Lake MacDonald Drive Cooroy - WMP
Workplace Management Plan
Lake MacDonald Drive, Cooroy
The Foreman shall perform the following checks before service installation commences:
▪ Confirm approval of bedding material;
▪ Ensure that the equipment is appropriate for the required tasks;
▪ Confirm that the setting out for line and level is adequate;
▪ Brief the work crew on the extent of the work and ensure they understand and follow correct placing
techniques.
Underground services will be installed in accordance with the drawings and the specification.
Draw cords and cable marker tape will be installed where required by the drawings and specification.
Services will be tested in accordance with the local authority requirements.
The Foreman shall perform the following checks before backfilling commences:
▪ Confirm that backfill material is free from organic matter;
▪ Ensure that the equipment is appropriate for the required tasks;
▪ Brief the work crew on the extent of the work.
Backfilling will be performed in accordance with the drawings and specifications.
Where suitable, backfill will be obtained from the trench excavation.
Compaction will be achieved using a vibrating trench roller and/or vertical rammer.
Density tests will be performed as per specifications.
Excavation and Foundation Preparation For Concrete Works
The Foreman shall ensure that the following pre-commencement checks occur:
▪ Confirm that the set out is adequate
▪ Confirm that an excavation permit is in place
▪ Confirm the location of existing services;
▪ Ensure that the equipment is appropriate for the required task;
▪ Obtain approval of spoil location
▪ Brief the work crew on the extent of the work.
When the excavation is down to the correct level, the Foreman shall complete the following checks:
▪ Inspect the foundation and place blinding concrete where required;
▪ Gain approval from the superintendent for the removal and replacement of unsuitable material.
Compaction tests shall be undertaken on the foundation in accordance with the specifications.
Where required on the drawings, the Foreman shall ensure that soil bearing tests are undertaken.
The Foreman shall obtain approval of the foundation prior to commencing formwork for concrete.
IMS-04-01_P – Reviewed – September 2020 Document Uncontrolled When Printed Page 48 of 60