12. APP G. Stormwater Management Plan
Attached to the e-mail MCU14/0102 Development application Part 3 of 4 App G Stormwater Management Plan.
Original PDF page 15, section 1. The text section number identifies this passage in the reader.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn STORMWATER QUANTITY, DETENTION &
HYDRAULICS
OBJECTIVES
The stormwater discharge from the proposed development shall maintain the pre-developed
flow rates for all storm events, from the 1 in 1 year (frequent flow) to 1 in 100 year (major storm
events).
The stormwater management strategy will also need to comply with the Noosa Council
Stormwater Management Code.
METHODOLOGY
A hydrologic model was created using XP-RAFTS. The model was calibrated and verified via a
comparison to the results of the Rational Method calculations (described in Section 4.5). The
critical storm event for each standard ARI was determined via an investigation of storm
durations ranging from 10mins to 720mins. The model was then used to route post-
development runoff through detention basin structures to determine adequate detention basin
size to comply with the objectives. The model was iteratively optimised to achieve the most
efficient design dimensions.
The required detention volume is proposed to be included as additional volume above the
extended detention depth within the proposed bio-retention basin. The runoff routing model has
therefore considered suitable dimensions to allow for the installation of filter material in the base
of the basin. The weir width and outlet pipe size have also been individually designed according
to the required discharge flow rates and receiving system.
5.1.1 MODEL CONDITIONS
Three hydrologic conditions were modelled as shown below.
Case 1 - Existing Scenario
Case 2 - Developed Scenario
Case 3 - Mitigated (Developed with Detention Scenario)
5.1.2 DETENTION BASIN DESIGN
Table 5.1 presents the design details of the proposed detention basin which is required to
achieve the waterway stability management objectives. The basin design has been iteratively
optimised to ensure peak performance.
It has been determined that due to the increase in impervious area, that the site requires
stormwater quantity controls to mitigate flows. A detention basin has therefore been proposed to
mitigate this consequent increase in peak discharge resulting from the development.
The proposed lot layout incorporates the proposed basin area listed in Table 5.1.
Stormwater Management Plans
Page 8 Hyder Consulting Pty Ltd-ABN 76 104 485 289
f:\aa007595\f-reports\f0002-aar-aa007595 sbswmp report\f0002-aa007595-aar-03.-smp.docx
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLarge file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.