CAPITAL PROGRAM 2024/25 DELIVERY STATUS · Report
SERVICES & ORGANISATION COMMITTEE MEETING 12 NOVEMBER 2024
Remaining
Commitments/contract 6,897,858 2,499,953 9,397,811
values
Table 1 – Capital Finance data as at 30 September 2024
Figure 2 – Budget Status of Capital Works as at 30 September 2024
Grant Funding
The 2024/25 financial year Capital Works Program includes an unprecedented amount of grant
funding.
Figures 3 and 4 below demonstrate the non-grant funded capital projects compared to projects with
grant funding, as well as Council’s contribution towards grant funded projects.
Figure 3 detail Percentage Value of
of CWP CWP
Non-Grant funded 58% $31.1m
Projects
Projects with Grant 42% $22.7m
Funding
Figure 3 – Projects with and without grant funding.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.