Minor Change Existing Approval - 51901 25 01 (As Published)

of 7

Page text shows just the words. Original shows the document exactly as it was published.

                      Note: Asbestos is a Regulated Waste. The Department of Environment & Science licenses
                      businesses that transport asbestos waste, and landfills that accept this waste.
                      General
               32.    Infrastructure including reticulated water, sewerage, stormwater, and electricity must be
                      protected from damage and made safe to the standard required by the regulatory authority.
               33.    Any damage to footpaths, street plantings, natural vegetation/trees, kerb and channel,
                      bridges or roadways at the removal/demolition site must be repaired or reinstated to at least
                      pre-existing conditions.
                      Plumbing and Drainage
               34.    It is a requirement of the ‘Standard Plumbing and Drainage Regulation 2019’ that at
                      demolition of a building, the existing sanitary drain upstream from the connection point for a
                      service provider’s sewerage system must be sealed water tight. This work is deemed as
                      notifiable Work and must be carried out by a suitably licenced plumber who must submit an
                      As Constructed plan and Form 4 (Notifiable Works Form) to the QBCC (Queensland Building
                      Construction Commission) within 10 days of completing the work.
               5.     REFERRAL AGENCIES

               Not applicable.
               6.     ADVISORY NOTES

               Not applicable.
               7.     PROPERTY NOTES

               Not applicable.
               8.     VARIATION APPROVAL DETAILS

               Not applicable.
               9.     FURTHER DEVELOPMENT PERMITS REQUIRED

                Type of Development Permit Required                Subject

                Development Permit for Building Works              All building work

               10.    SUBMISSIONS

               Not applicable.
               11.    RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.




                                                                                                       Page 5 of 7
Document Set ID: 23941513
Version: 4, Version Date: 17/07/2025
Log in to download the original file

Minor Change Existing Approval - 51901 25 01 (As Published).pdf · 160 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.