Approved Decision Notice - OPW24/0098 - [AS PUBLISHED]
Plan No. Rev. Plan/Document Name Date
0282-CS Cover Sheet prepared by SCG Consulting May 2024
Engineers
0282-CN Construction Notes prepared by SCG May 2024
Consulting Engineers
0282-OW3.1 Earthworks prepared by SCG Consulting May 2024
Engineers
CURRENCY PERIOD
2. The Currency Period for this development approval lapses if the development has not
substantially started by 25 September 2026, unless an application to extend the currency
period is approved by Council.
Site Specific Conditions
3. The submitted Geotechnical Investigation Report (reference PTG/00259 – 0001 - Rev 0
prepared by PTG Consulting) must be updated when the demolition of the existing structures
on the site has been completed. The report must be based upon additional investigations to
meet Queensland Acid Sulfate Soils Technical Manual (QASSTM) requirements. The
amended report must be submitted to Council at least 5 business days prior to the pre-start
meeting.
4. A site control and/or compliance bond of $10,000 is to be submitted to Council prior to the
pre-start meeting. The bond is to secure performance of all conditions of this approval, prior
to the pre-start meeting. The cash bond or trading bank guarantee will be returned on
performance of the conditions of approval less any costs incurred by Council in respect of
enforcing performance of this permit. Council reserves the right to call upon the bond or
guaranteed sum to effect compliance with conditions.
PRIOR TO COMMENCEMENT OF WORKS
Engineering
5. All necessary approvals from external service providers (eg Unitywater) and external parties
on which the development works are proposed have been obtained and a copy supplied to
Council.
6. Copies of the approved plans, duly signed by the consultant Registered Professional
Engineer of Queensland (RPEQ) must be provided to Council’s Engineering Officer
Construction at the “pre start” meeting.
7. A condition report including photographs of the frontage of the site must be completed and
submitted to Council at the prestart meeting / prior to any works commencing.
8. Certificates demonstrating currency of public liability insurance and works insurance covering
the works must be submitted to Council prior to the prestart meeting.
9. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. Civil engineering works;
b. Erosion and sediment control works;
c. Other relevant parties
10. A Construction Management Plan must be submitted to Council prior to the pre-start meeting
and must specifically address the following:
a. Traffic Management during all aspects of the construct phase including:
Page 2 of 9
Document Set ID: 23264906
Version: 4, Version Date: 30/09/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Approved Decision Notice - OPW24/0098 - [AS PUBLISHED]Related document
SUPERSEDED Approved Decision Notice - OPW24/0098 - [AS PUBLISHED]Related documentApplication case desk ↗
About this file
- File size
- 160 KB (small file)
- File type
No other editions are linked here.