LANDSCAPE GENERAL NOTES: Generally soil to be used shall comply with AS 4419 and the contractor should ensure it complies
with the following specification:
1. Friable and free drainage.
THE CONTRACTORS SHALL: 2. Good texture and structure for selected use.
Remove all un-wanted debris/material from site. 3. Acceptable conductivity and ph. levels for intended plant species to be planted.
Confirm all dimensions in site prior to construction. MULCH:
Seek instruction from superintendent where level discrepancies and poor soil structure occurs. All mulch proposed to be used on site shall be free of foreign matter including anthrpogenic
waste, rock, soil, sediment, contamination, weeds and sticks.
SERVICES:
Planted areas should be mulched to a minimum 100mm deep to ensure site water conversation
The contractor shall confirm the location of all services with relevant authorities prior to planting requirements are achieved as specified.
and excavating.
GENERAL:
All trees must be planted a min. of 1000mm from underground services.
For more detail regarding architecture or engineers refer to the projects Architect and Engineers
All trees must be planted 4 m from overhead street lights. drawings.
DRAINAGE: Planting shown reflects the design intent, exact numbers and locations will require confirmation
Install sub-soil drains as required and where garden abuts building and connect into stormwater. on site by the superintendent.
Sub-soil drains to be 100mm slotted ag pipe covered with filter fabric and shall be surrounded Any changes to be made to the landscape plan must be approved by the landscape architect
with a minimum 100mm or 25mm diameter drainage gravel. and superintendent.
Ensure drainage works correlate with adjacent land and specified finished levels. All planting layouts are to be approved by the landscape architect on site prior to planting.
GENERAL PLANTING: All structures are to be approved by the appropriate government departments prior to any
construction taking place.
Plant stock is to be approved by landscape contractor and qualified aborist prior to
acceptance of delivery. All landscape plans presented assume that all base and survey information is accurate and to
scale. The contractor shall check landscape plans presented for any discrepancies with the
Mulch bed areas should not exceed a 1:3 grade; where slopes are more than 1:3, install
existing site conditions or other dwelling presented prior to any construction work taking place. If
biodegradable jute matt. Where slopes are greater than 1:2 install jute mesh product to
discrepancies do occur these shall be highlighted at once to the superintendent prior to any
manufacturers specification.
construction work taking place.
Install specified topsoil and crown bed at centre with 1 inch Hoop Mulch as specified.
IRRIGATION:
All plantings shall incorporate the inclusion of a slow release native plant fertiliser (as per
These landscape plans assume all landscapes areas will be irrigated automatically to
manufacturers specification) and the use of soil moisture retention additive (as per
appropriate standards and installed by a suitably qualified person and have a minimum 12
manufactures specification), placed adjacent to the plant root ball at the time of planting.
month warranty.
Trees are to be certified by a qualified aborist as natspec compliant prior to delivery to site.
MAINTENANCE:
Qualified aborist to select natspec compliant trees at nursery and check delivery to site.
It is recommended that the whole landscape is maintained. This will be quoted on separately.
Maintenance is recommended fortnightly basis for the first 13-14 weeks.
TOPSOIL:
Irrigation and watering:
All imported topsoil to comply with AS 4419.
Daily for 3 weeks, every 2-3 days thereafter.
Where site soil is to be used as topsoil, ameliorate site soil as specified by the soil testing
laboratory. All soil stockpiles are to be maintained to control weeds routinely and guard against irrigation system is installed which by the garden can be watered automatically for 30 mins per
dispersion by wind or water. Stockpiles shall be limited to a maximum height of 2m and may day for watering or every second / third day.
require covering or retaining. Stockpiles are not permitted within close proximity to residential
Weed removal and wick wiping, as required to reduce competition and seeding.
properties.
Re- mulching, as required to maintain a consistent depth until plants are established.
outside a: 4 rene street, noosaville, qld 4566
p: 07 5448 0250
this drawing/design is subject to
copyright, with all
remaining to outside noosa.
these drawings should not be
rights Client:
Kim and Bob Monahan
date: 07/09/2015 designed by: JS + AL
w: www. outsidenoosa.com.au job no: drawn by: AL
landscape architects John: 0409 960 538
copied without permission.
+ horticultural specialists e: [email protected]
all contractors are to confirm
issue: A
measurements on site prior to
Client address: scale N/A @A3
noosa
Abi: 0411 138 269 construction or planting. the
Lot 27 Noosa Dunes
identification of existing services
e: [email protected] should also take place before sheet no 2 of 9 purpose: Concept
commencement of works.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.