Stormwater Management Plan - Rev 1

of 93

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (12.7 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
Water Quality and Drainage Code
Noosa Council Plan July 2020
Performance and Acceptable Outcomes Table
Version: 2020

Performance Outcomes                                      Acceptable Outcomes                                    Solution1                       Comments                                    Council Use


                                                          Editor's Note— PSP6 Engineering Design
                                                          Standards - Roads, drainage and earthworks
                                                          provides guidance on prepare a groundwater
                                                          recharge and discharge plan.
Construction and establishment of stormwater management systems
PO14                                                      AO14.1                                                                RO14.1
Construction methods provide for appropriate              An erosion and sediment control plan                                  An Erosion and Sedimentation Control
controls to avoid entry and transport of litter,          prepared in accordance with the International                         Plan shall be prepared (prior to
sediment, and associated prescribed water                 Erosion Control Association Best Practice                             commencement of construction) and
contaminants into receiving waters.                       Books demonstrates that the capture and                               maintained for the management of the
                                                          release of stormwater achieves the design                             sediment laden stormwater during the
Editor's note— Water contaminants are                     objectives listed in Table A: Construction                            construction phase in accordance with
prescribed in the                                         phase – stormwater management design                                 IECAs Best Practice guidelines.
Environmental Protection Act 1994                         objectives of the State Planning Policy
                                                          (Appendix 2).

                                                           Editor’s note— PSP6 Engineering Design
                                                           Standards - Roads, drainage and earthworks
                                                           provides guidance on requirements for
                                                           preparing an Erosion Management Plan.
                                                           AO14.2                                                               RO14.2
                                                           Construction works are designed and                                  Unnecessary disturbance to soil shall be
                                                           managed to restrict the extent of clearing and                       avoided and all soil surfaces shall remain
                                                           soil exposure to the minimum necessary for                          stabilized.
                                                           access, and safe construction at any one
                                                           time
                                                           AO14.3                                                               RO14.3
                                                           For buildings:                                                       The proposal complies. Refer to RO14.1.
                                                          (a) upstream runoff is diverted around the
                                                                construction site;
                                                          (b) sediment barriers are provided                         
                                                                downslope of disturbed areas to prevent
                                                                sediment washing into gutters, drains
                                                                and waterways , wetlands or drainage

1
    Solution:          Acceptable Solution                                                                                                                                                          Page 8 of 10
                A/S     Alternative Solution              D:\JOBS\20-Jobs\20169 - 101 & 105 Eumundi Noosa Road, Noosaville\Civil\Reports\SBSMP\Working\Appendices\20169 - NSC Water Quality and Drainage Code 2020.docx
                N/A     Not applicable to this proposal                                                                                                                                                      Job: 20169
                                                                                                                                                                                                            Rev:      0
Site Address: 101-105 Eumundi Noosa Road, Noosaville                                                                                                                                                    30/11/2020
Log in to download the original file

Stormwater Management Plan - Rev 1.pdf · 12.7 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.