Council archive · source document
Decision Letter - Change to an Existing Approval [As Published] - 132005.699.03
2005/699
2847-DA-16 01 GFA – Villas – Blackburne Jackson 04-04-08
Design
2847-DA-17 01 GFA – Level 1 & 2 – Blackburne 04-04-08
Jackson Design
2847-DA-18 01 GFA – Level 3 & 4 – Blackburne 04-04-08
Jackson Design
7 ADVISORY NOTES
The following Advisory Notes are for information purposes only and do not form conditions of
approval:
1. The applicant is informed that approval of this development application will trigger an
Infrastructure Charge in accordance with the Coastal Major Road Network Infrastructure
Charges Plan for the estimated amount of $71,637 and is subject to variations in the
Consumer Price Index, All Groups Brisbane from June 2005 until the date of payment. An
Infrastructure Charge Notice will be issued in accordance with Chapter 5 of the Integrated
Planning Act 1997.
2. The requirements of the Environmental Protection Amendment Regulation (No. 2) 1999 and
Local Law No. 12, prevents a builder or building contractor carrying out building work on a
building site in a way that makes or causes audible noise to be made from the building work:-
2.1. On a Sunday or public holiday, at any time; or
2.2. On a Saturday or a business day, before 7.00am or after 6.30pm.
A maximum penalty of $1,500 applies to an offence under this legislation.
3. We advise ‘interested parties’ i.e. ‘developer’, ‘owner’, ‘tenant’ to consider their responsibilities
under the Disability Discrimination Act (DDA) in regard to the installation of disabled access
and the provision of disabled facilities, and that access to this building and the provision of
sanitary facilities may need to comply with the requirements of Section D Part D3 and Section
F Clause F2.4 of the Building Code of Australia.
4. Pursuant to the Building and Construction Industry (Portable Long Service Leave) 1991 Act if
the cost of operational works exceeds $80,000, then a portable long service levy is required to
be paid. In accordance with Section 77.(1) of the Act, Council is required to sight the approved
form issued by the Building and Construction Industry (Portable Long Service Leave) Authority
that confirms that the requirements of the Act have been satisfied. A statutory declaration
outlining the cost of the operational works must be submitted to Council with the lodgement of
any application for operational works over the site.
5. Payment via credit card transaction will not be an acceptable method of payment for
development contributions conditioned in this permit or for infrastructure charge notices issued
separately.
9. In accordance with the Environmental Protection (Water) Policy 1997, all sand, silt, mud, paint,
cement, concrete, builders waste or rubbish shall not be permitted to enter or be placed where
it could reasonably be expected to move into a roadside gutter, stormwater drain or a water
course. On the spot fines apply for such offences.
Payment via credit card transaction will not be an acceptable method of payment for development
contributions conditioned in this permit or for infrastructure charge notices issued separately.
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
Page 12 of 16
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Letter - Change to an Existing Approval [As Published] - 132005.699.03Related documentApplication case desk ↗
About this file
- File size
- 86 KB (small file)
- File type
No other editions are linked here.