Noosa Shire Council
Adopted Infrastructure Charges Resolution (No. 1) 2014
Column 1 Column 2 Column 3 Column 4 Column 5
Use under an applicable local planning Development Unit of measure Adopted charge Adopted charge
instrument class for transport, for stormwater
public parks and network ($ per m2
land for of impervious
Use class Defined use community area)
facilities, water
supply and
sewerage
networks ($ per
unit of measure)
government determines should apply for the
use at the time of assessment
Service & utility - Type
Minor uses Nil Nil Nil
3 Tower
the charge (in column 4) for the charge
Service & utility - Type
category (in columns 1 & 2) that the local
4 Treatment, recycling Special uses $10
government determines should apply for the
& disposal; use at the time of assessment
the charge (in column 4) for the charge
Transport - Type 1 category (in columns 1 & 2) that the local
Special uses $10
Passenger terminal government determines should apply for the
use at the time of assessment
the charge (in column 4) for the charge
Transport - Type 2 category (in columns 1 & 2) that the local
Special uses $10
Carpark government determines should apply for the
Infrastructure use at the time of assessment
Transport - Type 3
Industry m2 GFA $50 $10
Depot
the charge (in column 4) for the charge
Transport - Type 4 category (in columns 1 & 2) that the local
Special uses $10
Aeronautical government determines should apply for the
use at the time of assessment
Note:
(1) Where connection to the water supply or sewerage networks is not provided, Table 13.1 Column 4 adopted charges is
reduced by 20% for each network not provided
(2) Sport and recreation uses are exempt from “Public Parks and Land for Community Facilities” network proportion of
the adopted charge.
(3) For Retirement and residential care developments, the net charge payable for Council “Transport” and “Public Parks
and Land for Community Facilities” networks is reduced to 70% of the standard calculated charge apportioned to
those networks.
(4) Development that is for provision of “trunk” infrastructure is exempt from and not subject to payment of
infrastructure charges.
Council Resolution dated 6 February 2014
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.