Approved Decision Notice - OPW24/0098 - [AS PUBLISHED]

of 9

Text shows just the words. Original shows the document exactly as it was published.

                           Plan No.           Rev.     Plan/Document Name                          Date

                           0282-CS                     Cover Sheet prepared by SCG Consulting May 2024
                                                       Engineers

                           0282-CN                     Construction Notes prepared by SCG May 2024
                                                       Consulting Engineers

                           0282-OW3.1                  Earthworks prepared by SCG Consulting May 2024
                                                       Engineers

               CURRENCY PERIOD
               2.     The Currency Period for this development approval lapses if the development has not
                      substantially started by 25 September 2026, unless an application to extend the currency
                      period is approved by Council.
                      Site Specific Conditions
               3.     The submitted Geotechnical Investigation Report (reference PTG/00259 – 0001 - Rev 0
                      prepared by PTG Consulting) must be updated when the demolition of the existing structures
                      on the site has been completed. The report must be based upon additional investigations to
                      meet Queensland Acid Sulfate Soils Technical Manual (QASSTM) requirements. The
                      amended report must be submitted to Council at least 5 business days prior to the pre-start
                      meeting.
               4.     A site control and/or compliance bond of $10,000 is to be submitted to Council prior to the
                      pre-start meeting. The bond is to secure performance of all conditions of this approval, prior
                      to the pre-start meeting. The cash bond or trading bank guarantee will be returned on
                      performance of the conditions of approval less any costs incurred by Council in respect of
                      enforcing performance of this permit. Council reserves the right to call upon the bond or
                      guaranteed sum to effect compliance with conditions.
               PRIOR TO COMMENCEMENT OF WORKS
                      Engineering
               5.     All necessary approvals from external service providers (eg Unitywater) and external parties
                      on which the development works are proposed have been obtained and a copy supplied to
                      Council.
               6.     Copies of the approved plans, duly signed by the consultant Registered Professional
                      Engineer of Queensland (RPEQ) must be provided to Council’s Engineering Officer
                      Construction at the “pre start” meeting.
               7.     A condition report including photographs of the frontage of the site must be completed and
                      submitted to Council at the prestart meeting / prior to any works commencing.
               8.     Certificates demonstrating currency of public liability insurance and works insurance covering
                      the works must be submitted to Council prior to the prestart meeting.
               9.     Council must be contacted at least 5 working days prior to any works commencing to
                      organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
                      pre-start meeting must include the relevant parties for the following aspects of the works:
                      a.      Civil engineering works;
                      b.      Erosion and sediment control works;
                      c.      Other relevant parties
               10.    A Construction Management Plan must be submitted to Council prior to the pre-start meeting
                      and must specifically address the following:
                      a.      Traffic Management during all aspects of the construct phase including:


                                                                                                        Page 2 of 9
Document Set ID: 23264906
Version: 4, Version Date: 30/09/2024

Used in these records

About this file

File size
160 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Approved Decision Notice - OPW24_0098 - [AS PUBLISHED].pdf · 160 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.