6.1 Management of Stormwater
This sub-section describes the treatment train (Drawings 02 & 06) used to manage
stormwater flowing through the Essence of Peregian development. The treatment train
is designed to keep stormwater within the landscape of the proposed development site.
There are three treatment units in the design treatment train:
6.1.1 Roof Water capture
Guttering provides capture of the rainwater incident upon the roofs of the buildings
within the development. 100% of the roof guttering is connected to rainwater tanks,
which provide both rainwater storage for re-use within the development, and attenuation
of stormwater flows.
These tanks have been sized in line with MP-4.3 of the Queensland Building Code to
meet water savings targets, and sized are as follows
• Beach Shacks: 3 kL
• Building A: 100 kL
• Building B: 100 kL
• Hotel/Commercial Area: 100k L
These tanks are to be provided with appropriate inlet arrangements, including first-flush
diverters. Overflow of the tanks are to be connected to the Bioretention basins for
treatment before release to the receiving environment.
6.1.2 Vegetated Buffers
Vegetated buffers provide stable groundcover, thereby minimising the erosion potential
of the landscape surface. Vegetation includes grassed surfaces and deep rooted
vegetation. Energy from rainfall is dissipated over a broad, stable surface, and shallow
sheet-flow of accumulated stormwater is slowed by the rough surface provided by the
vegetation. The soil binding capacity of the plant roots, and the capacity of the plants to
assimilate nutrients from infiltration water, provides the first step of the treatment train.
Stormwater flows from the vegetated buffers into Bio-retention Trenches or directly into
the Constructed Wetland System.
6.1.3 Blo-retention Trenches
The Bio-retention Trenches are generally dry, but during a stormwater flow the trenches
may contain accumulated water to a depth of 200 mm, and 150 mm shortly thereafter
when the trench is dewatering.
Flow out of the Bio-retention Trenches is underground, with filtered water percolating
through the base of the terminal gabion wall, through a readily permeable geotextile
layer. Flow out of the Bio-retention Trenches during high flow will primarily be through,
and across, the crest of the gabion weirs. Maximum flow depths over the weir crests in
the 100 year local runoff event are estimated to be less than 25 mm. Outflow is towards
the terminal Wetland.
Overland sheet-flow for the majority of the development is to be piped from stormwater
collection pits to the bio-retention basin. For the periphery, where it is not possible to
use stormwater collection pits, an interceptor drain, essentially a grassed swale, will be
used to capture and divert incident stormwater to the bio-retention basins for treatment.
Pipe and swale entrances to the bio-retention basins are to use rock basins and energy
diffuser arrays to protect against scouring (drawing 04 & 05).
©2012 Simmonds & Bristow Pty Ltd Contrast Constructions J-1005-310 - 13 January 2012
I:\CLIENTFILES\Contrast Constructions\1108-155c - Essence of Peregian SCEP Stage 1 Update\09 Output Documents\1108-155C_SWMP
SCEMP_Scanion Property Group V3.O_ta_120113.doc Page 8 of 24
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
PART Response to Information RequestRelated documentApplication case desk ↗
About this file
- File size
- 26.7 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.