                              ii.      Licensed Surveyor in regard to the cadastral and locational information, levels
                                       and applicable survey datum.
                      d.      The data must be in accordance with Council’s “Planning Scheme Policy 6 –
                              Engineering Design Standards”, and fully detail the levels for all engineering works
                              including but not limited to the drainage network and structures, finished ground and
                              pavement surface levels.
                      e.      Landscaping, including all assets and improvements within parks, open space and road
                              reserves areas are to be shown on an accompanying separate landscape plan
                              (prepared in .dwg file format with accompanying hardcopy PDFs) and include a
                              complaint ADAC XML file. Details of the landscaping and all associated assets and
                              improvements may be included in the ADAC XML digital file prepared for associated
                              civil infrastructure, or alternatively, be provided as a separate ADAC XML digital file
                              containing landscape and asset information only.
                      On Maintenance
               37.    All municipal works must be accepted ‘On Maintenance’ by Council in accordance with
                      Council’s relevant Planning Scheme Policy prior to the commencement of the use. To
                      achieve ‘On Maintenance’, the supervising RPEQ must submit to Council:
                      a.      certification that all works have been undertaken and completed in accordance with the
                              requirements of this Permit;
                      b.      as Constructed details in accordance with Council’s Planning Scheme Policy; and
                      c.      maintenance and operational manuals for all proprietary or site specific devices.
                      Off Maintenance
               38.    Prior to requesting an Off Maintenance inspection the developer must provide a written
                      request for the Off Maintenance inspection.
               39.    A re-inspection fee in accordance with Council’s Fees and Charge Register will be charged
                      where:
                      a.      a Council inspection reveals works do not comply with approval requirements; or
                      b.      submitted certification falsely states works comply with approval requirements.
               40.    A final inspection and approval of the new driveway and completed reinstatement works by
                      Council’s Inspector is required. Please contact Council on 5329 6500 to arrange for the
                      inspection.
               5.     REFERRAL AGENCIES

               Not applicable.
               6.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
                      General Advisory Notes
               1.     As this driveway is a private structure, the owner bears full responsibly for the standard of its
                      construction, maintenance and any liabilities associated with its construction. It is
                      recommended that professional advice be sought for the construction of the driveway to
                      ensure that the driveway is constructed in accordance with standard drawings RS-049, RS-
                      050 and any associated addendum.
               2.     Council has undertaken an audit check of the Operational Works drawings in relations to the
                      proposed works. A detailed check of the calculations and drawings has not been undertaken,
                      as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of
                      the engineering design. Council reserves the right to require further amendments and/or
                      additions at a later date should design errors become apparent.


                                                                                                        Page 7 of 10
Document Set ID: 22604431
Version: 3, Version Date: 03/10/2023

Used in these records

About this file

File size
163 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice OPW23 0120.pdf · 163 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.