RFI - SPEL Lifecycle Costing

of 4

Page text shows just the words. Original shows the document exactly as it was published.

                                                                                            PHONE: 07 3271 6960
                                                                                 EMAIL: [email protected]
                                                                      OFFICE: 130 Sandstone Pl, Parkinson QLD 4115
                                                                                                www.spel.com.au


Optimum performance of the equipment covered by this Agreement can be expected only if supplies
provided by, or meeting the specifications of Service Provider are used. Service Provider shall have full
and free access to the equipment to provide service thereon. If persons other than Service Provider's
representatives perform maintenance or repairs, and as a result further work is required by Service
Provider to restore the equipment to operating condition, such repairs will be billed at Service Provider's
published time and material rates then in effect.

4.      ANNUAL RATE FOR SERVICES
4.1     INCLUSIONS
                ACTIVITY                            FREQUENCY                     COST BREAK-DOWN
                                                   [subject to site               [subject to CPI index]
                                                   characteristics]
  Inspection and Maintenance:                   Every four months           $1,164.00 per inspection
  5 SPEL Stormsacks                             3 x per year                $3,492.00 per annum
  7 cartridges SPELFilter system

  - Visual inspection of the Stormsacks,
  vault and filter conditions – SPEL
  technician to empty the Stormsacks bag.
  Replacement Factors:                          Based on the [site]         1 x Labour, travel expenses
  -SPEL Stormsack bags and SPELFilter           stormwater treatment
  replacement – allowance for 3 times           train and past              15 x SPEL Stormsack bags
  change out of Stormsacks and 1 time           experience we               Replacement
  replacement of Filters throughout the 10      estimate the life of the
  year period.                                  SPELFilters to be           7 x SPEL Filters Replacement
  -All old SPELFilters and Stormsack bags       between 6 - 8 years.
  removed, disposed and replaced.                                           Total once in
                                                The Stormsack bags          10 years =               $24,750.00
  Note: The vault to be cleaned out via         to be changed out in
  a vacuum truck prior to installation          year 3, 6 and 9.            Per annum =                $2,475.00
  of the new filter units, price on
  application.
                                                SUMMARY
      Replace the 5 Stormsacks and 7 Filters in accordance with above in 10 years, turnkey operation
       • Inspection and Maintenance: $3,492.00 per annum
       • Replacement Factors: $2,475.00 per annum
       • Total Investment Value Per Annum: $5,967.00 + (GST)

The annual rate for maintenance of SPEL Stormsack & SPEL Filter for a 10 year term is $5,967.00 +
(GST) and shall be paid upon receipt of invoice. The annual rate shall be indexed by CPI at each annual
renewal date. Any payment not made by the 30th day of the month shall be considered overdue and in
addition to Service Provider's other remedies, Service Provider may levy a late payment charge equal to
4% per month on any overdue amount. SPEL to send maintenance report per service.

4.2     EXCLUSIONS
             ACTIVITY                     FREQUENCY [subject to                  COST BREAK-DOWN
                                             site characteristics]               [subject to CPI index]
  Vacuum out of Filter tank, removal      When necessary, based            This is an additional cost to the
  and disposal of pollutants              on the maintenance               regular maintenance contract
                                          inspection and report            and has not been included in
  Note: Cigarette holes in Stormsack                                       the annual rate indicated below.
  bags is not eligible for warranty
                                                                           Costing to be confirmed at time of
                                                                           activity based on extent of
                                                                           pollutants removed and disposed.
Log in to download the original file

RFI - SPEL Lifecycle Costing.pdf · 475 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.