Skip to the record
Noosa’s premier civic archive.

Council archive · source document

Negotiated Decision Notice [As Published] · 132009.1270

of 11

Text shows just the words. Original shows the document exactly as it was published.

                                                                                         2009/1270



        site infiltration etc are in compliance with Council’s standards, conform with all aspects of the
        design and that the completed works will not have any adverse impacts on the stability of
        adjoining buildings and/or structures and/or services and/or lands and the sand dune.
Contribution Towards Council Infrastructure
34.     Monetary contributions shall be paid to Council towards the cost of providing and/or
        upgrading various infrastructure at the rates applicable at the time of payment. An estimate
        only of the contribution amounts under the current Council policies and requirements is
        outlined in the table below:
          Contribution Required For:                                                   Amount:
          PSP20 – Pathway Trunk Network Contributions                                  $727
                                                                                       $727
          TOTAL Contribution Amount =
          Please note that these amounts are all subject to variations in the Consumer Price Index,
          All Groups Brisbane from September 2009 until the date of payment.

      All contributions must be paid prior to commencement of the use
5     REFERRAL AGENCY CONDITIONS

The referral agencies applicable to this application are:

 Referral Trigger              Referral Status   Referral Agency         Referral Address

 Not applicable

6     APPROVED PLANS/DOCUMENTS
The approved plans and / or documents for this development approval are listed in the following
table:
 Plan / Document No.       Rev.     Plan / Document Name                       Date

 WD01                      A        Site Calculations – Soul Space Building    6 November 2009
                                    Design

 WD02                      A        Site Plan – Soul Space Building            6 November 2009

 WD03                      A        Site Setback    Plan –     Soul   Space    6 November 2009
                                    Building

 WD04                      A        Sub Floor Plan – Soul Space Building       6 November 2009

 WD05                      A        Lower Floor Plan – Soul Space Building     6 November 2009

 WD06                      A        Lower Floor Setout Plan – Soul Space       6 November 2009
                                    Building

 WD07                      A        Main Floor Plan – Soul Space Building      6 November 2009

 WD08                      A        Main Floor Setout Plan – Soul Space        6 November 2009
                                    Building

 WD09                      A        Upper Floor Plan – Soul Space Building     6 November 2009

                                                                                           6 of 11

Used in these records

About this file

File size
70 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Negotiated Decision Notice [As Published].pdf · 70 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.