LATE RFI - Revised SWMP
CONCLUSION
This Stormwater Management Report has outlined how the stormwater run-off from the site is to be managed to
comply with the relevant requirements and minimise any adverse impacts to the downstream catchments.
• Due to the low-density nature of the proposed subdivision and surrounding sites, and lack of downstream
infrastructure, the internal drainage will rely on grading surfaces to discharge run-off as overland sheet flows
from the lots.
• The site has been assessed against potential future development of the lots assuming a 40% impervious
area. Modelling of the pre and post developed peak site run-off has found that the overall increase to
impervious peak flows as a result of this level of development will not significantly alter conditions from their
existing level, and therefore attenuation is not considered necessary for the future dwellings.
• A table drain upstream of a proposed access road will be provided along the eastern and northern property
boundaries, to intercept upstream flows and run-off from the existing access easement and divert them
around the future allotments. The discharge of this run-off will be dispersed by employing level spreaders
along the western property boundary to ensure the stormwater from the site is discharged as sheet flow
across the boundary, minimising potential flow concentrations or scour to the downstream property.
• During construction, best practice erosion and sediment control measures are to be implemented to
minimise potential contaminants impacting the downstream receiving environment achieving the objectives
of Appendix 2 of the SPP. An erosion and sediment control plan shall be developed as part of a submission
for Operational Works approvals.
• The proposed stormwater solution manages resolves a number of existing drainage issues within the site,
and the development will not result in significant impacts to water quality or quantity, and is therefore
considered to meet the Water Quality and Drainage objectives of the Noosa Plan.
Project number 20220217
Page 13 of 16
File 20220217 Pavilion St SWMP Rev1.docx, 2023-04-19 Revision 1
P +61 7 5211 1003 A 75 Noosa Drive, Noosa Heads,Qld 4567 E [email protected] recorconsulting.com
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.