                                                                      C1
                                                                                                                                                         B
                                                                                                                                       B




                                                                                                                    C1
                                                                                                                                       B




                                                                                                                                                                                                3
                                                                                                                                                                                                                                                               shop
                                                                                                                    B




                                                                                   C1
                                                                                                                    B




                                                                                                                                                                                                                                                       W ork




                                                                                                                                                                                                                    6150
                                                                                                                                                                                                                                                                                                                                                                   call 0411 125 425
                                                                                   B




                                                               C1                                                                                                                                                                                                                                                                                                  email [email protected]
                                                                                   B




                                                                                                                                                                                                                                                                                                                                                                   post box 5337 maroochydore qld
                                                                                                                                                                                                                                                                                                                                                                   qbcc lic. 1070982
                                                               B




                                         C1
                                                               B




                                                                                                                                                                                                                                                                                                                                                                   abn 33 080 662 473

                                                                                                                                                                                                        4
                                         B




                                                                                                                                                                                                                                                                                                                                                                   Project
                                         B




                                                                                                                                                                                                                                                                                                                                                                   Noosa Bus Depot

                                                                                                                                                                                                                           6150
                                                      L o t: 274                                                                                                                                                                                                                                                    L o t: 256                                     5-13 Production Street
                                                                                                                                                                                                                                                                                                                                                                   Noosavile, Qld.
                                                                                                                                                       L o t: 257                                                                                                      hb a y
                                                                                                                                                                                                                                                               W as                                                                                                Title
                                                                                                                                                                                                             5

                                                                                                                                                                                                                                      6000                                                     3700                                                                Site Plan




                                                                                                                                                                                                                                                                                                          C
                                                                                                                                                                                                                                                                       0
                                                                                                                                                                                                                                                                   1460




                                                                                                                                                                                                                                                                                            B
                                                                                                                                                                                                                                                                                                                                                                   Client

                                                                                                                                                                                                                                                                                                                                                                   Integral Construction
                                                                                                                                                                                                                    6



               Bioretention
                  basin                                                                                                                                                                                                                                                                                                                                            Issue
                                                                                                                                                                                                                                              A

                                                                                                                                                                                                                                                                                                                                                                   Preliminary
                                                                                                                                                                                                                                                                                                                                                                   Dwn                                          North Point
                                                                                                                                                                                                                                                                                                                                                                            GT
                                                                                                                                                                                                                                                                                                                                                                   App




                                                                                                                                                                                                                                                                                                                                                                                                                  North
                                              31500 mm       180° 00' 55"                                                                          31500 mm       180° 00' 55"                                                                                             33000 mm        180° 00' 55"
                                                                                                                                                                                                                                                                                                                                                                   Scale
                                                                                                                                                                                                                                                                                                                                                                            As indicated         (at A3)


                                                                                                                                                       Site Plan
                                                                                                                                                                                                                                                                                                                                                                   Date
                                                                                                                                                                                                                                                                                                                                                                            30/05/2024 1:15:07 PM
                                                                                                                                                 1     Scale 1 : 300                                                                                                                           1:300
                                                                                                                                                                                                                                                                                                              0        3     6          9      12          15      Dwg No

                                                                                                                                                                                                                                                                                                                                                                            1580 - DA01
                                                                                                                                                                                                                                                                                                                                                                                                                          Rev

                                                                                                                                                                                                                                                                                                                                                                                                                          E
                                                                                                                                                                                                                                                                                                                                                                 © This drawing is Copyright and is owned by tyson design studio

Page 29

                                                                                                                                                                                                                                                                                                     Rev         Description                          Date
                                                                                                                                                                                                                                                                                                     A   Preliminary Issue                           08/05/24
                                                                                                                                                                                                                                                                                                     B   Preliminary Issue                           09/05/24
                                                                                                                                                                                                                                                                                                     C   Design Review 01                            14/05/24
                                                                                                                                                                                                                                                                                                     D   Design Review 02                            24/05/24
                                                                                                                                                                                                                                                                                                     E   Design Review 03                            30/05/24




                                  1                                                                                           2                          3                                             4                             5                                     6
                                                                             10930                                                           4650                                     6150                       6150                              6000

                                            2000        214           4010           92         2518       92     1940        214            4500        150                                       12000                         1501200           3600              1200



                                                                                                                                    Washdown bund               Bol                              Bol       Bol          Bol

C




                                                                                                                                                                                                                                                                                       150
                                                                                                                                                                                                                                     Dp
                                                                                                                         Dp




                                                                                                                                                                                                                                                                               2100
                                                                                                                                                                                                                              Exit
        3700




                                                                                                                 Gate



                                                                                                                              MSB
                                                                                                                        A/C
    B
                214

                       214




                                                   Dp
                                                                                       Wc                       Wc      Wc




                                                                                                                                                                    10604
                                                                                       Wc
                       3637




                                                                                                                                                                                                                                     Dp
                                                                                                                U                           Store
                                                                                                F-Wc             M-Wc
                6026




                                                                 Meeting
                       92




                                                                                            V                   U
                                                                                                                                                                                                                                                                                                               Areas
                       1120




                                                                                      Comms




                                            Entry
                                                                                                                             V                                                                                                                                                                                      Name                  Area




                                                                                                                                                                                                                                                                                       18000
                                                                                                                                                                                                                                                                                                               Workshop                      274.2 m²
                                                                                                                                                                                                 Workshop
                       2350 92




                                                                                                                                                                                                                                              Washbay




                                                                                                                                                                                                                                                                               15000
                                                                                                       V      Mv        Wc                                                                                                                                                                                     Office                        183.1 m²
                                                                                                                                                                                                                                              (bunded area)                                                    Washbay                       109.8 m²
                150




                                                                                                           Pwd
                                                                                      Lockers




                                 Dp            Exit                                                                     Sh                                                                                                                                                                                     Alfresco                       24.8 m²
                                                                                                                                                                                                                                                                                                               Entry                           4.0 m²
        14600




                                                                                                                                                                    92
                                                                                                                                                                                                                                                                                                                                             595.9 m²
                       92




                                                                                                                                           Store




                                                                                                                                                                    2200
                                                                                                                                                                                                                                                                                                     Do not scale drawings. Use written dimensions only
                3884




                                                              Waiting                                                                                                                                                                Dp                                                              Contractor to verify all dimensions & levels on site prior
                                                                                                                                                                                                                                                                                                     to commencing any work or making any shop drawings




                                                                                                                                                                    92 1720 92
                                                                                                                                                             Exit
                                 Dp
                                                                                                                                    Exit
                92

                       6789




                                                                                                                                                                                                                                                       Pit
                                                                                                   Lunch                                                                                                                                                                                             call 0411 125 425
                                                                                                                                                                                                                                                                                                     email [email protected]
                                                                                                                                                                                                                                                                                                     post box 5337 maroochydore qld
                4020




                                                        Operations                                                                                                                                                                                                                                   qbcc lic. 1070982
                                                                                                                                                                    3200



                                                                                                                                                                                                                                                                                                     abn 33 080 662 473
                                                                                                                                            Office                                                                                                                                                   Project

                                                                                                                                                                                                                                                                                                     Noosa Bus Depot




                                                                                                                                                                                                                                                                               1200
                                                                                                   Exit                                                                                                                              Dp

    A
                                 Dp
                214

                       214




                                                                                                                                                                                                                                                                                                     5-13 Production Street




                                                                                                                                                                                                                                                                                       150
                                                                                                                                                                                                                                                                                                     Noosavile, Qld.
                                                                                92 640 1120            92       2698          214                                                                                                                                                                    Title


                                      214                      6010                  92                4550                   214            4500        150
                                                                                                                                                                                                                                                                                                     Floor Plan
                                                                                                                                              5000 Ltr




                                                                                                          Alfresco                                                                                                                                                                                   Client

                                                                                 Dp
                                                                                                                                                                                                                                                                                                     Integral Construction
                                                                                                                                                                                                                                                                                                     Issue
        3                                                                                                                                                                                                                                                                                            Preliminary
                                                                                                                                                                                                                                                                                                     Dwn                                          North Point
                                                                                                                                                                                                                                                                                                              GT
2                 4                                                                                                                                                              Floor Pan                                                                                                           App

                                                                                                                                                               1                 Scale 1 : 125                                                                                                       Scale
                                                                                                                                                                                                                                                                                                              1 : 125              (at A3)
                                                                                                                                                                                                                                                                                                                                                   North
    1                                                                                                                                                                                                                                                                                                Date
                                                                                                                                                                                                                                                                                                              30/05/2024 1:15:11 PM
Elevations                                                                                                                                                                                                                                         0         1   2     3       4        5      6     Dwg No                                                Rev

                                                                                                                                                                                                                                           1:125                                                              1580 - DA02                                  E
                                                                                                                                                                                                                                                                                                   © This drawing is Copyright and is owned by tyson design studio

Page 30

                                                                                                                                              Rev         Description                          Date
                                                                                                                                              A   Design Review 01                            14/05/24
                                                                                                                                              B   Design Review 02                            24/05/24
                                                                                                                                              C   Design Review 03                            30/05/24



                1                  2                      3                       4          5                              6
                    10930              4650                           6150            6150               6000




                                                   3.0°



C
    3700




B


                                                                                      3.0°
    14600




                            3.0°
                                                                                                                                              Do not scale drawings. Use written dimensions only
                                                                                                                                              Contractor to verify all dimensions & levels on site prior
                                                                                                                                              to commencing any work or making any shop drawings




                                                                                                                                              call 0411 125 425
                                                                                                                                              email [email protected]
                                                                                                                                              post box 5337 maroochydore qld
                                                                                                                                              qbcc lic. 1070982
                                                                                                                                              abn 33 080 662 473
                                                                                                                                              Project

                                                                                                                                              Noosa Bus Depot
A                                                                                                                                             5-13 Production Street
                                                                                                                                              Noosavile, Qld.
                                                                                                                                              Title

                                                                                                                                              Roof Plan
                                        5000 Ltr




                                                                                                                                              Client

                                                                                                                                              Integral Construction
                                                                                                                                              Issue
    3                                                                                                                                         Preliminary
                                                                                                                                              Dwn                                          North Point

2           4                                                     Roof Plan                                                                            GT

                                                              1
                                                                                                                                              App

                                                                  Scale 1 : 125                                                               Scale
                                                                                                                                                       1 : 125              (at A3)
    1                                                                                                                                         Date
                                                                                                                                                       30/05/2024 1:15:13 PM
Elevations                                                                                               0      1   2   3       4   5   6     Dwg No                                                Rev

                                                                                                 1:125                                                 1580 - DA03                                  C
                                                                                                                                            © This drawing is Copyright and is owned by tyson design studio

Page 31

                                                                                           Rev         Description                          Date
                                                                                           A   Design Review 01                            14/05/24
                                                                                           B   Design Review 02                            24/05/24
                                                                                           C   Design Review 03                            30/05/24




               1                         2   3       4                       5                                                6


Roof
13500
        2900




Level 1
10600
        3100




Gnd
7500




                   Elevation 1 - South
               1   Scale 1 : 100




                             C     B             A                                         Do not scale drawings. Use written dimensions only
                                                                                           Contractor to verify all dimensions & levels on site prior
                                                                                           to commencing any work or making any shop drawings
        900




Roof
13500
                                                                                           call 0411 125 425
                                                                                           email [email protected]
                                                                                           post box 5337 maroochydore qld
                                                                                           qbcc lic. 1070982
        2900




                                                                                           abn 33 080 662 473
                                                                                           Project

                                                                                           Noosa Bus Depot
Level 1
10600
                                                                                           5-13 Production Street
                                                                                           Noosavile, Qld.
                                                                                           Title

                                                                                           Elevations 1, 2
        3100




                                                                                           Client

Gnd                                                                                        Integral Construction
7500                                                                                       Issue

                                                                                           Preliminary
                                                                                           Dwn                                          North Point
                                                                                                    GT
                   Elevation 2 - West                                                      App

               2   Scale 1 : 100
                                                                                           Scale
                                                                                                     1 : 100             (at A3)
                                                                                           Date
                                                                                                    30/05/2024 1:15:14 PM
                                                                 0   1   2   3   4   5     Dwg No                                                Rev

                                                         1:100                                      1580 - DA04                                  C
                                                                                         © This drawing is Copyright and is owned by tyson design studio

Page 32

                                                                                                     Rev         Description                          Date
                                                                                                     A   Design Review 01                            14/05/24
                                                                                                     B   Design Review 02                            24/05/24
                                                                                                     C   Design Review 03                            30/05/24




                 6                       5   4   3             2                                                                  1




                                                     900
Roof
13500
          2900




Level 1
10600
          3100




Gnd
7500




                     Elevation 3 - North
                 3   Scale 1 : 100




                                     A               B     C                                         Do not scale drawings. Use written dimensions only
                                                                                                     Contractor to verify all dimensions & levels on site prior
                                                                                                     to commencing any work or making any shop drawings




Roof
13500
                                                                                                     call 0411 125 425
                                                                                                     email [email protected]
                                                                                                     post box 5337 maroochydore qld
        2900




                                                                                                     qbcc lic. 1070982
                                                                                                     abn 33 080 662 473
                                                                                                     Project

                                                                                                     Noosa Bus Depot
Level 1
10600
                                                                                                     5-13 Production Street
                                                                                                     Noosavile, Qld.
                                                                                                     Title

                                                                                                     Elevations 3, 4
        3100




                                                                                                     Client
Gnd                                                                                                  Integral Construction
7500                                                                                                 Issue

                                                                                                     Preliminary
                                                                                                     Dwn                                          North Point
                                                                                                              GT
                     Elevation 4 - East                                                              App


                 4   Scale 1 : 100
                                                                                                     Scale

                                                                                                     Date
                                                                                                               1 : 100             (at A3)

                                                                                                              30/05/2024 1:15:16 PM
                                                                           0   1   2   3   4   5     Dwg No                                                Rev

                                                                   1:100                                      1580 - DA05                                  C
                                                                                                   © This drawing is Copyright and is owned by tyson design studio

Page 33

                                                                                                                                                    Rev        Description                           Date
                                                                                                                                                    A   New & Previous areas                        30/05/24




                                                                                                           Area Schedule
                                               Workshop                    Washbay                                 Name       Area
                                               274.2 m²                    109.8 m²                        Alfresco            24.8 m²
                                                                                                           Office             183.1 m²
                                                                                                           Washbay            109.8 m²
         Office                                                                                            Workshop           274.2 m²
                                                                                                                              591.9 m²
        183.1 m²




                             Alfresco
                             24.8 m²




                                                                                                           Original Areaa




                                                                                           0
                   11000




                                                                                        30
                                                                                                                                                    Do not scale drawings. Use written dimensions only




                                                                                      18
                                                                                                                                                    Contractor to verify all dimensions & levels on site prior
                                                                                                                   Name       Area                  to commencing any work or making any shop drawings
                                                                                                           1_Alfresco          14.7 m²
                                                                            1_Washbay                      1_Office
                                                                                                           1_Washbay
                                                                                                                              215.6 m²
                                                                                                                              109.8 m²
                                                                             109.8 m²                      1_Workshop         265.8 m²
                                                                                                                              605.9 m²
                                                                                                                                                    call 0411 125 425
                                                                                                                                                    email [email protected]
                                                                                                                                                    post box 5337 maroochydore qld
                                                                                                                                                    qbcc lic. 1070982
                                                     1_Workshop                                                                                     abn 33 080 662 473
                                                       265.8 m²                                                                                     Project

                                                                                                                                                    Noosa Bus Depot
15000




                           1_Office                                                                                                                 5-13 Production Street
                                                                                                                                                    Noosavile, Qld.
                           215.6 m²                                                               00                                                Title
                                                                                               60
                                                                                                                                                    Floor Areas
                                                                                                                                                    New & Previous
                                                                                                                                                    Client


                                                                       0
                                                                                                                                                    Integral Construction
                                                                    60                                                                              Issue
                                        1_Alfresco                14
                                         14.7 m²
                                                                                                                                                    Preliminary
                                                                                                                                                    Dwn                                          North Point
                                                                                                                                                             Author
                                                                                                                                                    App
                            15000                                                                                                                            Approver
                                                                                                                                                    Scale
                                                                                                                                                              1 : 200             (at A3)
                                                                                                                                                    Date
                                                                                                                                                             30/05/2024 12:48:23 PM
                                                                                                               0      2   4          6   8   10     Dwg No                                                Rev

                                                                                                       1:200                                                 1580 - DA06                                  A
                                                                                                                                                  © This drawing is Copyright and is owned by tyson design studio

Page 34

Noosa Bus Depot
5-13 Production St, Noosaville, Qld.   Bus Swept Paths - Sheet 6   May 2024   1:300   1580 - TT06   1

Page 35

                                   2                                                                                                                  1500
                                                                                                                                                           3



                                                                                                                         3400
                                                           Washdown bund                                                                                                                           H.C
                                                                                                                                                                                                       Bol

                      Dp
                                                                                                                                                    Indicative Waste Oil
                                                                                                                                                    Storage Location
                                   MSB




                                                                                        SCALE                                                                                                               PROJECT                                          PROJECT NUMBER   ORIGINAL SIZE
                                                                                            0   0.25            0.5      0.75         1.0   1.25m                                                                     Proposed Transport Depot
                                                                                                                                                      TTM CONSULTING PTY LTD                                                                                 24BRW0157            A3
                                                                                                                                                                                                                      5 - 13 Production Street, Noosaville
                                                                                                                                                      ABN 65 010 868 621                                    DRAWING TITLE                                    DRAWING NUMBER     REVISION
                                                                                                        SCALE 1:25 AT ORIGINAL SIZE
                                                                                                                                                      LEVEL 8, 369 Ann Street, BRISBANE QLD 4000
                                                                                        NORTH          CLIENT                                         P.O. BOX 12015, BRISBANE QLD 4003                                                                      24BRW0157-01          A
                                                                                                                                                                                                              REFUSE STORAGE AREA LAYOUT
                                                                                                       Evolution MIT Services P/L TTE                 T: (07) 3327 9500 F: (07) 3327 9501                     FLOOR PLAN - TTM MARKUP                        DATE                SHEET
 A     09-07-24   ORIGINAL ISSUE                              NL       SK      SK                                                                     E: [email protected]   W: www.ttmgroup.com.au                                                    9 Jul 2024       1 OF 1
REV.    DATE                       AMENDMENT DESCRIPTION     DRAWN   CHECKED APPROVED

Page 36

Appendix C                              Systems and Specifications




Site: 5 – 13 Production Street, Noosaville                           35
Reference: 24BRW0157

Page 37

C.1           Specified Refuse Management Equipment

The table below provides contextual examples of the specific equipment types specified in this OWMP and is
not intended to provide an exhaustive list of all potential options of the required equipment.


                   Waste
 Bin Types                                   Examples               Information
                   Streams
 Back of           General                                          Various options and sizes available. Tenant to
 House area        waste,                                           supply depending on preference and space
 bins              recycling,                                       available.
                   food waste,                                      Example: 60L multisort bins
                   paper /                                          https://www.sourceseparationsystems.com.au-
                   cardboard                                        /product/multisort




 1100L bins        General                                          Dimensions approx.
                   waste,                                           (Excluding lift pockets)
                   recycling,                                       1070 x 1240 x 1330mm (L x W x H)
                   paper /                                          (dimensions depend on contractor)
                   cardboard
                                                                    Examples:
                                                                    http://www.justwheeliebins.com.au,
                                                                    https://www.australianwaste
                                                                    management.com.au
 Drums on          Liquid Waste                                     Spill containment, e.g. for waste cooking oil
 Bunded                                                             containers
 pallets                                                            Example:
                                                                    https://www.tradeenviro
                                                                    .com.au/bunded-pallets
                                                                    https://www.materialshandling
                                                                    .com.au/products/bunded-pallet


 Refuse /          All Streams                                      Assisted manual transfer of refuse
 Cleaners                                                           Examples:
 Trolleys                                                           https://rubbermaidcommercial
 (Optional)                                                         .com.au/products/waste-management/mega-
                                                                    brute
                                                                    https://www.materialshandling
                                                                    .com.au/products/deluxe-compact-cleaning-
                                                                    carts




Site: 5 – 13 Production Street, Noosaville                                                                      36
Reference: 24BRW0157

Page 38

                   Waste
 Bin Types                                   Examples   Information
                   Streams
 Secure            Confidential                         Secure bins, sizes range up to 240L.
 Destruction       Paper                                Examples
 Papers Bin                                             https://www.shred-x.com.au/document-
 (Optional)                                             destruction/document-shredding-destruction/
                                                        https://www.cleanaway.com.au/waste/secure-
                                                        document-destruction/




Site: 5 – 13 Production Street, Noosaville                                                     37
Reference: 24BRW0157

Page 39

ttm

Appendix D Refuse Signage

Site: 5 — 13 Production Street, Noosaville 38
Reference: 24BRWO157

Page 40

D.1          Refuse Signage
Waste signage guideline are provided by the Queensland government:
https://www.qld.gov.au/environment/pollution/management/waste/recovery/recycling/signage.

General Refuse Signage




Other Refuse Signage




Colour coding as per AS 4123.7-2006

               Mixed (Commingled) Recycling                PMS 108
               General waste (landfill)                   PMS 032C
               Organics                                 PMS 15-0343
               Paper and cardboard recycling          PMS Process Blue C
               Soft Plastics                              PMS 1655
               Used Cooking Oil                             Grey




Site: 5 – 13 Production Street, Noosaville                                                  39
Reference: 24BRW0157

Page 41

D.2          Other Refuse, Facility and Safety Signage
Various signage including refuse area, safety and facility signage should be arranged through certified
signage providers. Example signs can be found at http://www.signblitz.com.au, https://www.wayout.com.au
or https://www.smartsign.com.

Example Refuse Room Signage




Example Facility Signage




Example Safety Signage




Site: 5 – 13 Production Street, Noosaville                                                          40
Reference: 24BRW0157

Page 42

Appendix E                              Terms and Abbreviations




Site: 5 – 13 Production Street, Noosaville                        41
Reference: 24BRW0157

Page 43

In this OWMP, a term or abbreviation has the following meaning unless indicated otherwise:
 TERM                     ABBREVIATION       DEFINITION
 Equipment
 Bin (Refuse Bin)                            A plastic or steel container for disposal and temporary storage of waste or recycling items.
                                             Various types and sizes exist for different items and purposes. Examples include residential
                                             unit bins, bulk bins, MGB, steely bins and specialised for medical waste or cigarette butts.
 Bin Storage Area                            An enclosed area designated for storing on-site refuse bins or a refuse compactor within
                                             the property.
 Bulk Bin                                    A galvanized or steel bin receptacle that is greater than 360L in capacity generally ranging
                                             from 1.00m³ to 4.50m³ used for the storage of refuse that is used for on-site refuse
                                             collection.
 Bulk Mobile              Bulk MGB           A plastic (polypropylene) receptacle that is greater than 360L in capacity generally ranging
 Garbage Bin                                 from 660L to 1100L used for the storage of refuse.
 Collection Point                            An identified position where refuse bins are stored for collection and emptying. The
                                             collection point can also be the bin storage area.
 Compactor                                   A receptacle that provides for the mechanical compaction and temporary storage of
                                             refuse. It allows to reduce bin numbers and collection frequency.
 Composter                                   A container or machine used for composting specific food scraps and/or organic materials.
 Food Waste                                  Defined as a vacuum or pump-based system for shredding, macerating or pulping of food
 Recycling System                            waste. The food waste is transferred through pressure (service) pipes to sealed liquid
                                             storage tanks.
 Green Waste                                 All vegetated organic material such as small branches, leaves and grass clippings, tree and
                                             shrub pruning, plants and flowers.
 Liquid Waste                                Non-hazardous liquid waste generated by commercial premises should be connected to
                                             sewer or collected for treatment and disposal by a liquid waste contractor (including
                                             grease trap waste).
 Mobile Garbage           MGB                A plastic (polypropylene) bin or bins used for the temporary storage of refuse that is up to
 Bin                                         360L in capacity and may be used in kerbside refuse collection or on-site collection.
 Putrescible Waste                           Putrescible waste is the component of the waste stream liable to become putrid and
                                             usually breaks down in a landfill to create landfill gases and leachate. Typically applies to
                                             food, animal and organic products.
 Recycling                                   Recycling contains all material suitable for re-manufacture or re-use, e.g. glass bottles and
                                             jars; plastics such as PET, HDPE and PVC; aluminium aerosol and steel cans and lids; milk
                                             and juice cartons; soft drink, milk and shampoo containers; paper, cardboard, junk mail,
                                             newspapers and magazines.
 Refuse                                      Refuse is material generated and discarded from residential and commercial buildings
                                             including general waste, recyclables, green waste and bulky items.
 Refuse Storage                              An area identified for storing on-site MGBs or Bulk Bins within the property.
 Room
 Refuse Tolley                               A cart on wheels that can be used to collect smaller quantities of refuse from different
                                             areas or rooms of a building or site, and wheel the collected refuse to a (bulk) bin storage
                                             area where it is disposed. Refuse trolleys are commonly used in hotels or offices.
 Regulated Waste                             Regulated waste is waste prescribed under legislation as regulated waste.




Site: 5 – 13 Production Street, Noosaville                                                                                              42
Reference: 24BRW0157

Page 44

 TERM                     ABBREVIATION       DEFINITION
 Transfer (Manual                            Manual transfer means physical transfer of refuse material and associated bulk bins or
 Transfer)                                   trolleys without assistance.
 Waste                                       Waste is referred to as refuse material with the exclusion of recycling, green waste,
                                             hazardous waste, special waste, liquid waste and restricted solid waste.
 Waste (General                              General waste is generally referred to as material free of any actual or apparent
 Waste)                                      contamination such as pathological / infectious, radioactive materials and / or hazardous
                                             chemical. Reporting use is for material considered to be free of food waste.
 Wheelie Bin                                 A MGB of up to 360L, usually with 2 wheels for easy transfer. A common type is a 240L
                                             wheelie bin used for kerbside collection in many residential areas.
 Measures
 Cubic Metre              m3                 Volume in cubic metre(s) related to refuse management equipment.
 Ground Floor Area        GFA                The GFA of all storeys of a building is measured from the outside of the external walls or
                                             the centre of a common wall. It is commonly measured in square metres.
 Kilogram                 kg                 Kilogram(s) related to refuse weight.
 Litre                    L                  Litre(s) related to refuse volumes.
 Square Metre             m2                 Square metre(s) related to refuse areas.
 Ton                      T                  Ton(s) related to refuse weight.
 Collection Vehicles
 Body Truck                                  A conventional heavy vehicle with a covered loading area. It is generally not specifically
                                             designed for emptying the content of bins into the truck during refuse collections, but can
                                             be used to carry entire (full) bins for servicing by bin swap-over.
 Refuse Collection        RCV                A vehicle specifically designed for collecting and emptying refuse bins and refuse
 Vehicle                                     compactors.
 Rear-End-Loading         REL RCV            A truck specially designed to collect municipal solid waste and recycling, typically 240L
 Refuse Collection                           wheelie bins to 1100L bulk bins, from rear loading mechanism and haul the collected
 Vehicle                                     waste to a solid waste treatment facility.
 Tank Truck                                  An RCV that is specifically designed to collect liquid wastes such as waste cooking oil and
                                             food waste pulp. The waste is typically pumped from a waste storage tank into the truck
                                             via a hose. Liquid waste management equipment is often provided by the contractor who
                                             collects the waste and operates the truck.




Site: 5 – 13 Production Street, Noosaville                                                                                               43
Reference: 24BRW0157

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.