9.4.2            Earthworks Code

9.4.2.1          Application
(1)   This code applies to assessable development identified as requiring assessment against the Earthworks code by the tables of
      assessment in Part 5 (Tables of Assessment).
(2)   All provisions in this code are assessment benchmarks for applicable assessable development.

9.4.2.2          Purpose and Overall Outcomes
(1)   The purpose of the Earthworks code is to ensure earthworks do not unreasonably impact on the natural environment or
      other properties and provide a safe and secure work environment.
(2)   The overall outcomes sought for the Earthworks code are:
      (a)   Earthworks are designed and constructed to be structurally sound.
      (b)   All onsite works provide land stability (including differential settlement or expansion in reactive soils).
      (c)   Earthworks avoid contamination of land.
      (d)   Flooding and drainage are appropriately addressed.
      (e)   Groundwater, watercourses and wetlands are protected.
      (f)   The loss of native remnant or regrowth vegetation is avoided.




Table 9.4.2.3 ­ Criteria for assessment

Effects of works         Table 9.4.2.3 Criteria for assessment (part)
Performance outcomes                                               Acceptable Outcomes
Assessable Development

Effects of works
Drainage
PO1                                                                AO1
Finished surface levels ensure land is free draining.              Filled or excavated areas have a minimum gradient of 0.5%
                                                                   and drain to Council’s stormwater infrastructure where
                                                                   available, or where stormwater infrastructure is not available,
                                                                   toward the street.
                                                                                            Able to comply by sending water to
Hydraulics                                                                                  waterway (legal point of discharge)
PO2
Change to the levels on site do not have an adverse impact on No acceptable outcome provided
the flooding and drainage characteristics off­site.                                  No Acceptable Outcome Applicable
Geotechnical considerations
PO3                                                                AO3.1
Earthworks do not result in geotechnical instability on­site or    Filling works are undertaken in accordance with Council’s
to nearby premises.                                                Planning Scheme Policy PSP6 Engineering design standards
                                                                   ­ roads, drainage and earthworks.
                                                                                          Able to comply
                                                                   AO3.2
                                                                   Where the filling is for residential, commercial or industrial
                                                                   purposes the works comply with Australian Standard ­
                                                                   Guidelines for earthworks on commercial & residential
                                                                                            Able to comply

                                             NOOSA PLAN 2020 ­ AMENDED AT 25 SEPTEMBER 2020                                  Page 1 of 3
Log in to download the original file

earthworks code assessment.pdf · 1.4 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 2 pages

Page 2

Performance outcomes                                               Acceptable Outcomes
                                                                   development.
Local amenity
PO4                                                                AO4.1
Undertaking earthworks does not adversely impact on the            The following control measures are implemented—
amenity of the local area by way of dust, noise or visual          (a)   regular water spraying of exposed areas to suppress
amenity.                                                                 dust;
                                                                   (b)   provision of dust stabilised or sealed internal roads;
                                                                   (c)   protective covering of exposed areas that are left for
                                                                         more than 2 weeks; and
                                                                   (d)   unless a development permit provides otherwise,
                                                                         disturbed areas are revegetated using species identified
                                                                         in Council's Planning Scheme Policy PSP2
                                                                         Landscaping.
                                                                                                  Able to comply
                                                                   AO4.2
                                                                   Earthworks are undertaken only during the hours of 7:00am to
                                                                   6:00pm, Monday to Friday and 7:00am to 3:00pm on
                                                                   Saturday. No work is undertaken on Sunday or public
                                                                   holidays.                     Able to comply

Vegetative waste
PO5                                                                AO5.1
Vegetation cleared from a development site is disposed of in       Cleared vegetation is transported off­site for disposal in an
an environmentally responsible manner.                             approved green waste disposal facility.
                                                                                                       No vegetation to
                                                                   AO5.2                               be removed
                                                                   Cleared vegetation is mulched on­site and reused for
                                                                   landscaping of the finished development.

                                                                   AO5.3
                                                                   Cleared vegetation is disposed of for the purpose of firewood.

                                                                   AO5.4
                                                                   Disposal of vegetative waste by burning off is avoided.
Managing contamination risk
PO6                                                                AO6.1
Materials used as fill are suitable for development and future     Fill material is solid clean earth, free of putrescible or refuse
use of the land and filling or excavation works do not result in   material, vegetation, acid sulfate soils, building or construction
the contamination of land.                                         material or other material or contaminants.
                                                                                                 Able to comply
                                                                   AO6.2
                                                                   The site is not on the contaminated land register. Not on the CLR
Haulage activity and amenity
PO7
Haulage of material to and from a site ensures—                    No acceptable outcome provided
(a)   minimal disturbance to neighbouring properties and
      properties along the haulage route; and                                              No Acceptable Outcome Applicable
(b)   Council’s road infrastructure including pavements is not
      adversely affected.



                                             NOOSA PLAN 2020 ­ AMENDED AT 25 SEPTEMBER 2020                                   Page 2 of 3

Page 3

Performance outcomes                                               Acceptable Outcomes
Extent of earthworks
PO8                                                                AO8
The layout of the development provides adequate, clearly           All earthworks, including cut and fill batters, retaining walls
defined and easily accessible—                                     and the like are contained within the subject site.
(a)   on­site vehicle parking and manoeuvring areas; and                                      Able to comply
(b)   loading and manoeuvring areas for delivery and service
      vehicles.


Sloping sites
PO9                                                                AO9
On sloping sites development follows the natural landform          Cut or fill is less than 1.5 metres in depth relative to the
wherever practical and excavation or filling is minimal.           natural ground level.           Able to comply

Infrastructure protection
PO10
Earthworks and vehicular access do not adversely impact on the     No acceptable outcome provided
capacity, operations and maintenance of existing infrastructure.                           No Acceptable Outcome Applicable

Environmental protection
PO11
Earthworks minimise any adverse impact upon groundwater,       No acceptable outcome provided
watercourses, drainage lines, wetlands, and native vegetation.                     No Acceptable Outcome Applicable

Dams
PO12                                                               AO12.1
Dam location and construction does not impact upon                 Where the site is in the Rural zone—
neighbouring properties or road reserves, in terms of—             (a)   the land has a slope of less than 25% (1:4);
(a)   hydrology;                                                   (b)   the earthworks including cut and fill batters and retaining
(b)   alteration of existing overland flow paths and patterns;           walls are setback a minimum of 50 metres from the
(c)   landslide or failure of dam wall; and                              property boundary; and

(d)   effluent disposal areas.                                     (c)   the size of the lot is greater than 5 hectares.

                                                                   AO12.2
                                                                   Where the site is in the Rural residential zone or the Rural
                                                                   zone and the lot is less than 5 hectares:
                                                                   (a)   the land has a slope of less than 1:6;
                                                                   (b)   the earthworks including cut and fill batters and retaining
                                                                         walls are setback a minimum of 20 metres from the
                                                                         property boundary; and
                                                                   (c)   the dam work involves less than 500m³ of material.
                                                      Not Applicable as not for a dam - Furthermore the site is 2.8ha, slope is flat,
                                                      there will beAO12.3
                                                                    no fill batters associated with 100mm of fill over 1000m2.
                                                                   For all other zones—
                                                                   No acceptable outcome provided




                                              NOOSA PLAN 2020 ­ AMENDED AT 25 SEPTEMBER 2020                                      Page 3 of 3

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.