Dewatering Management Plan

of 44

Page text read automatically using OCR, there may be inaccuracies

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
                                                                                           ADG Consulting Pty Ltd



     Table 5 Monitoring responsibilities

                           Activity                          Frequency          Responsibility        Person

       Monitoring of field parameters in discharge water         Daily          Site Manager       Site Manager

       Monitoring of field parameters in discharge                              Environmental     Environmental
                                                               Weekly             Consultant
       water, receiving waters and background waters                                                Consultant

       Laboratory analysis of samples recovered from                            Environmental     Environmental
                                                               Weekly             Consultant
       discharge water and receiving waters                                                         Consultant

       Monitoring of field parameters in extracted         Initially, then as   Environmental     Environmental
       groundwater (pre‐treated)                               required           Consultant        Consultant

       Laboratory analysis of samples recovered from       Initially, then as   Environmental     Environmental
       extracted groundwater (pre‐treated)                     required           Consultant        Consultant

6.6 Maintenance
     The groundwater treatment systems must be regularly maintained. Maintenance must include:
          Regular cleaning and or replacement of media within the filtration unit, where required to be
           installed.
          Regular removal of sediment from the sedimentation tank. The sediment must be either returned
           to the excavation pit for dewatering and bulking out with excavated material, or removed from the
           site by a licensed liquid waste contractor.
          Regular check of the dosing system and top‐up of buffering solutions and flocculants.
6.7 Reporting
     Dewatering management procedures and monitoring results will be reviewed by the Environmental
     Consultant weekly to ensure that the treatment procedures are effective, and that the receiving waters
     are not being impacted by the extracted groundwater being discharged.

     The following reporting procedures will be adopted:
          A summary report will be prepared upon completion of the initial/pre‐discharge monitoring. The
           report will be submitted to the Site Manager, Dewatering Contractor, and NSC upon request.
          Weekly interim reports will be prepared upon receipt of laboratory data for each round of ongoing
           compliance monitoring. The interim reports will display all data obtained during the previous
           monitoring event, and provide comments and recommendations based on the results.
          A dewatering compliance report will be prepared on completion of the project (upon request).
     The above reports will be prepared by the Environmental Consultant and provided to the Site Manager
     and Dewatering Contractor as they become available. The reports will include all water quality results
     and comparison to the WQOs, corrective actions and recommendations made to the Site Manager and
     Dewatering Contractor during the monitoring period.

     The Site Manager must keep records of complaints, volumes of chemicals used, and treatment methods
     employed. These records must be available on‐site at all times and submitted to NSC by the Site Manager
     upon request.
6.8 Contingencies
     If water quality monitoring indicates ongoing exceedances of the performance criteria, and the water
     quality objectives for the receiving waters cannot be met, then corrective actions will be adopted as
     necessary. Possible contingencies may include one or more of the following:

ADG1786.25 Dewatering Management Plan_Rev0_20.02.25                                                        Page 15
Log in to download the original file

Dewatering Management Plan.pdf · 3.2 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.