change reps - zauss
OPW PLANS – CONDITION 1
The landscape plans have been updated in accordance with MCU condition 23 for waste
management to include wheelie bins located behind the front fence. There is still ample
landscaping areas in front of the building and fence to screen the bulk of the building,
whilst providing for bin storage at the front of the site.
Please update condition 1 to include the following landscape plans:
Plan No. Rev Plan/Document Name Date
ED22266OPW - 01 F Site Layout Plan prepared by element design 21.11.23
ED22266OPW – 02 F Planting Plan (Ground Level) prepared by element design 21.11.23
ED22266OPW – 03 F Planting Plan (Level 04) prepared by element design 21.11.23
ED22266OPW – 04 F Details Plan prepared by element design 21.11.23
ED22266OP - 05 F Plant List & Specification Plan prepared by element 21.11.23
design
--------------------------------------------------------------------------------------------------------------------
If you have any further queries in relation to the above, please do not hesitate to contact
myself.
Regards,
Jack Lewis B.Sc Hons UNSW M.Plan Otago MPIA
Planner/Director
Pivotal Perspective Pty Ltd
0406 334 227
FM6002Q/1-01/07/2017 Page 3 of 3